# RA bill in construction: running account bills, deductions and a worked example

> How a running account bill moves from the measurement book to certification and payment, every deduction a contractor sees on it, and a fully worked RA bill with Indian numbers.

Page: https://www.emplotec.com/guides/ra-bill · Updated: 2026-11-06

Published: 2026-11-06 · Modified: 2026-11-06 · 11 minute read · Market: India

## What is an RA bill?

An RA bill (running account bill) is an interim bill a contractor raises for the work done so far on a contract, usually every month. It is called running because the account stays open: each bill shows the total work done up to date, subtracts what was paid on earlier bills, and claims only the difference. The last bill, raised after the work is complete and finally measured, is the final bill, which closes the account.

RA bills are how almost all building, infrastructure, MEP, interiors and industrial contracts in India are paid, by government departments (where the CPWD and state PWD manuals set the procedure) and by private clients. A main contractor raises RA bills on the client, and the same contractor certifies RA bills from its own subcontractors, so most contractors handle both sides every month.

|  | RA bill | Final bill |
| --- | --- | --- |
| When | Monthly or at an agreed stage, while work continues | Once, after completion and final measurement |
| Quantities | Measured or estimated up to date; may be adjusted later | Final measured quantities for every BOQ item |
| Nature of payment | Advance against the final bill (on account) | Final settlement of the contract |
| Deductions | Retention, advance recovery, TDS, GST TDS, cess, material recovery | Same, plus final adjustment of all earlier bills, extra and deviated items |
| After it | Next RA bill | Retention release after the defect liability period |

## How an RA bill is prepared: measurement, checking and certification

Every RA bill starts in the measurement book (MB). The site engineer or quantity surveyor records the work actually done against each BOQ item, with location, dimensions and the computed quantity, and the contractor's representative signs it as accepted. In government work the MB is a numbered, controlled book and the engineer-in-charge or a test-checking officer checks a share of the entries. In private work it is often an abstract sheet with joint measurement signatures, but the principle is the same: no measurement, no payment.

1. Joint measurement on site for the period, recorded item by item against the BOQ.
2. Abstract of cost: up-to-date quantity × BOQ rate for each item, the total of work done to date.
3. Add extra and substituted items only if they are approved (a variation order or extra item rate).
4. Add secured advance on materials brought to site, if the contract allows it.
5. Subtract the gross amount of all previous RA bills to get the value of this bill.
6. Apply the deductions and recoveries the contract and the law require.
7. Certification by the engineer-in-charge or the client's project manager, often with a quantity surveyor's check, then passing by accounts and payment.

> Warning: Most disputes on RA bills are not about rates. They are about quantities measured without the other side present, extra items executed without written approval, and recoveries the contractor did not expect. Keep every MB page, approval and drawing revision the bill relies on.

## What an RA bill must show

| Part | What it contains |
| --- | --- |
| Header | Contractor and client with GSTINs, contract or work order number and date, name of work, bill number (RA-07), period of work, date of bill |
| Abstract | BOQ item, description, unit, contract quantity, rate, quantity up to previous bill, quantity this bill, quantity up to date, amount up to date |
| Extra items | Approved variations and extra items with their approval reference |
| Summary | Gross value up to date, less previous bills, value of this bill |
| Recoveries | Retention, mobilisation and machinery advance recovery, secured advance adjustment, materials issued free or at cost by the client, hire of client equipment, water and power |
| Statutory deductions | Income-tax TDS, GST TDS where the client is a government body, building workers' cess |
| GST | Taxable value and GST on the bill; tax invoice details |
| Net payable | Amount payable this bill, in figures and words |
| Certification | Measured by, checked by, certified by, with dates |

Our RA bill format has these columns with the totals already worked as formulas. Use it with the BOQ format so the item numbers and rates match line for line.

## Deductions on an RA bill

Contractual deductions come from the contract; statutory ones come from the law. Both are subtracted from the bill, but only the statutory ones are deposited with the government.

