Free templateProjects and construction
Method statement template for construction (RAMS)
A method statement sets out how a job will be done safely, step by step: the scope, the sequence, the plant and people, the permits and what to do in an emergency. Fill this one in on the page, or download it in Word or Excel.
- CDM 2015
- Sequence, plant, PPE, permits
- Briefing sign-off
- Free, no sign-up
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
Read with the risk assessment for this task. Brief every operative before work starts.
Scope of work
Sequence of work
| Step | Activity | Hazards and controls | By |
|---|---|---|---|
Plant and equipment
| Plant or equipment | Inspection or certificate | Operator competence |
|---|---|---|
PPE
Permits and checks
Emergency arrangements
Briefing record: I have read and understood this method statement
| Name | Company | CSCS or card no. | Signature | Date |
|---|---|---|---|---|
Read with the risk assessment for this task. Brief every operative before work starts.
Scope of work
Excavate and lay 110 m of 150 mm uPVC foul drain from MH3 to MH7 at depths of 1.2 to 1.8 m, bedded and surrounded in pea gravel; build two precast manholes; air test; backfill and reinstate. Not included: connections to the public sewer and road reinstatement.
Sequence of work
| Step | Activity | Hazards and controls | By |
|---|---|---|---|
Plant and equipment
| Plant or equipment | Inspection or certificate | Operator competence |
|---|---|---|
PPE
Permits and checks
Emergency arrangements
Briefing record: I have read and understood this method statement
| Name | Company | CSCS or card no. | Signature | Date |
|---|---|---|---|---|
Example entries. Go back to blank to fill in your own.
What a method statement is
A method statement describes, step by step, how a particular job will be done safely: what the work is, the order it is done in, the plant and people it needs, the precautions at each step, and what happens if something goes wrong. It is written for the people doing the work and the supervisor checking it.
On UK construction sites it usually goes with the risk assessment as RAMS: risk assessment and method statement. The risk assessment decides which controls are needed; the method statement shows how the job is done with those controls in place.
Is a method statement a legal requirement?
No law requires a document called a method statement. The law requires the thinking behind it. The Management of Health and Safety at Work Regulations 1999 require a risk assessment, and the Construction (Design and Management) Regulations 2015 require every contractor to plan, manage and monitor their own work so it is carried out safely, and to give workers the information and instructions they need.
- Principal contractors must draw up a construction phase plan before the construction phase starts, and most ask each trade for RAMS to feed into it.
- HSE expects a written safe system of work for high-risk tasks: excavations, work at height, lifting operations, demolition, confined spaces and work near live services.
- A project lasting more than 30 working days with more than 20 workers on site at the same time, or more than 500 person days of work, must be notified to HSE by the client on form F10.
What to include in a method statement
| Section | What to write |
|---|---|
| Project details | Project, client, principal contractor, site address, document reference and revision |
| Scope of work | Exactly what the task covers and what it doesn't, with drawing numbers |
| Sequence of work | Each step in order, with the hazards and controls for that step and who does it |
| Plant and equipment | What will be used, its inspection or certificate, and the competence the operator needs |
| People and competence | The supervisor, the team, the cards and training they hold |
| PPE | What must be worn, and anything beyond the site minimum |
| Permits and checks | Permits to dig, hot work, confined space or electrical isolation; inspections before and during the work |
| Emergency arrangements | First aiders, the nearest A&E, the assembly point and what to do for the likely emergencies |
| Briefing record | Signatures of everyone briefed on the method statement before they start |
How to write the sequence of work
- Write it in the order the work is done on site, from setting up to clearing away, one action per step.
- Put the controls beside the step they belong to: the trench box goes in step 2, not in a general list at the end.
- Write for the operative: short, plain sentences, the drawing numbers they need, the hold points where a supervisor must check before work continues.
- Name the role, not just the company, for each step.
High-risk work and the rules that apply
| Work | Regulations | What the method statement should show |
|---|---|---|
| Excavations | CDM 2015 | Support or battering, inspection at the start of every shift, edge protection, services located |
| Work at height | Work at Height Regulations 2005 | Why height can't be avoided, the access equipment, edge protection and rescue plan |
| Lifting operations | LOLER 1998 | The lift plan, the appointed person, slinger and signaller, and certificates in date |
| Confined spaces | Confined Spaces Regulations 1997 | Whether entry can be avoided; if not, the permit, gas testing and rescue arrangements |
| Hazardous substances | COSHH 2002 | The COSHH assessment reference and the controls it requires |
Common mistakes
- A generic method statement copied from the last job, with the wrong site, depths or plant.
- A sequence that doesn't match how the gang actually does the work.
- Emergency arrangements left blank, or the nearest A&E for a different site.
- No briefing record, so there is no proof that anyone read it.
- Not revising it when the job changes: a new depth, a new machine or a new gang means a new revision and a new briefing.
Emplotec Projects
Keep the method statement with the job it describes.
In Emplotec Projects, each subcontract has its work order, its programme and its documents on the project, so site and office work from the same revision.
- Tasks, milestones and the Gantt for each project, so the sequence of work sits in the programme.
- Subcontractor work orders on the project, with their documents kept in the document vault.
- A daily progress report from site on mobile, which works offline.
- Ask Emplotec which subcontractors start next week without approved documents, and it lists them for the site manager.
- D. Carter Trench inspected at start of shift, box in place
- D. Carter Daily report: 22 m laid, MH3 to MH4
- M. Hughes MS-GW-04 rev B briefed to 4 operatives
Drainage works on a Leeds residential job: the programme for the week and the subcontractor's documents on the project. Example companies, people and figures.
Questions people ask about the method statement format
What is a method statement in construction?
A document that sets out, step by step, how a task will be done safely: the scope, the sequence, the plant, the people, the controls and the emergency arrangements. Principal contractors usually ask for one from each trade before work starts.
What does RAMS stand for?
Risk assessment and method statement. The risk assessment identifies the hazards and the controls needed; the method statement shows how the work will be done with those controls.
Is a method statement a legal requirement?
Not by name. The law requires a risk assessment and, under CDM 2015, that contractors plan, manage and monitor their work and inform their workers. A method statement is the usual way to show that for higher-risk tasks.
What is the difference between a risk assessment and a method statement?
A risk assessment asks what could go wrong and what controls are needed. A method statement describes how the job is done, in order, with those controls built into each step.
Who should write a method statement?
The contractor doing the work, usually a supervisor or manager who knows the job, with input from the people who will do it. The principal contractor reviews and accepts it.
What is a construction phase plan?
The principal contractor's plan for managing health and safety during the construction phase, required by CDM 2015 before work starts. Contractors' method statements feed into it.
Sources
- HSE: Construction (Design and Management) Regulations 2015, duties of contractors and principal contractorshttps://www.hse.gov.uk/construction/cdm/2015/index.htm
- The Construction (Design and Management) Regulations 2015https://www.legislation.gov.uk/uksi/2015/51/contents
- HSE: Notifying a construction project (F10)https://www.hse.gov.uk/forms/notification/f10.htm
- HSE: Excavationshttps://www.hse.gov.uk/construction/safetytopics/excavations.htm