SOW template: statement of work with deliverables and milestones

A statement of work for one project under a master service agreement: what will be delivered, how it is accepted, when each milestone is paid, and what is out of scope. Edit it here, or download Word or Excel.

  • Under an MSA
  • Milestone fees worked out
  • Acceptance criteria per deliverable
  • Not legal advice

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Statement of work

Under master service agreement [MSA number]

1. Objective

[What this SOW delivers and for whom, in one or two sentences.]

2. Scope

In scope: [what is in scope].

3. Out of scope

[what is out of scope] Anything not listed in clause 2 is out of scope and needs a change request under clause 3 of the MSA.

4. Deliverables, acceptance and milestones

MilestoneDeliverableAcceptance criteriaDue by% of feeMilestone fee
Total fee before GST

5. Fees and payment

The fixed fee for this SOW is [fixed fee] before GST, invoiced on acceptance of each milestone at the percentage above. Payment terms are as in clause 4 of the MSA. Expenses for travel outside [city] are reimbursed at cost if approved in writing beforehand.

6. Team and responsibilities

Provider: [the Provider's team]. Client: [what the Client provides, and by when]. Delays caused by late Client inputs move the due dates by the same time.

7. Assumptions

[what the plan assumes] If an assumption proves wrong, either party may raise a change request.

8. Changes to the MSA for this SOW

[None.] / [the clause changed for this SOW only, and how] An SOW changes the MSA only where it names the clause it changes.

9. Change requests

Changes follow clause 3 of the MSA. Each change request records what changes, the effect on the due dates and fees, and who signs it. No change binds either party until it is signed by both.

For the Provider
For the Client

What a statement of work is

A statement of work (SOW) describes one project or phase: what will be delivered, how each deliverable is accepted, when, by whom and for what fee. It is usually signed under a master service agreement (MSA), which holds the legal terms, so the SOW can stay short and specific.

A good SOW is written so that two people who weren't in the meetings can tell, a year later, whether the work was done. That means deliverables a person can check, acceptance criteria written as tests, and a clear list of what is out of scope.

The sections of an SOW, explained

SectionWhat it doesWhat to watch
HeaderLinks the SOW to its MSA, dates, pricing and ownerAlways quote the MSA number: it brings in the legal terms.
ObjectiveOne or two lines on why the project existsKeeps the scope honest when trade-offs come up.
ScopeWhat will be doneUse countable items: screens, users, integrations, days of support.
Out of scopeWhat won't be doneUsually the section that prevents the most disputes.
Deliverables and milestonesWhat is handed over, how it's accepted, when and for how muchAcceptance criteria are tests. Milestone percentages should add up to 100.
Fees and paymentThe fee model and when each part is invoicedPayment days come from the MSA unless the SOW says otherwise.
Team and responsibilitiesWho does what on both sidesClient inputs with dates, so delays are attributed fairly.
AssumptionsWhat the plan relies onA wrong assumption is a reason for a change request, not a dispute.
Changes to the MSAAny MSA term this SOW alone changesName the clause, or the change has no effect.
Change requestsHow scope changes are priced and agreedNothing changes until both sign.

Stamp duty and signing in India

  • Stamp duty: an SOW signed under an MSA is usually treated as an agreement in its own right, under the state's article for an agreement "not otherwise provided for". Duty is set by the stamp act of the state where the document is signed, or first received if it is signed outside India, and it is paid before or at signing.
  • Rates differ by state and change. In Tamil Nadu, an agreement not otherwise provided for (Article 5(j)) has carried ₹200 since 3 May 2024; in Maharashtra the same kind of agreement (Article 5(h)(B)) carries ₹500 since the October 2024 amendment. Check your state's current schedule before you buy the paper.
  • E-stamping: most states issue e-stamp certificates through the Stock Holding Corporation of India (SHCIL), online or at authorised centres, and some run their own systems. The certificate carries a unique number that anyone can verify online.
  • An agreement that isn't properly stamped can't be relied on as evidence until the duty and a penalty are paid (section 35 of the Indian Stamp Act). The Supreme Court held in December 2023 that it is not void and the defect can be cured, but curing it costs more than stamping it on time.
  • Signing: the agreement can be signed on paper, with a digital signature certificate (DSC) or by Aadhaar eSign, which is an electronic signature under the IT Act, 2000. Each person signing for a company should have authority to do so, usually from a board resolution or a power of attorney.
  • Some companies sign SOWs by email or a purchase order. A signed SOW, stamped as your state requires, is easier to rely on if the work is disputed.

