# Production planning and control: functions, MRP, capacity and a worked example

> What production planning and control covers, how each function works on a real shop floor, how MRP and capacity fit in, and a worked week-by-week example with machine hours.

Page: https://www.emplotec.com/guides/production-planning-and-control · Updated: 2026-11-06

Published: 2026-11-06 · Modified: 2026-11-06 · 13 minute read · Market: India

## What is production planning and control?

Production planning and control (PPC) decides what the plant will make, on which machine, in what order and by when, and then checks every day that the plan is being followed. Planning happens before the work starts: it fixes the route, the quantities, the start and finish dates and the material. Control happens while the work runs: it releases jobs to the floor, records progress and corrects the plan when a machine stops, material is late or a rush order arrives.

In most Indian plants PPC sits between sales and the shop floor. Sales gives a promise date to the customer; PPC turns that order into work orders and a machine schedule; production runs it; stores and purchase supply the material. When PPC is weak, the symptoms are familiar: promise dates that slip without warning, a few machines always overloaded while others wait, material bought in a panic, and expediters walking the floor with a list of urgent jobs.

|  | Planning | Control |
| --- | --- | --- |
| Question | What should we make, where and when? | Is it happening, and what do we change if it isn't? |
| Time | Before the work is released | While the work runs |
| Main outputs | Master schedule, routings, MRP, machine schedule | Released job cards, progress, delay reasons, replans |
| Owned by | PPC or planning cell | PPC with shift supervisors |

The objectives are the same in every plant: deliver on the date promised, keep the bottleneck machines busy on the right work, hold as little inventory and work in progress as the plan allows, and give the floor a schedule it can actually keep.

## The functions of PPC: routing, scheduling, loading, dispatching and follow-up

Textbooks list the functions of production planning and control in a fixed order. The order matters because each step uses the output of the one before it.

| Function | What it decides | Document it produces | Example |
| --- | --- | --- | --- |
| Routing | The sequence of operations and the work centre for each | Routing (process sheet) | Housing GH-220: turning, VMC milling, drilling and tapping, washing, final inspection |
| Scheduling | When each operation starts and finishes | Master schedule, operation schedule | Turning on 16 and 17 November, milling 17 to 19 November |
| Loading | How many hours each machine carries, against what it can do | Machine load chart | VMC cell at 136 of 144 hours in week 47 |
| Dispatching | Releasing the job to the floor with what it needs | Job card, material issue slip, drawing, tool list | Job card JC-7712 released with 300 castings and program O2201 |
| Follow-up (expediting) | Checking progress and removing delays | Progress report, delay log | VMC-2 down for 16 hours; 2 jobs moved |

Some books add two more: inspection, which confirms the work meets the drawing before the next operation, and corrective action, which feeds what went wrong back into the next plan (a wrong cycle time in the routing, a supplier who is always late).

> Note: Routing errors are the most expensive kind. If the cycle time in the routing is 6 minutes and the machine really takes 9, every schedule built on it is wrong by a third, and nobody notices until the orders are late.

## How MRP fits into production planning

Material requirements planning (MRP) answers the material half of the plan. It takes the master production schedule (what finished items are needed, in what quantity, by when), explodes each item through its bill of materials, subtracts what is in stock and already on order, and offsets the rest by the lead time. The result is a list of planned purchase orders and planned work orders with dates.

1. Gross requirement: the quantity the schedule needs, plus the scrap allowance in the BOM.
2. Less stock on hand that is free (not reserved for another order, not on QC hold).
3. Less open purchase orders and work orders due before the need date.
4. Net requirement: what is left. Round it to the order multiple or minimum order quantity.
5. Offset by lead time: the order must be released that many days before the need date.

