# Control plan format for IATF 16949, free in Excel and PDF

> A control plan lists, for every process step, the product and process characteristics you check, how you measure them, how often, and what you do when a check fails. Fill this one in on the page, or download it.

Page: https://www.emplotec.com/templates/control-plan-format · Updated: 2026-11-06

Market: India

- IATF 16949, Annex A
- AIAG Control Plan, 2024
- A4 landscape
- Free, no sign-up

## Download

- Excel: https://www.emplotec.com/downloads/control-plan-format.xlsx
- Word: https://www.emplotec.com/downloads/control-plan-format.docx
- PDF (blank, A4): https://www.emplotec.com/downloads/control-plan-format.pdf
- Fill it in online: https://www.emplotec.com/templates/control-plan-format

## What the format contains

- Title: Control plan (Prepared to IATF 16949 (clause 8.5.1.1 and Annex A) and the AIAG Control Plan manual)
- Fields: Phase, Control plan no. and rev., Part no. and drawing rev., Part name, Organisation and plant, Customer, Key contact, Core team, Date, original, Date, revised, Customer approval, date, PFMEA reference
- Line table, columns: Op. no., Process name, Machine, Char. no., Product char., Process char., Class, Specification, Measurement, Size, Frequency, Control method, Reaction plan
- Notes: Class: mark special characteristics with the symbol your customer specifies (CC critical, SC significant are used here). Phase: prototype, pre-launch, safe launch or production. Reaction plan: contain suspect product, stop the process making more, and bring it back under control; name who acts or refer to the work instruction. Every gauge used must be in the calibration system.
- Signatures: Prepared by (quality engineer), Approved by (plant head), Customer approval, if required

## What a control plan is

A control plan is a summary of how a part is kept within specification while it is made. For each process step it lists the characteristics that matter, the specification, how and how often each is checked, the control method and the reaction plan if a check fails.

It is one of the automotive core tools. It comes out of the process flow diagram and the PFMEA, goes into the PPAP submission, and is the document an auditor compares against what operators actually do on the line.

## What IATF 16949 asks for

- Clause 8.5.1.1 requires control plans at the system, subsystem, component or material level, for pre-launch and production, linked to the design risk analysis, the process flow diagram and the PFMEA.
- Annex A of IATF 16949 sets the minimum contents of a control plan: general data, product and process controls, methods, and the reaction plan.
- The control plan must say how special characteristics are monitored, and what happens when the product is nonconforming or the process becomes unstable or not capable.
- It is reviewed and updated when a nonconformity reaches the customer, when the process, product or PFMEA changes, and after customer complaints.

> Note: In March 2024 AIAG replaced its combined APQP and Control Plan manual with APQP 3rd edition and a separate Control Plan 1st edition. The new manual adds a safe launch phase and clarifies what a reaction plan must cover. Check which edition your customer requires.

## The phases of a control plan

**Control plan phases in the AIAG Control Plan manual, 1st edition (2024).**

| Phase | When | What it covers |
| --- | --- | --- |
| Prototype | While building prototypes | Dimensional checks, material and performance tests on prototype parts. |
| Pre-launch | After prototypes, before full production | Extra checks and higher frequencies while the process is proved. |
| Safe launch | At the start of production | Added, temporary controls with exit criteria agreed with the customer, under the 2024 AIAG manual. |
| Production | Mass production | The controls the process keeps for the life of the part. |

## Each column of the control plan format, explained

**The columns follow the AIAG Control Plan form.**

| Column | What to write |
| --- | --- |
| Op. no. and process name | The operation number and name, as in the process flow diagram and the PFMEA. |
| Machine | The machine, device, jig or tool used. |
| Characteristic no. | The balloon number from the drawing, or your own number for process characteristics. |
| Product characteristic | A feature of the part: a diameter, a thread, a hardness, a surface finish. |
| Process characteristic | A process setting that drives a product characteristic: tool life, temperature, torque, pressure. |
| Class | The special characteristic symbol, if the customer or your PFMEA designates one. |
| Specification | The value and tolerance from the drawing or the process sheet. |
| Measurement | The gauge or method: CMM, air gauge, go/no-go gauge, visual against a limit sample. |
| Sample size and frequency | How many parts, and how often: 5 every hour, 100%, first and last off, per heat. |
| Control method | How the check is controlled: SPC chart, check sheet, error-proofing, first-off approval. |
| Reaction plan | What the operator does when a check fails: hold suspect parts, stop, correct, inform, and who decides. |

