# Daily construction report template with manpower, weather and delays

> A daily construction report (daily log) records what happened on site each day: weather, who worked and for how long, equipment, work done, deliveries, inspections, safety and delays. This one totals the labor and equipment hours and the delay time for you.

Page: https://www.emplotec.com/templates/daily-construction-report-template · Updated: 2026-11-27

Market: US

- Labor hours by trade, totaled
- Weather by time of day, delay hours
- Inspections, deliveries and safety
- Excel with formulas, Word, PDF

## Download

- Excel: https://www.emplotec.com/downloads/daily-construction-report-template.xlsx
- Word: https://www.emplotec.com/downloads/daily-construction-report-template.docx
- PDF (blank, A4): https://www.emplotec.com/downloads/daily-construction-report-template.pdf
- Fill it in online: https://www.emplotec.com/templates/daily-construction-report-template

## What the format contains

- Title: Daily construction report (Report no. 142)
- Issuer block: Name and address, Name and address
- Fields: Project, Project no., Date, Working day, Superintendent, Owner's rep., Permit no., Shift
- Fields: 7 AM weather, Noon weather, 4 PM weather, Precipitation, ground
- Manpower, columns: Company, Trade, Foreman, Workers, Hours each, Total hours, Area worked. Totals row: Total on site
- Equipment, columns: Equipment, Owned or rented, by, Hours used, Hours idle, Note. Totals row: Total
- Work performed: Level 2 deck, area B: placed 186 CY of 5,000 psi concrete (19 trucks), pour 7:40 AM to 1:30 PM; finished and covered with insulated blankets per the cold weather plan. Level 3 columns C1 to C6: rebar cages set. Level 1: underground electrical conduit, grid lines 1 to 3. Schedule activity 3120 (L2 deck B) complete.
- Concrete placed: Ordered (CY), Placed (CY), Returned or wasted (% of ordered)
- Deliveries, columns: Time, Supplier, Material, Ticket no., Checked by
- Inspections and tests, columns: Inspection or test, By, Result
- Delays and issues, columns: Delay or issue, Cause, Hours lost, Crews affected, Notice or RFI. Totals row: Total hours lost
- Safety: Toolbox talk 6:40 AM: cold stress and slips on frozen deck, 23 attended. No injuries or incidents; one near miss (blanket roll dropped from L2 edge to barricaded zone), reported NM-26-031. Fall protection inspected on L2 and L3 edges.
- Visitors, instructions and changes: P. Nakamura (owner's rep.) walked the L2 pour 9:00 to 10:00 AM. City inspector not on site today. Verbal request from the architect to move the L1 floor box at grid C-2: asked for it in writing, no work done.
- Photos: 28 photos, uploaded to project folder 2026-11-19: pour sequence, blankets, unmarked line at grid 2.
- Signatures: Superintendent, Project manager

## What a daily construction report is

A daily construction report, also called a daily log or superintendent's daily report, is the general contractor's record of one working day on one project. It records the conditions, the people and equipment on site, the work done, materials delivered, inspections, safety events, visitors, instructions received and anything that held the work up. It is written by the superintendent on the day and signed.

Its value shows up later. When there is a dispute about a delay, a change, a back charge or an injury months on, the daily reports are often the only record made at the time, and they carry more weight than anyone's memory. A report written every day, with facts and numbers, is the best protection a contractor has.

## What to include in a daily construction report

| Section | What to write | Why it matters |
| --- | --- | --- |
| Header | Project, number, date, working day, superintendent, permit, shift hours | Ties the report to the schedule and contract days |
| Weather | Temperature, conditions and wind at set times, precipitation, ground conditions | Weather delays are excused only if they are recorded, and cold or hot weather changes concrete, paint and roofing work |
| Manpower | Each company and trade, foreman, number of workers and hours | Proves crew levels, supports back charges and certified payroll checks |
| Equipment | Each machine, who owns it, hours used and idle | Standby and idle time is a cost in delay and change claims |
| Work performed | What was done where, quantities, and schedule activities started or finished | Progress for pay applications and the schedule update |
| Deliveries | Supplier, material, ticket number, who checked it | Matches invoices and finds shortages |
| Inspections and tests | What was inspected or tested, by whom, the result and report number | Evidence for code compliance and quality |
| Delays and issues | What stopped work, the cause, hours lost, crews affected, notice or RFI sent | The basis for time extensions and claims |
| Safety | Toolbox talk and attendance, incidents, near misses, inspections | Feeds OSHA records and shows a working safety program |
| Visitors, instructions and changes | Who came, what they said, any direction that may change the work | Unwritten directions are where change disputes start |
| Photos and signature | Where the photos are, and the superintendent's signature | Dated photos are the strongest evidence |

## The numbers the template works out

Total hours for each company = workers x hours each, and the template totals the workers and hours on site. In the example: 4 x 8 + 9 x 10 + 5 x 8 + 3 x 8 + 2 x 8 = 32 + 90 + 40 + 24 + 16 = 202 labor hours from 23 workers. Equipment totals 16 hours used and 7 idle. Delays total 6 hours lost.

For concrete, the template works out what was returned or wasted as a share of the order: (190 - 186) / 190 x 100 = 2.11%. Tracked pour by pour, it shows whether takeoffs or ordering need tightening.

