# Reorder level calculator, with the formula, safety stock and EOQ

> Enter daily usage and lead time to get the reorder level, the safety stock behind it, the economic order quantity and the minimum and maximum stock levels.

Page: https://www.emplotec.com/tools/reorder-level-calculator · Updated: 2026-11-06

Market: Any country

Use the calculator: https://www.emplotec.com/tools/reorder-level-calculator

- Max-min or service-level method
- Safety stock and EOQ
- Minimum and maximum levels
- Stock chart

## The reorder level formula

Reorder level = demand during the lead time + safety stock. When stock falls to this level, you place the next order, and it should arrive just as stock reaches the safety stock.

Cost accounting texts write the same thing as reorder level = maximum usage × maximum lead time. That is the max-min method: it plans for the worst usage over the longest lead time, and the safety stock is whatever that adds above average demand.

| Level | Formula |
| --- | --- |
| Reorder level | Maximum usage × maximum lead time (max-min), or average usage × average lead time + safety stock |
| Safety stock (max-min) | Maximum usage × maximum lead time − average usage × average lead time |
| Safety stock (service level) | z × σ of daily usage × √lead time |
| Minimum level | Reorder level − average usage × average lead time |
| Maximum level | Reorder level + reorder quantity − minimum usage × minimum lead time |
| Average stock | Minimum level + ½ reorder quantity |
| Economic order quantity | √(2 × annual demand × cost per order ÷ carrying cost per unit a year) |

## Two ways to set safety stock

The max-min method needs only the highest and average figures you have seen, so it is quick and easy to explain. It is also generous: it assumes the worst usage and the worst lead time happen together, which is rare.

The service-level method uses how much usage varies. Pick the share of order cycles you want to get through without running out, look up its z-value, and multiply by the standard deviation of demand over the lead time. If lead time varies too, the spread becomes √(lead time × σ of usage² + average usage² × σ of lead time²).

**From the standard normal distribution. Going from 95% to 99% raises safety stock by about 41%.**

| Service level | z | Safety stock with σ of 8 a day and a 10-day lead time |
| --- | --- | --- |
| 90% | 1.282 | 33 units |
| 95% | 1.645 | 42 units |
| 97.5% | 1.960 | 50 units |
| 98% | 2.054 | 52 units |
| 99% | 2.326 | 59 units |
| 99.9% | 3.090 | 79 units |

## The EOQ formula

Economic order quantity is the order size at which the cost of placing orders equals the cost of carrying stock, so their total is lowest. EOQ = √(2DS ÷ H), where D is annual demand, S the cost of placing one order, and H the cost of holding one unit for a year (usually the unit cost × a carrying rate of 15% to 30%).

The total cost curve is flat near the EOQ, so rounding it to a pack size or a supplier's minimum costs little. Use it as the reorder quantity in the minimum and maximum level formulas.

## A worked example

An item used at 40 units a day on average (25 at least, 55 at most), with a lead time of 10 days (7 at least, 14 at most). An order costs ₹1,500 to place, a unit costs ₹250, carrying cost is 20% a year, and the stores work 300 days.

| Figure | Working | Result |
| --- | --- | --- |
| Lead-time demand | 40 × 10 | 400 units |
| Reorder level (max-min) | 55 × 14 | 770 units |
| Safety stock (max-min) | 770 − 400 | 370 units |
| Safety stock at 95%, σ of 8 a day | 1.645 × 8 × √10 | 42 units (reorder level 442) |
| EOQ | √(2 × 12,000 × 1,500 ÷ 50) | 849 units |
| Minimum level | 770 − 400 | 370 units |
| Maximum level | 770 + 849 − 25 × 7 | 1,444 units |
| Average stock | 370 + 849 ÷ 2 | 795 units |

These are the calculator's opening figures. The two methods differ by 328 units of safety stock, worth ₹82,000 at cost and ₹16,400 a year to carry: the price of planning for the worst case on every count.