**MRP for the rough casting of housing GH-220 (example)**

| Line | Quantity | How it is worked out |
| --- | --- | --- |
| Order for GH-220 housings | 600 | Customer schedule, dispatch 27 November |
| Gross requirement for castings | 612 | 600 plus 2% scrap allowance in the BOM |
| Free stock on hand | 180 | After 40 reserved for another order |
| Open PO due 13 November | 200 | Sahyadri Precision Castings, PO-3318 |
| Net requirement | 232 | 612 less 180 less 200 |
| Planned order | 250 | Rounded up to the supplier's lot of 50 |
| Release by | 10 November | Need date 24 November less 2 weeks lead time |

Classic MRP assumes the plant has unlimited capacity. It tells you that 600 housings must be milled in week 47; it does not tell you whether the VMC cell has the hours. That is why MRP must be followed by a capacity check, and why a material plan that looks clean can still produce late orders.

## Capacity planning: infinite and finite loading

Capacity is the number of productive hours a work centre can give in a period. Work it out from the shop's own numbers, not the brochure:

> Capacity (hours a week) = machines × shifts × hours per shift × working days × efficiency

Efficiency here covers breakdowns, setups not in the routing, short shifts and the minutes lost at shift change. If you track OEE, the availability and performance figures are a good starting point. For a VMC cell of 2 machines on 2 shifts of 7.5 hours, 6 days a week, at 80%: 2 × 2 × 7.5 × 6 × 0.8 = 144 hours a week.

| Level | Checks | Horizon | Typical tool |
| --- | --- | --- | --- |
| Resource requirement planning | Can the plant and its key lines carry the year's plan? | 6 to 18 months | Annual budget, capex plan |
| Rough-cut capacity planning | Can the bottleneck work centres carry the master schedule? | 4 to 12 weeks | Load per bottleneck per week |
| Capacity requirements planning | Hours per work centre per week from every planned and released order | 1 to 6 weeks | Load chart after MRP |
| Finite scheduling | Exact sequence per machine, never above capacity | Days to 2 weeks | Scheduling board |

Infinite loading stacks every job on the date it is wanted and shows where the load goes over capacity, leaving the planner to fix it. Finite loading never puts more on a machine than it can do: it pushes the job to the next free slot and shows the date that results. Infinite loading is honest about demand; finite loading is honest about dates. A good PPC cell looks at both: the infinite view to see where capacity must be added, the finite view to promise and dispatch.

## PPC in a job shop, a batch shop and a line

The functions are the same everywhere, but their weight changes with the type of production. A plant often has more than one type: a machine shop that works as a job shop feeding an assembly line.

|  | Job shop | Batch production | Line (flow) production |
| --- | --- | --- | --- |
| Example | Toolroom, fabrication to drawing, general engineering | Machined components in lots, forgings, castings | Two-wheeler assembly, packaging line, continuous wire drawing |
| Routing | New for many orders; written by the planner | Standard per part, reused | Fixed by the line itself |
| Scheduling | Operation by operation, priority rules, many changes | Lot sizes and sequence to save setups | Rate per hour or shift, model mix |
| Loading | Critical: every job competes for the same machines | Important at bottleneck centres | Balanced once, when the line is designed |
| Dispatching | Job cards per operation, daily priorities | Job card per lot, with material | Daily production plan to the line |
| Follow-up | Heavy expediting, queue at each machine | Lot tracking and WIP between operations | Output per hour against target, stoppages |
| Main risk | Long queues and unknown lead times | Large lots that block the bottleneck | One stoppage stops everything |

In a job shop the planner spends most time on sequencing and on promise dates for new enquiries. In a batch shop the big levers are lot size and setup reduction, because every setup on a bottleneck is capacity lost. On a line the plan is mostly a rate and a model mix, and control is about stoppages, material at the line side and changeovers between models.