## How to prepare a control plan

1. Start from the process flow diagram: one block of rows for each operation, in the same order and numbering.
2. Take every product and process characteristic the PFMEA relies on as a detection or prevention control.
3. Add the special characteristics from the drawing and the customer's requirements, with their symbols.
4. For each characteristic, choose the measurement method and confirm the gauge is capable (MSA) and calibrated.
5. Set sample sizes and frequencies from the risk: higher for special characteristics, higher still at pre-launch and safe launch.
6. Write a reaction plan for each line that an operator can follow at 3 a.m. without calling anyone.
7. Have the cross-functional team review it, get customer approval where required, and keep it in step with the PFMEA every time either changes.

## Control plan, PFMEA and inspection plan compared

|  | PFMEA | Control plan | Inspection plan or work instruction |
| --- | --- | --- | --- |
| Answers | What can go wrong, and how bad is it? | What do we check, how and how often? | How does this operator do this check? |
| Covers | Every failure mode of every step | The characteristics that need control | One station or one check |
| Used by | The engineering team | Quality, production and auditors | The operator and the inspector |

## Common mistakes in control plans

- A control plan that doesn't match the PFMEA: controls in one that the other never mentions.
- Reaction plans that say only "inform supervisor". Say what happens to the suspect parts already made.
- Frequencies nobody follows. The auditor checks the SPC chart or check sheet against the plan.
- Gauges named in the plan that are overdue for calibration.
- One generic control plan for every part in a family, without the part-specific characteristics.

## Or let the control plan run the checks.

In Emplotec Quality the control plan sits with the part, beside its PFMEA and PPAP pack. Each line becomes an in-process check on the shop-floor app, at the frequency the plan sets, against a calibrated gauge.

- PFMEA (AIAG-VDA), control plans and PPAP packs are versioned with the part.
- Readings feed basic SPC: X̄-R charts and Cp and Cpk for each characteristic.
- Gauges come from the gauge register, and an overdue gauge is blocked from inspections.
- A failed check holds the stock in QC and opens an NCR, so the reaction plan is followed, not just written.

Read more: [Emplotec Quality](https://www.emplotec.com/erp/quality.md)

## Questions and answers

### What is a control plan in IATF 16949?

A documented description of how product and process characteristics are controlled at each step, required by clause 8.5.1.1, with minimum contents set in Annex A. It covers pre-launch and production, and links to the process flow and the PFMEA.

### What are the phases of a control plan?

Prototype, pre-launch and production, with safe launch added by the AIAG Control Plan manual published in 2024. Each phase lists the controls that apply at that stage of the product's life.

### What is the difference between a control plan and a PFMEA?

The PFMEA analyses what can go wrong at each step and how risky it is. The control plan lists the checks that keep those risks under control on the line: what is measured, how, how often, and the reaction when a check fails.

### What should a reaction plan in a control plan include?

What to do with suspect product already made, how to stop the process making more, how to bring it back under control, and who is responsible. Refer to a detailed instruction where the steps are long.

### What are special characteristics in a control plan?

Product or process characteristics that affect safety, regulatory compliance, fit, function or later processing. They are designated by the customer or by your own risk analysis, marked with the customer's symbol, and controlled more tightly.

### Is the control plan part of PPAP?

Yes. The control plan is one of the elements submitted in a PPAP, alongside the process flow diagram, the PFMEA, MSA studies and initial process studies.

## Sources

- [IATF: IATF 16949:2016, automotive quality management system standard](https://www.iatfglobaloversight.org/)
- [AIAG: APQP 3rd edition and Control Plan 1st edition](https://blog.aiag.org/our-presale-for-the-new-apqp-3rd-edition-and-standalone-control-plan-is-finally-here-1)
- [DQS: publication of APQP 3rd edition and Control Plan 1st edition](https://www.dqsglobal.com/en/explore/blog/hk/coming-publication-of-apqp-ed3-and-control-plan-ed1)

## Related

- [/erp/quality](https://www.emplotec.com/erp/quality.md)
- [/templates/costing-sheet-format](https://www.emplotec.com/templates/costing-sheet-format.md)
- [/templates/grn-format](https://www.emplotec.com/templates/grn-format.md)
- [/guides/production-planning-and-control](https://www.emplotec.com/guides/production-planning-and-control.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All templates: https://www.emplotec.com/templates.md
- /erp/quality: https://www.emplotec.com/erp/quality.md