GuideProjects and construction · 9 min read

Retention money in construction: rates, release, bank guarantees and accounting

What retention money is, how much is held and when it comes back, how to replace it with a bank guarantee, and how contractors and clients account for it, with Indian, UK and US practice.

Last updated

What is retention money?

Retention money is a part of each payment that the client holds back from a contractor as security for completing the work and fixing defects. It is deducted from every running account (RA) bill, held until the work is complete, and released in stages, the last after the defect liability period. In government contracts it is often called security deposit. The money still belongs to the contractor; the client simply holds it until the contract's conditions are met.

Retention exists because the client has less hold over the contractor as the work nears completion. If the contractor leaves defects or abandons the job, the client can use the retention to pay someone else to finish or repair. The same logic runs down the chain: a main contractor holds retention from its subcontractors, usually on the same terms the client applies to it.

TermMeaning
Retention moneyThe share of each bill held back until completion and the defect liability period
Security depositThe government contract term for the same thing, sometimes combined with an earnest money deposit
Performance guaranteeA separate bank guarantee for performance of the contract, given at the start; not the same as retention
Defect liability period (DLP)The period after completion, often 12 months, during which the contractor must fix defects at its own cost
RetainageThe US term for retention

How much retention is held?

Retention is set by the contract, not by law in India. The common pattern is 5% to 10% of each RA bill, with a cap on the total held, often 5% of the contract value. Once the cap is reached, later bills are paid without retention. Some contracts deduct retention on the work value, others on the gross bill including GST; the contract says which.

MarketTypical retentionRelease
India, private building and industrial5% to 10% of each bill, capped at 5% of contract valueHalf on completion, half after the DLP, or all after the DLP
India, government worksSecurity deposit deducted from each bill as the tender documents setAfter the DLP and the final bill, on the engineer's certificate
UKCommonly 3% to 5%Half at practical completion, half at the end of the rectification period
USCommonly 5% to 10% (retainage)Often reduced after 50% completion; many states limit retainage on public work

A worked example: retention on a ₹4.2 crore contract

Sri Venkata Builders Pvt Ltd (an example company) has a ₹4.2 crore contract for a factory shed. The contract deducts 5% retention on the work value of each RA bill, capped at 5% of the contract value (₹21 lakh). Half is released on the completion certificate and half after a 12-month defect liability period.

StageWork value (₹)Retention this stage (₹)Retention held (₹)
RA bills 1 to 62,13,24,50010,66,22510,66,225
RA bill 766,11,2503,30,56313,96,788
RA bills 8 to 101,30,25,0006,51,25020,48,038
Final bill10,39,25051,962 (reaches the ₹21 lakh cap)21,00,000
Completion certificate, 31 March 2027Release 10,50,00010,50,000
End of DLP, 31 March 2028Release 10,50,0000

At the final bill, ₹21 lakh of the contractor's money is with the client: more than the profit on many contracts of this size. That is why retention deserves its own register, with dates, and not a line buried in the debtor's ledger.

When and how retention is released

  1. Complete the work and get the completion certificate (practical completion in the UK). Note its date; the DLP runs from it.
  2. Claim the first half if the contract releases it on completion. Attach the certificate.
  3. During the DLP, fix every defect notified, in writing, and keep the closure records signed by the client.
  4. At the end of the DLP, ask for the defects liability certificate or a no-defects letter.
  5. Raise the claim for the balance retention with the certificate and the final bill reference.
  6. Follow up as an overdue receivable from the due date. Retention not claimed is often simply never paid.

Clients may withhold release for defects not fixed, for recoveries on the final bill, or because a subcontractor has a claim against the main contractor that the client has heard about. Keep defect closure records and the final bill settlement on file; they are what releases the money.

Bank guarantee in lieu of retention

Many contracts let the contractor replace cash retention with a bank guarantee (BG) for the same amount, either from the start or once retention reaches its cap. The client gets the same security; the contractor gets the cash.

Cash retentionBank guarantee in lieu
Cash flowHeld for the whole period, often 2 to 3 yearsReleased to the contractor when the BG is accepted
CostThe interest on money you don't haveThe bank's commission, and the BG uses up your non-fund limit
Security for the bankNone neededOften a margin deposit or a charge on assets
RiskClient may delay releaseClient may invoke the BG; it must be renewed if the DLP is extended
ClosingPayment by the clientReturn of the original BG and the bank's release
  • Match the BG's validity to the DLP plus the claim period the contract allows, usually a few months beyond the DLP.
  • Track expiry dates: a BG that lapses while the contract still needs it is a breach, and a BG not returned keeps eating your limit.
  • Show open guarantees as contingent liabilities in the notes to accounts.

Accounting for retention money

Retention is part of the contract price, so the contractor recognises the revenue as the work is done, including the retained amount. Retention is not a discount or a cost. The question is only where the retained amount sits in the balance sheet until it is paid.