## A worked example: one order through PPC

Nordwerk Components (an example company) machines gearbox housings at its Sriperumbudur plant. On Monday 9 November an OEM confirms 600 housings GH-220 for dispatch on Friday 27 November (week 48). The routing and the plant's capacity are below.

| Op | Operation | Work centre | Setup | Run time per piece | Hours for 600 |
| --- | --- | --- | --- | --- | --- |
| 10 | Turning | CNC-L2 (1 lathe) | 45 min | 4 min | 41 |
| 20 | Milling | VMC cell (2 machines) | 60 min per lot | 9 min | 92 (2 lots) |
| 30 | Drilling and tapping | DRL-1 | 20 min | 3 min | 31 |
| 40 | Washing, final inspection | QC | nil | 1.5 min | 15 |

| Work centre | Capacity a week | Week 46 load | Week 47 load | Week 48 load |
| --- | --- | --- | --- | --- |
| CNC-L2 (1 × 2 shifts × 7.5 h × 6 days × 80%) | 72 h | 30 + 41 = 71 h | 40 h | 25 h |
| VMC cell (2 × 2 × 7.5 × 6 × 80%) | 144 h | 90 + 46 = 136 h | 96 + 46 = 142 h | 60 h |
| DRL-1 (1 × 1 × 7.5 × 6 × 80%) | 36 h | 20 h | 18 + 15.5 = 33.5 h | 10 + 15.5 = 25.5 h |

1. Routing and MRP: the castings are planned as in the MRP table above, so 250 more are ordered on 10 November.
2. Scheduling: the order is split into two lots of 300, so milling can start on the first lot while the second is still on the lathe. This transfer batch cuts the order's lead time by about a week.
3. Loading: all 600 are turned in week 46 (71 of 72 hours). Lot A is milled in week 46 and lot B in week 47, which leaves the VMC cell at 142 of 144 hours. Drilling follows one week behind milling.
4. Dispatching: job cards for lot A go to the floor on 10 November with 300 castings issued, the drawing at revision C and the VMC program.
5. Follow-up: on Wednesday of week 47, VMC-2 breaks down and loses 16 hours. The cell's week-47 capacity drops to 128 hours against a load of 142, an overload of 14 hours.
6. Replan: the planner looks for the lowest-priority job on the VMC cell that week. A stock replenishment order PR-118 (14 hours, needed in week 50) moves to week 48, where the cell carries only 60 hours. GH-220 keeps its dispatch date and nothing else becomes late.

> Note: The alternatives were Sunday overtime (cost, and operators already on 2 shifts) or splitting lot B (a second setup, another hour lost). Moving a job with slack is usually the cheapest fix, but only if the planner can see every order's slack at once.

## KPIs for production planning and control

Measure the plan and the plant separately. A plant can run its machines hard and still deliver late if it is making the wrong things.

| KPI | Formula | What it tells you |
| --- | --- | --- |
| On-time in full (OTIF) | Order lines delivered on the promised date and in full ÷ order lines due | Whether customers get what was promised |
| Schedule adherence | Work orders finished in the planned week ÷ work orders planned for that week | Whether the floor can keep the plan |
| Capacity utilisation | Load hours ÷ available hours, per work centre | Where the bottleneck is and how close to full it runs |
| OEE | Availability × performance × quality | How much of the planned time turns into good parts |
| Manufacturing lead time | Days from work order release to completion | How long the floor really takes; feeds promise dates |
| WIP in days | Value of work in progress ÷ average daily cost of production | How much is stuck between operations |
| Shortages at release | Work orders released without all material ÷ work orders released | Whether MRP and purchase are in step |
| Plan changes in the frozen zone | Changes to the next week's schedule after it is frozen | How stable the plan is; high numbers mean firefighting |

Review the delay reasons behind the numbers every week: machine breakdown, material late, quality hold, operator absent, program not ready. Five or six reasons usually explain most of the delays, and each has an owner outside PPC.

## Common PPC problems and how to fix them

- Promise dates given without a capacity check. Fix: sales asks PPC, or the system, for a date from the actual load on the bottleneck.
- Routings with wrong cycle times. Fix: compare job card times with the routing every month and correct the worst ten.
- A plan that changes every day. Fix: freeze the next 3 to 5 days, and allow changes inside the frozen zone only with the plant head's approval.
- Jobs released without material. Fix: check material availability before a job card is released, not after it reaches the machine.
- Big lots on the bottleneck. Fix: split into transfer batches and cut setup time on the bottleneck first.
- Progress known only at the end of the shift. Fix: record start, stop and quantity at the machine, on a kiosk or a phone, as the work happens.
- The schedule lives in one planner's Excel. Fix: one shared board everyone reads, so stores, quality and maintenance plan from the same dates.