## When daily reports are required

No general law requires a private contractor to keep a daily log, but most construction contracts and specifications do, and some public work rules make related records mandatory:

| Rule or document | What it asks for |
| --- | --- |
| The contract's general conditions and Division 01 specifications | Usually a daily report or log, often submitted to the owner or architect daily or weekly |
| UFGS 01 45 00, Quality Control (federal work under Unified Facilities Guide Specifications) | Contractor quality control daily reports, signed with a certification that the report is complete and correct, on the schedule the contract sets |
| Davis-Bacon and related acts, 29 CFR 5.5(a)(3) | Weekly certified payrolls (DOL form WH-347 or an equivalent). The daily manpower log is how you check them |
| FAR 52.249-10(b), fixed-price construction | The contractor is not in default for delays from unforeseeable causes beyond its control, including unusually severe weather, if it notifies the contracting officer in writing within 10 days of the start of the delay |
| 29 CFR 1926.20(b)(2), OSHA construction | Frequent and regular inspections of the jobsite, materials and equipment by competent persons |

> Note: Weather delays are measured against normal weather. Record actual conditions every day, including good days, so you can show that the bad days were unusual and that they stopped critical work.

## Recording weather for concrete and other temperature-sensitive work

ACI 306 treats cold weather as a period when the air temperature has fallen, or is expected to fall, below 40 F during the protection period. Record temperatures at set times, the concrete temperature at placement and the protection used (blankets, heated enclosures), as in the example, because these are what an engineer will ask for if cylinder breaks come back low.

## How to fill in the daily construction report

1. Fill the header each morning, with the working day count from the schedule.
2. Record the weather at the same times every day, and the ground conditions.
3. Get headcounts and hours from each foreman before they leave; the template works out total hours.
4. Write work done by area with quantities and the schedule activity.
5. Log deliveries with ticket numbers, and every inspection or test with its result.
6. Record every delay with its cause, hours and the crews affected, and note any notice or RFI sent the same day.
7. Write down visitors and any instruction that could change the work, especially verbal ones.
8. Note where the photos are, sign, and send it to the project manager before the end of the day.

## Common mistakes in daily reports

- Filling it in at the end of the week from memory.
- "Weather: cold" instead of temperatures and times.
- Subcontractor headcounts copied from yesterday.
- Delays recorded with no cause or hours, so they can't support a time extension.
- Verbal directions from the owner or architect left out because no work was done yet.
- Opinions and blame instead of facts. The report may be read by a judge or arbitrator.

## Or file the daily report from the site, on a phone.

In Emplotec Projects the superintendent files the day's report on the mobile app, offline if the site has no signal. Work, labor, equipment and material post to the project as they are entered, so nobody retypes the daily log into a spreadsheet at night.

- Work done is entered against cost codes and schedule activities, so progress, earned value and the S-curve update from the same entries.
- Material received and issued comes from the site store, and consumption is reconciled against the estimate.
- Subcontractor work orders sit on the project, so each crew's work in the daily report is there when their pay application comes in.
- Emplotec drafts the weekly owner's report from the week's daily reports, for the project manager to check and send.

Read more: [Emplotec Projects](https://www.emplotec.com/erp/projects.md)

## Questions and answers

### What should be included in a daily construction report?

The project, date and superintendent; weather at set times; manpower by company and trade with hours; equipment hours used and idle; work performed with quantities; deliveries; inspections and tests; delays with cause and hours; safety; visitors and instructions; photos; and a signature.

### Who fills out the daily construction report?

The general contractor's superintendent, from what they saw and from each foreman's headcount and hours. Subcontractors often keep their own daily reports, which the superintendent collects.

### Are daily reports required by law?

Not as a general rule for private work, but most contracts and specifications require them. On federal work, UFGS 01 45 00 calls for signed contractor quality control daily reports, Davis-Bacon work needs weekly certified payrolls, and FAR 52.249-10 requires written notice of excusable delays within 10 days.

### How do you record weather delays?

Record the actual weather every day at set times, which work was stopped, the crews and hours affected, and whether that work was on the critical path. Send written notice as the contract requires. Compare against normal weather for the month when you claim time.

### What is the difference between a daily report and a daily log?

Most contractors use the terms for the same document. Some keep a daily log as the superintendent's diary and a daily report as the formal version sent to the owner. This template works as either.

### How long should daily construction reports be kept?

At least as long as the contract, warranty and claim periods, and your state's statute of repose for construction defects, which can run for many years. Federal contracts set their own record retention terms. Keep them with the photos.

## Sources

- [WBDG: UFGS 01 45 00, Quality Control](https://www.wbdg.org/dod/ufgs/ufgs-01-45-00)
- [29 CFR 5.5, contract provisions and related matters (Davis-Bacon)](https://www.law.cornell.edu/cfr/text/29/5.5)
- [U.S. Department of Labor: WH-347, certified payroll form](https://www.dol.gov/agencies/whd/forms/wh347)
- [FAR 52.249-10, default (fixed-price construction)](https://www.acquisition.gov/far/52.249-10)
- [29 CFR 1926.20, general safety and health provisions (construction)](https://www.law.cornell.edu/cfr/text/29/1926.20)
- [ACI: Cold weather concreting (ACI 306)](https://www.concrete.org/topicsinconcrete/topicdetail/cold%20weather%20concreting)

## Related

- [/erp/projects](https://www.emplotec.com/erp/projects.md)
- [/templates/change-order-template](https://www.emplotec.com/templates/change-order-template.md)
- [/templates/incident-report-template](https://www.emplotec.com/templates/incident-report-template.md)
- [/templates/dpr-format](https://www.emplotec.com/templates/dpr-format.md)
- [/templates/punch-list-template](https://www.emplotec.com/templates/punch-list-template.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All templates: https://www.emplotec.com/templates.md
- /erp/projects: https://www.emplotec.com/erp/projects.md
- /templates/change-order-template: https://www.emplotec.com/templates/change-order-template.md
- /templates/incident-report-template: https://www.emplotec.com/templates/incident-report-template.md