Method statement template for construction (RAMS)

A method statement sets out how a job will be done safely, step by step: the scope, the sequence, the plant and people, the permits and what to do in an emergency. Fill this one in on the page, or download it in Word or Excel.

  • CDM 2015
  • Sequence, plant, PPE, permits
  • Briefing sign-off
  • Free, no sign-up

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Method statement

Read with the risk assessment for this task. Brief every operative before work starts.

Scope of work

Sequence of work

StepActivityHazards and controlsBy

Plant and equipment

Plant or equipmentInspection or certificateOperator competence

PPE

Permits and checks

Emergency arrangements

Briefing record: I have read and understood this method statement

NameCompanyCSCS or card no.SignatureDate
Prepared by
Approved by (contractor)
Accepted by (principal contractor)

What a method statement is

A method statement describes, step by step, how a particular job will be done safely: what the work is, the order it is done in, the plant and people it needs, the precautions at each step, and what happens if something goes wrong. It is written for the people doing the work and the supervisor checking it.

On UK construction sites it usually goes with the risk assessment as RAMS: risk assessment and method statement. The risk assessment decides which controls are needed; the method statement shows how the job is done with those controls in place.

What to include in a method statement

The sections of this method statement template.
SectionWhat to write
Project detailsProject, client, principal contractor, site address, document reference and revision
Scope of workExactly what the task covers and what it doesn't, with drawing numbers
Sequence of workEach step in order, with the hazards and controls for that step and who does it
Plant and equipmentWhat will be used, its inspection or certificate, and the competence the operator needs
People and competenceThe supervisor, the team, the cards and training they hold
PPEWhat must be worn, and anything beyond the site minimum
Permits and checksPermits to dig, hot work, confined space or electrical isolation; inspections before and during the work
Emergency arrangementsFirst aiders, the nearest A&E, the assembly point and what to do for the likely emergencies
Briefing recordSignatures of everyone briefed on the method statement before they start

How to write the sequence of work

  • Write it in the order the work is done on site, from setting up to clearing away, one action per step.
  • Put the controls beside the step they belong to: the trench box goes in step 2, not in a general list at the end.
  • Write for the operative: short, plain sentences, the drawing numbers they need, the hold points where a supervisor must check before work continues.
  • Name the role, not just the company, for each step.

High-risk work and the rules that apply

WorkRegulationsWhat the method statement should show
ExcavationsCDM 2015Support or battering, inspection at the start of every shift, edge protection, services located
Work at heightWork at Height Regulations 2005Why height can't be avoided, the access equipment, edge protection and rescue plan
Lifting operationsLOLER 1998The lift plan, the appointed person, slinger and signaller, and certificates in date
Confined spacesConfined Spaces Regulations 1997Whether entry can be avoided; if not, the permit, gas testing and rescue arrangements
Hazardous substancesCOSHH 2002The COSHH assessment reference and the controls it requires

Common mistakes

  • A generic method statement copied from the last job, with the wrong site, depths or plant.
  • A sequence that doesn't match how the gang actually does the work.
  • Emergency arrangements left blank, or the nearest A&E for a different site.
  • No briefing record, so there is no proof that anyone read it.
  • Not revising it when the job changes: a new depth, a new machine or a new gang means a new revision and a new briefing.

Emplotec Projects

Keep the method statement with the job it describes.

In Emplotec Projects, each subcontract has its work order, its programme and its documents on the project, so site and office work from the same revision.

  • Tasks, milestones and the Gantt for each project, so the sequence of work sits in the programme.
  • Subcontractor work orders on the project, with their documents kept in the document vault.
  • A daily progress report from site on mobile, which works offline.
  • Ask Emplotec which subcontractors start next week without approved documents, and it lists them for the site manager.
Kirkstall Road apartmentsLeeds · project P-2614 · week 47
ProgrammeDocumentsDaily reportsDaily reportExport
EmplotecRidings Roofing starts on 1 December. Their method statement for the roof is not on the project yet.
Drainage, MH3 to MH7
Mon 16Tue 17Wed 18Thu 19Fri 20Mon 23Tue 24Wed 25
Scan and mark outAire Groundworks
Done
Lay MH3 to MH5Aire Groundworks
60 m run
Lay MH5 to MH7Aire Groundworks
50 m run
Manholes, testMH4, MH6
Test and backfill
Subcontractor documents
DocumentSubcontractorRev.Status
MS-GW-04Foul drainageAire GroundworksBApproved
RA-GW-04DrainageAire GroundworksBApproved
MS-BW-02Brick and blockWharfe BrickworkAApproved
MS-RF-01Roof and leadworkRidings RoofingNot received
Site today
  • D. Carter Trench inspected at start of shift, box in place
  • D. Carter Daily report: 22 m laid, MH3 to MH4
  • M. Hughes MS-GW-04 rev B briefed to 4 operatives

Drainage works on a Leeds residential job: the programme for the week and the subcontractor's documents on the project. Example companies, people and figures.

Questions people ask about the method statement format

What is a method statement in construction?

A document that sets out, step by step, how a task will be done safely: the scope, the sequence, the plant, the people, the controls and the emergency arrangements. Principal contractors usually ask for one from each trade before work starts.

What does RAMS stand for?

Risk assessment and method statement. The risk assessment identifies the hazards and the controls needed; the method statement shows how the work will be done with those controls.

Is a method statement a legal requirement?

Not by name. The law requires a risk assessment and, under CDM 2015, that contractors plan, manage and monitor their work and inform their workers. A method statement is the usual way to show that for higher-risk tasks.

What is the difference between a risk assessment and a method statement?

A risk assessment asks what could go wrong and what controls are needed. A method statement describes how the job is done, in order, with those controls built into each step.

Who should write a method statement?

The contractor doing the work, usually a supervisor or manager who knows the job, with input from the people who will do it. The principal contractor reviews and accepts it.

What is a construction phase plan?

The principal contractor's plan for managing health and safety during the construction phase, required by CDM 2015 before work starts. Contractors' method statements feed into it.

Sources

  1. HSE: Construction (Design and Management) Regulations 2015, duties of contractors and principal contractorshttps://www.hse.gov.uk/construction/cdm/2015/index.htm
  2. The Construction (Design and Management) Regulations 2015https://www.legislation.gov.uk/uksi/2015/51/contents
  3. HSE: Notifying a construction project (F10)https://www.hse.gov.uk/forms/notification/f10.htm
  4. HSE: Excavationshttps://www.hse.gov.uk/construction/safetytopics/excavations.htm

Stop typing method statements by hand.

Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.

WhatsApp