| Deduction | Typical rate | Basis | Notes |
| --- | --- | --- | --- |
| Retention (security deposit) | 5% to 10% of each bill, often capped at 5% of contract value | Contract | Released after completion and the defect liability period; often replaceable by a bank guarantee |
| Mobilisation advance recovery | Pro rata, so the advance is recovered by a set stage (often 80% to 90% of work) | Contract | Advance usually 5% to 10% of contract value against a bank guarantee; interest only if the contract says so |
| Secured advance adjustment | As the materials are used in the work | Contract | Advance on materials at site, recovered as they are consumed |
| Material issued by the client | Issue rate × quantity | Contract | Cement or steel issued free or at a fixed rate, reconciled against theoretical consumption |
| Income-tax TDS on contracts | 1% (individual or HUF), 2% (others) | Section 393(1), Income-tax Act 2025 (formerly section 194C) | On the bill value excluding GST when GST is shown separately; above ₹30,000 a bill or ₹1,00,000 a year |
| GST TDS | 2% (1% CGST + 1% SGST, or 2% IGST) | Section 51, CGST Act | Only when the client is a government department, local authority or notified body and the contract value exceeds ₹2.5 lakh |
| Building workers' cess | 1% of the cost of construction | Code on Social Security, 2020 (formerly the BOCW Welfare Cess Act, 1996) | Usually deducted at source by government clients; many private clients do the same |

> Note: From 1 April 2026 the Income-tax Act, 2025 replaced the 1961 Act. TDS on payments to contractors is now under section 393(1) (Table, serial 6(i)) in place of section 194C; the rates and thresholds carried over. TDS returns for payments after that date quote the new section.

## GST on RA bills

A construction contract that involves transfer of goods in the execution of work on immovable property is a works contract service under GST (heading 9954). After the rate changes of 22 September 2025 (Notification 15/2025-Central Tax (Rate)), most works contracts, including government works contracts and their subcontracts that earlier carried 12%, are taxed at 18%. A few specified entries carry other rates, so check the entry that applies to your contract before you bill.

- Time of supply: a construction contract is usually a continuous supply of services. The invoice is due on or before the due date of payment in the contract, or when the milestone the payment is linked to is completed (section 31(5), CGST Act).
- Value: GST is charged on the gross value of work in the bill. Retention and advance recovery are deductions from the amount payable, not from the taxable value, when the invoice is raised for the full certified value.
- Mobilisation advance: tax on an advance for services is due when the advance is received, and it is adjusted when the bills that recover it are raised.
- Free-issue material: if the client supplies cement or steel free and its value is not part of the consideration, check whether it must be added to the taxable value; the answer depends on the contract terms.
- Input tax credit: a contractor can claim credit on inputs used for a works contract service it supplies. The client cannot claim credit on works contract services for building its own immovable property, except plant and machinery.

## A worked RA bill

Sri Venkata Builders Pvt Ltd (an example company) is building a factory shed for a private client in Oragadam under a ₹4.2 crore contract. The contract provides 5% retention on each bill, a 10% mobilisation advance (₹42 lakh, paid against a bank guarantee) recovered at 12.5% of each bill, and 1% labour cess deducted by the client. This is RA bill 7, for October 2026.

**RA bill 7: abstract (amounts in rupees)**

| Item | Unit | Rate | Qty to previous | Qty this bill | Qty to date | Amount to date |
| --- | --- | --- | --- | --- | --- | --- |
| 2.1 PCC M15 in foundations | cum | 6,800 | 410 | 0 | 410 | 27,88,000 |
| 3.4 RCC M25 in columns and beams | cum | 9,450 | 690 | 185 | 875 | 82,68,750 |
| 4.2 Reinforcement steel, Fe 550D | MT | 78,500 | 96 | 22 | 118 | 92,63,000 |
| 6.1 Structural steel, fabricated and erected | MT | 1,12,000 | 40 | 28 | 68 | 76,16,000 |
| Total work done to date |  |  |  |  |  | 2,79,35,750 |

**RA bill 7: summary and deductions**

| Line | Amount (₹) | How it is worked out |
| --- | --- | --- |
| Work done to date | 2,79,35,750 | From the abstract |
| Less gross value of RA bills 1 to 6 | 2,13,24,500 | Previous quantities at the same rates |
| Value of this bill (taxable value) | 66,11,250 | Difference |
| Add GST at 18% | 11,90,025 | Works contract, heading 9954 |
| Gross amount of invoice | 78,01,275 | Value plus GST |
| Less retention at 5% | 3,30,563 | 5% of 66,11,250 |
| Less mobilisation advance recovery | 8,26,406 | 12.5% of 66,11,250 |
| Less TDS under section 393(1) at 2% | 1,32,225 | 2% of 66,11,250, a company |
| Less building workers' cess at 1% | 66,113 | 1% of 66,11,250 |
| Net payable | 64,45,968 | 78,01,275 less the four deductions |

Check the arithmetic the client will check: the TDS and cess are on the value before GST, the retention and advance recovery are on the work value (as this contract says; some contracts take retention on the gross including GST), and the net payable is what reaches the bank. The ₹1,32,225 of TDS appears in the contractor's Form 26AS and is claimed against its tax; the ₹3,30,563 of retention is still the contractor's money, held by the client until release.