The steps, state by state, are in our guide to e-signing and e-stamping an agreement in India.

How to fill in this template

  1. Enter the SOW and MSA numbers, the dates, the pricing model and the client's project owner.
  2. Write the objective in a sentence, then list the scope and what is out of scope.
  3. List each milestone with its deliverable, acceptance criteria, due date and percentage of the fee. The milestone fees work themselves out from the total in the formula.
  4. Name the team and the client's inputs with their dates.
  5. Write down the assumptions, and any MSA clause this SOW changes.
  6. Have it reviewed, sign it under the MSA, and stamp it as your state requires.

Common SOW mistakes

  • Deliverables such as "portal development" with no acceptance criteria.
  • No out-of-scope list, so every new idea becomes a free change.
  • Milestones paid on dates rather than on acceptance, or the reverse with no deemed acceptance.
  • Client inputs without dates, so a late input becomes the provider's delay.
  • An SOW that quietly changes the MSA's liability cap without naming the clause.

Emplotec Contracts

Or bill each milestone the day it's accepted.

In Emplotec an SOW is a record under its MSA, inheriting its terms. Its milestones become a billing plan, and an accepted milestone releases its invoice for a person to approve.

  • An SOW inherits its MSA's liability cap and payment terms unless it names the clause it changes.
  • Milestones become a billing plan, and an accepted milestone releases its invoice for approval.
  • Change requests are versions of the SOW, compared line by line.
  • Signing with Aadhaar eSign or DocuSign, and Indian e-stamping, with signing authority checked first.
SOW-02 · Dealer portalUnder MSA/2026/007 · fixed price ₹18,00,000
SummaryObligationsDocumentsSend for signingDownload PDF
Before signingM1 accepted by Meera on 4 Feb. Its invoice of ₹3,60,000 before GST waits for approval.
Key terms
MSA
MSA/2026/007
Fee
₹18,00,000 before GST
Milestones
4, by acceptance
Payment
45 days, MSA cl. 4
Liability cap
From MSA cl. 9
Ends
30 Jun 2027
Before it goes for signing
  • M1 designs accepted4 Feb
  • M2 in testDue 15 Apr
  • M3 go-liveDue 31 May
  • M4 support endsDue 30 Jun

Emplotec M1 was accepted on 4 February, so 20% of the fee, ₹3,60,000 before GST, can be invoiced under the billing plan. The client's dealer list for M2 is due on 15 March.

SOW-02 cl. 4M1 acceptanceBilling plan
Prepare invoice

SOW-02 under Indus Stack's MSA, with M1 accepted and its invoice ready for approval. Example companies, people and figures.

Questions people ask about the SOW format

What is the full form of SOW?

Statement of work: the document that describes one project's scope, deliverables, acceptance criteria, timeline and fees, usually signed under a master service agreement.

What should an SOW include?

The MSA it sits under, the objective, scope and out of scope, deliverables with acceptance criteria and due dates, milestones and fees, the team and the client's inputs, assumptions, any MSA terms it changes, and how changes are agreed.

Is an SOW a contract?

Signed under an MSA, an SOW usually forms a contract on the MSA's terms for that project. Read clause 1 of the MSA format: it says so expressly.

What is the difference between an SOW and a purchase order?

An SOW describes the work and how it is accepted. A purchase order is the client's order to pay for it. Many clients issue a PO against a signed SOW; the MSA's order of precedence should keep the PO's printed terms from overriding the agreed ones.

Sources

  1. Indian Contract Act, 1872, India Codehttps://www.indiacode.nic.in/
  2. Indian Stamp Act, 1899, India Codehttps://www.indiacode.nic.in/
  3. Information Technology Act, 2000, India Codehttps://www.indiacode.nic.in/
  4. E-stamp certificates and verification, Stock Holding Corporation of Indiahttps://www.shcilestamp.com/
  5. Tamil Nadu stamp duty revision from 3 May 2024 (JSA)https://www.jsalaw.com/newsletters-and-updates/recent-amendments-made-to-the-stamp-duty-payable-on-various-instruments-in-tamil-nadu
  6. Maharashtra Stamp Act amendments, October 2024 (Khaitan & Co)https://www.khaitanco.com/thought-leaderships/Amendments-to-Maharashtra-Stamp-Act-An-Effort-to-Increase-Revenue
  7. Unstamped agreements: the seven-judge bench, December 2023 (JSA)https://www.jsalaw.com/newsletters-and-updates/jsa-prism-dispute-resolution-december-2023/

Stop typing SOWs by hand.

Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.

WhatsApp