# Job card format for production, in Excel and PDF

> A job card travels with a batch on the shop floor and records each operation: who ran it, on which machine, for how long, and how many parts came out good. Fill it in here, or download it.

Page: https://www.emplotec.com/templates/job-card-format · Updated: 2026-11-06

Market: India

- One row per operation
- Good, rework and rejected quantities
- Efficiency worked out
- A4 landscape, Excel with formulas

## Download

- Excel: https://www.emplotec.com/downloads/job-card-format.xlsx
- Word: https://www.emplotec.com/downloads/job-card-format.docx
- PDF (blank, A4): https://www.emplotec.com/downloads/job-card-format.pdf
- Fill it in online: https://www.emplotec.com/templates/job-card-format

## What the format contains

- Title: Job card (Travels with the batch. Fill in each operation as it is completed.). Copy line: Shop copy
- Issuer block: Name and address, Name and address
- Fields: Job card no., Work order no., Customer and order, Issue date, Part no. and name, Drawing and revision, Material and heat no., Batch quantity, Route, Target completion, Priority, Issued by (PPC)
- Operations, columns: Op., Operation, Machine, Operator, Date, Start, End, Setup min, Run min, Total min, Qty in, Good, Rework, Rejected, Balance, Inspected by. Totals row: Total
- Rejection and rework details, columns: Op., Defect, Qty, Cause code, Disposition, NCR no.. Totals row: Total
- Operation 20: efficiency: Good quantity, Standard time per piece, minutes, Earned hours (good quantity x standard time), Actual hours (setup and run), Efficiency, %
- Signatures: Issued by (PPC), Shift supervisor, Final inspection, Received in stores

## What a job card is in production

A job card is the document that travels with a batch through the shop. Planning issues it against a work order; each operator fills in their operation as they finish it; and when the batch reaches stores, the job card shows exactly what happened to it: who worked on it, on which machine, how long it took, and how many parts were good, reworked or rejected.

It is the shop floor's source for three numbers that matter: the actual cost of the job, the efficiency of each operation, and where the rejections came from. No law prescribes it, so the format is whatever your shop needs, but most Indian machine shops record the same fields.

## What a job card format contains

| Part | Fields |
| --- | --- |
| Header | Job card number, work order, customer order, part number and name, drawing and revision, material and heat number, batch quantity, route, target date. |
| Each operation | Operation number and name, machine, operator, date, start and end time, setup and run minutes. |
| Quantities | Quantity received at the operation, good, sent for rework, rejected, and the balance still in process. |
| Quality | Who inspected each operation; defects, cause codes, disposition and NCR numbers for rejections. |
| Sign-offs | Planning, supervisor, final inspection and stores. |

## How to fill in a job card on the shop floor

1. Planning fills the header from the work order and the route, and issues the card with the material.
2. Before starting, the operator checks the drawing revision and the heat number against the card.
3. At each operation, write the machine, your name, the date and start time. Note setup minutes separately from run minutes.
4. When the operation ends, write the end time and the quantities: good, rework and rejected. The balance should come to zero, or show what is still in process.
5. The inspector signs the operation. Rejected parts get a line in the rejection table, with a cause code and the NCR number.
6. When the last operation is signed, final inspection and stores sign the card, and it goes to planning for closing.

## Job card, work order, route card and job sheet compared

**One work order can have several job cards if the batch is split across shifts or machines.**

|  | What it is | Who uses it |
| --- | --- | --- |
| Work order (production order) | The instruction to make a quantity of a part by a date | Planning, stores, accounts |
| Route card (routing) | The standard sequence of operations, machines and times for a part | Engineering, planning |
| Job card | The record of what actually happened to one batch at each operation | Operators, supervisors, inspectors |
| Job sheet (vehicle service) | A workshop's record of a repair: complaint, work done, parts and labour | Service workshops |

## Using job cards for costing and efficiency

- Labour and machine cost: setup and run minutes per operation, multiplied by the machine hour rate, give the actual conversion cost of the batch.
- Efficiency: earned hours (good quantity times standard time) divided by actual hours. The calculation block above does it for one operation: 114 good parts at 17.5 minutes is 33.3 earned hours against 36.4 actual, or 91.3%.
- Yield: good quantity at the last operation divided by quantity issued. Here, rejections at operations 10 and 20 cost 3 parts out of 120.
- Setup time on its own line shows which jobs suffer from small batches or slow changeovers.

## Common mistakes with job cards

- Filling in times at the end of the shift from memory, so every operation takes exactly eight hours.
- Setup and run time recorded together, which hides changeover losses.
- Rejections written as a number with no cause, so the same defect repeats.
- Quantities that don't balance: 120 in, 118 good, nothing rejected, two parts missing.
- No heat number on the card, so a material problem can't be traced to the batches it affected.

## Or let the operator book the job card at the machine.

In Emplotec job cards are created from the work order and its routing, booked by operators at a shop-floor kiosk or on mobile, and every minute and rejection flows into the job's cost and the machine's OEE.

- Work orders, job cards and shop-floor kiosk entry, with digital work instructions for each operation.
- An operator certification check runs before a job card starts.
- Scrap, rejection and rework are recorded against the operation, and feed job costing, planned against actual.
- OEE and downtime come from the same bookings, and the schedule re-sequences when a machine stops.

Read more: [Emplotec Manufacturing](https://www.emplotec.com/erp/manufacturing.md)

## Questions and answers

### What is a job card in production?

The record that travels with a batch through the shop, showing each operation's machine, operator, times and the good, reworked and rejected quantities. It is the source for actual job cost and operation efficiency.

### What is the difference between a job card and a work order?

The work order is the instruction to make a quantity by a date. The job card records what actually happened at each operation. One work order can have several job cards.

### How is efficiency calculated from a job card?

Earned hours divided by actual hours, times 100. Earned hours are the good quantity multiplied by the standard time per piece; actual hours are the setup and run time booked.

### Who fills in the job card?

Planning fills the header and issues it; operators fill in their operation; inspectors sign each operation; stores signs when the finished batch is received.

### Should rework be counted as good or rejected?

Neither, at the time. Record it separately; when the reworked parts pass inspection, add them to the good quantity of that operation and note the rework time.

### Is a job card the same as a job sheet in a service workshop?

No. A vehicle or equipment service job card records a repair: the complaint, the work done, parts and labour. A production job card records manufacturing operations on a batch.

## Sources

- [Bureau of Indian Standards: IS/ISO 9001:2015, clause 8.5.1 (control of production) and 8.5.2 (identification and traceability)](https://www.bis.gov.in/)
- [ICMAI: Cost accounting standards (CAS-7 employee cost, CAS-3 production and operation overheads)](https://icmai.in/)

## Related

- [/erp/manufacturing](https://www.emplotec.com/erp/manufacturing.md)
- [/templates/costing-sheet-format](https://www.emplotec.com/templates/costing-sheet-format.md)
- [/tools/oee-calculator](https://www.emplotec.com/tools/oee-calculator.md)
- [/guides/production-planning-and-control](https://www.emplotec.com/guides/production-planning-and-control.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All templates: https://www.emplotec.com/templates.md
- /erp/manufacturing: https://www.emplotec.com/erp/manufacturing.md
- /templates/costing-sheet-format: https://www.emplotec.com/templates/costing-sheet-format.md
- /tools/oee-calculator: https://www.emplotec.com/tools/oee-calculator.md