## Reorder level and reorder quantity

The reorder level says when to order; the reorder quantity says how much. A fixed reorder quantity, usually the EOQ, is the classic two-bin system. A min-max system instead orders enough to bring stock back up to the maximum level, so each order varies.

## Common mistakes

- Setting a level once and leaving it. Usage and lead times change; review fast movers every quarter.
- Counting lead time from the PO date when approval and dispatch add days before it. Lead time runs from the moment stock hits the level to the moment it can be issued.
- Ignoring stock already on order: compare the level with stock in hand plus open orders, or you order twice.
- Using the same service level for every item. Class A items and those that stop the line deserve more than slow, cheap ones.
- Mixing days: working days for usage and calendar days for lead time.

## Or let the stores raise the indent for you.

In Emplotec, reorder levels and safety stock sit on each item and godown, and stock that crosses its level turns into an indent for someone to approve.

- Reorder levels and safety stock on one stock ledger across every godown, plant and branch.
- Indents raised from reorder levels go for approval and on to the right vendor, with Procurement.
- ABC/XYZ classes, cycle counts, and slow and non-moving stock, so the levels are set where they matter.
- Ask Emplotec which items fell below their level this week, and it lists them with what is already on order.

Read more: [Emplotec Inventory](https://www.emplotec.com/erp/inventory.md)

## Questions and answers

### What is the reorder level formula?

Reorder level = average usage × average lead time + safety stock. By the max-min method taught in cost accounting, it is maximum usage × maximum lead time.

### How do you calculate safety stock?

By the max-min method, safety stock = maximum usage × maximum lead time − average usage × average lead time. By the service-level method, it is z × the standard deviation of daily usage × √lead time in days.

### What is the EOQ formula?

EOQ = √(2 × annual demand × cost per order ÷ carrying cost per unit a year). With 12,000 units a year, ₹1,500 an order and ₹50 a year to carry a unit, EOQ is 849 units.

### What is the difference between reorder level and reorder quantity?

The reorder level is the stock at which you place an order; the reorder quantity is how much you order. The reorder quantity is often the EOQ.

### What is the formula for minimum and maximum stock level?

Minimum level = reorder level − average usage × average lead time. Maximum level = reorder level + reorder quantity − minimum usage × minimum lead time.

### What service level should I use for safety stock?

95% is a common default. Raise it to 98% or 99% for items that stop production or that customers wait for, and lower it for cheap, slow items where a short wait costs little.

## Sources

- [ICAI: Cost and Management Accounting study material, material cost and inventory control](https://www.icai.org/)
- [NIST/SEMATECH e-Handbook of Statistical Methods: the normal distribution and its critical values](https://www.itl.nist.gov/div898/handbook/eda/section3/eda3671.htm)
- [Harris, F. W., How Many Parts to Make at Once (1913), reprinted in Operations Research 38(6), 1990](https://pubsonline.informs.org/doi/10.1287/opre.38.6.947)

## Related

- [/erp/inventory](https://www.emplotec.com/erp/inventory.md)
- [/templates/indent-format](https://www.emplotec.com/templates/indent-format.md)
- [/templates/grn-format](https://www.emplotec.com/templates/grn-format.md)
- [/tools/cbm-calculator](https://www.emplotec.com/tools/cbm-calculator.md)

---

- Talk to us: https://www.emplotec.com/contact (we call back within one working day)
- Email: preethan@emplotec.com · Phone and WhatsApp: +91 93420 95081
- Evaluating an ERP? Read the brief: https://www.emplotec.com/erp/brief.md
- Every page as Markdown: https://www.emplotec.com/llms.txt
- All tools: https://www.emplotec.com/tools.md
- /erp/inventory: https://www.emplotec.com/erp/inventory.md
- /templates/indent-format: https://www.emplotec.com/templates/indent-format.md
- /templates/grn-format: https://www.emplotec.com/templates/grn-format.md