## How to set up PPC in a plant, step by step

1. List the work centres and measure their real capacity for a month: available hours, breakdowns, setups.
2. Find the bottleneck: the work centre with the highest load against capacity most weeks. Plan it first and everything else around it.
3. Clean the masters: one BOM per item with its revision, one routing per item with checked cycle times.
4. Build a master schedule from confirmed orders and forecasts for the next 8 to 12 weeks.
5. Run MRP weekly, and act on its planned orders the same day.
6. Load the bottleneck finitely, and set the frozen zone.
7. Release job cards only when material, drawings, tools and programs are ready.
8. Record progress at the machine, review delays daily, and replan the moment something stops.
9. Review the KPIs and delay reasons weekly with production, stores, purchase, quality and maintenance.

## Or let the schedule replan itself when a machine stops.

In Emplotec Manufacturing, MRP and a finite-capacity schedule check every order against your machines, and replan the moment a machine stops or a rush order lands.

- Routings, workstations and capacities sit with each BOM, so every work order is loaded against real hours.
- The scheduling board re-sequences on progress, breakdowns and rush orders, and what-if MRP shows a change against the live plan before anything is committed.
- Job cards on the shop-floor kiosk record progress as it happens, and OEE and downtime come from the same entries.
- Job costing puts planned against actual for material, labour, machine and overhead on every order.

Read more: [Emplotec Manufacturing](https://www.emplotec.com/erp/manufacturing.md)

## Questions and answers

### What are the main functions of production planning and control?

Routing (the sequence of operations), scheduling (when each starts and finishes), loading (hours on each machine against capacity), dispatching (releasing jobs with what they need) and follow-up (checking progress and removing delays). Many books add inspection and corrective action.

### What is the difference between production planning and production control?

Planning decides what to make, where and when before work starts. Control releases the work, tracks it against the plan and corrects the plan when something goes wrong.

### Is MRP the same as production planning?

No. MRP plans the material: what to buy or make, how much and when. Production planning also covers routings, capacity, sequencing and dispatch, and MRP alone assumes the machines have unlimited hours.

### What is the difference between loading and scheduling?

Loading assigns hours of work to a machine or work centre for a period and compares them with capacity. Scheduling fixes the start and finish time of each operation, in sequence, on that machine.

### Which KPIs should a PPC department track?

On-time in full delivery, schedule adherence, capacity utilisation at the bottleneck, OEE, manufacturing lead time, WIP in days and shortages at job release. Review the delay reasons behind them every week.

### How is PPC different in a job shop and in line production?

A job shop plans operation by operation, with loading and sequencing as the hard part and heavy follow-up. A line is balanced once and planned as a rate and model mix, with control focused on stoppages and material at the line.

## Sources

- [NPTEL: Production and Operation Management, IIT Roorkee](https://nptel.ac.in/courses/110107141)
- [ASCM (APICS) dictionary: MRP, capacity requirements planning, finite loading](https://www.ascm.org/learning-development/certifications-credentials/dictionary/)

## Related

- [/erp/manufacturing](https://www.emplotec.com/erp/manufacturing.md)
- [/templates/costing-sheet-format](https://www.emplotec.com/templates/costing-sheet-format.md)
- [/templates/control-plan-format](https://www.emplotec.com/templates/control-plan-format.md)
- [/guides/mis-report](https://www.emplotec.com/guides/mis-report.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All guides: https://www.emplotec.com/guides.md
- /erp/manufacturing: https://www.emplotec.com/erp/manufacturing.md
- /templates/costing-sheet-format: https://www.emplotec.com/templates/costing-sheet-format.md
- /templates/control-plan-format: https://www.emplotec.com/templates/control-plan-format.md