Contractor's entries for RA bill 7 (₹)
EntryDebitCredit
Raise the billClient 78,01,275Contract revenue 66,11,250; output GST 11,90,025
Record retention heldRetention receivable 3,30,563Client 3,30,563
Record TDS and other deductionsTDS receivable 1,32,225; mobilisation advance 8,26,406; cess expense 66,113Client 10,24,744
Receive paymentBank 64,45,968Client 64,45,968
Release after DLPBank (amount released)Retention receivable
  • Ind AS 115: a receivable is a right to consideration that is unconditional except for the passage of time. Retention that depends on completing the work or passing the DLP is usually presented as a contract asset until the condition is met; agree the treatment with your auditor.
  • Financing component: Ind AS 115 (paragraph 62(c)) treats retention held to protect the client against incomplete work as not usually a significant financing component, so it is not discounted.
  • Provision: if part of the retention is unlikely to be recovered because of defects or disputes, provide for it; don't carry it at full value for years.
  • Client's books: the retained amount is a liability (retention payable) to the contractor until released, and the full work value is capitalised or expensed as the work is done.

GST and TDS on retention money

TaxWhen it applies to the retained amountPractice
GSTWhen the invoice is raised for the full certified value, or by the due date of payment in the contract for a continuous supplyMost RA bills invoice the full value and show retention as a deduction from the amount payable, so GST on the retention is paid with the bill, long before the money is received
Income-tax TDSAt credit or payment, whichever is earlier, on the full sum credited to the contractorThe client deducts TDS on the full work value, including the part retained, under section 393(1) of the Income-tax Act 2025 (formerly section 194C)
GST TDS (government clients)On payment, at 2% of the taxable valueDeducted on the amount actually paid; check how your client's accounts treat the retained amount

Some contracts make the retention payable only on a future event and invoice it separately when it falls due. Then GST on it is charged on that later invoice. Which one applies depends on your contract and how you invoice, so agree it with the client's accounts team at the start and keep it the same for every bill.

Common problems with retention, and how to avoid them

  • Nobody tracks the DLP end date, so the claim goes in a year late or not at all. Keep a retention register: project, client, amount held, completion date, DLP end, claim date, status.
  • Subcontractors' retention is released before the client releases yours. Make subcontract retention back-to-back with the main contract.
  • Retention is deducted beyond the contract's cap. Check every RA bill against the cap.
  • A BG in lieu expires, or is never returned after the DLP. Track BG expiries and returns beside the retention.
  • Defects closed on the phone, not in writing. Get each closure signed; it is the evidence for release.
  • Retention written off quietly years later. Review old retention every quarter and either claim it or provide for it.

Emplotec Projects

Or see every rupee of retention, project by project.

In Emplotec Projects, retention and mobilisation advances are tracked on both sides of every contract: what your clients hold from you and what you hold from your subcontractors.

  • Subcontractor RA bills deduct retention, advance and free-issue recovery, TDS and labour cess from the certified quantities.
  • With Billing, retention held and advances left to recover show per project, beside billed and unbilled work.
  • With Books, bank guarantees issued and received are recorded with their limits, and open guarantees show as contingent liabilities.
  • Ask Emplotec which retentions fall due this quarter, and it lists them with the certificates you need to claim them.
RetentionAs on 6 Nov 2026
ClientsSubcontractorsGuaranteesClaim releaseExport
Held by clients₹1.42Cr
Due for release₹38.6L3 projects
Overdue claims₹11.4LDLP ended
From subcontractors₹46.2L
Retention held by clients
ProjectHeldDLP endsStatus
Warehouse, SriperumbudurCoastal Logistics Parks₹11,40,000Sep 2026Overdue
Office block, GuindyAnand Realty₹16,20,000Dec 2026Claim in Dec
Factory shed, OragadamRA bill 7₹13,96,788Under workAccruing
School block, TambaramBG in lieu, ₹11 L₹0Jan 2027BG active
Sriperumbudur warehouse release
  • Completion certificate, 30 Sep 2025
  • Final bill settled
  • 14 defects closed and signed
  • Defects liability letterAsked 2 Oct

Emplotec The Sriperumbudur warehouse DLP ended on 30 September and ₹11.4 lakh is still held. All 14 defects are closed and signed. Draft the release claim for RN to send?

Completion certificate CC-0925Defect log DL-118Final bill FB-31
Draft the claim

Retention held by clients and from subcontractors, with release dates and guarantees. Example companies, people and figures.

Questions people ask

What is the normal percentage of retention money?

In India, 5% to 10% of each running bill, usually capped at 5% of the contract value. In the UK 3% to 5% is common, and US retainage is commonly 5% to 10%.

When is retention money released?

Usually half on the completion certificate and the rest after the defect liability period, often 12 months, once defects are closed. Some contracts release all of it only after the defect liability period.

Can retention money be replaced by a bank guarantee?

Yes, if the contract allows it. The contractor gives a bank guarantee for the retention amount, valid until the end of the defect liability period plus the claim period, and the client releases the cash.

Is GST payable on retention money?

Yes. When the invoice is raised for the full certified value, GST on the retained part is paid with that invoice. If the contract invoices retention separately when it falls due, GST is charged on that later invoice.

Is TDS deducted on retention money?

Yes. TDS is deducted when the bill is credited to the contractor's account or paid, whichever is earlier, on the full sum including the retained part. From 1 April 2026 the section is 393(1) of the Income-tax Act 2025, formerly 194C.

Is retention money an asset or a liability?

For the contractor it is an asset: a contract asset while it depends on completing the work or the defect period, and a receivable once only time remains. For the client it is a liability, retention payable, until it is released.