## The final bill and closing the account

The final bill is prepared after the work is complete and the completion certificate is issued. Every item is finally measured, deviations beyond the contract's limits are priced, all extra items are settled, and the final quantities replace every estimate in earlier RA bills. The final bill then shows the total value of the contract as executed, less every amount paid on account, with all recoveries completed (the mobilisation advance must be fully recovered by now).

- Get a no-claim or no-dues certificate only after the final bill amount is agreed; it usually waives claims not listed.
- Reconcile free-issue material: theoretical consumption against issues, with the contract's wastage limit; excess consumption is recovered at the penal rate.
- Ask for return of bank guarantees for the mobilisation advance once it is fully recovered.
- Retention is not paid with the final bill unless the contract says so. It follows the defect liability period.

## Common RA bill mistakes

- Billing a quantity beyond the BOQ quantity without a deviation approval. The certifier will cut it, and the next bill starts with a dispute.
- Taking cumulative quantities from the wrong previous bill, so work is billed twice or missed.
- Deducting TDS on the GST-inclusive amount when GST is shown separately.
- Charging the wrong GST rate after 22 September 2025 on a government contract that used to be at 12%.
- Not tracking how much of the mobilisation advance is left, so the final bill carries a surprise recovery.
- Paying a subcontractor's RA bill without checking the measurement against the site's own progress record.
- Losing the trail of retention by project, so it is never claimed back after the defect liability period.

## Or let the site's progress write the RA bill.

In Emplotec Projects, the quantity measured in the daily progress report goes to the RA bill, and subcontractor bills are checked against the same record before anyone pays them.

- Subcontractor work orders and their RA bills carry BOQ rates, measured and certified quantities, retention, advance and free-issue recovery, TDS and labour cess.
- Retention and mobilisation advances are tracked on both sides, for the client and for every subcontractor.
- Cement and steel issued are reconciled against the BOQ's consumption, with the wastage limit, before the free-issue recovery is set.
- With Billing, the client's RA bill is raised with measurement and client certification, and retention held and advances left to recover show per project.

Read more: [Emplotec Projects](https://www.emplotec.com/erp/projects.md)

## Questions and answers

### What is the full form of RA bill?

Running account bill. It is an interim bill for work done to date on a contract, raised periodically while the work continues, with the account settled in the final bill.

### What is the difference between an RA bill and a final bill?

An RA bill is a payment on account based on quantities measured so far, and it can be revised later. The final bill is prepared once, after completion and final measurement, and settles the whole contract.

### Which section applies for TDS on RA bills now?

Section 393(1) of the Income-tax Act, 2025, from 1 April 2026; it replaced section 194C of the 1961 Act. The rate is 1% for an individual or HUF contractor and 2% for others, on the value excluding GST when GST is shown separately.

### What is the GST rate on a works contract RA bill?

18% for most works contracts from 22 September 2025, including government works contracts that were earlier at 12%. A few specified entries carry other rates, so confirm the entry for your contract.

### Is retention deducted before or after GST?

It depends on the contract. GST is charged on the full value of work in the invoice, and retention is then deducted from the amount payable, either on the work value or on the gross amount including GST, as the contract specifies.

### Who certifies an RA bill?

The engineer-in-charge in government work, or the client's project manager or quantity surveyor in private work, after checking the measurements. Accounts then pass the certified bill for payment.

## Sources

- [Income-tax Act, 2025: section 393 (tax deduction at source), Income Tax Department](https://www.incometaxindia.gov.in/)
- [CGST Act, 2017: sections 31 and 51, CBIC tax information portal](https://taxinformation.cbic.gov.in/)
- [Notification 15/2025-Central Tax (Rate), 17 September 2025, CBIC](https://taxinformation.cbic.gov.in/)
- [CPWD Works Manual: measurement books and running account bills](https://cpwd.gov.in/)
- [Code on Social Security, 2020, Ministry of Labour and Employment](https://labour.gov.in/)

## Related

- [/erp/projects](https://www.emplotec.com/erp/projects.md)
- [/templates/ra-bill-format](https://www.emplotec.com/templates/ra-bill-format.md)
- [/templates/boq-format](https://www.emplotec.com/templates/boq-format.md)
- [/guides/retention-money](https://www.emplotec.com/guides/retention-money.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All guides: https://www.emplotec.com/guides.md
- /erp/projects: https://www.emplotec.com/erp/projects.md
- /templates/ra-bill-format: https://www.emplotec.com/templates/ra-bill-format.md
- /templates/boq-format: https://www.emplotec.com/templates/boq-format.md