RA bill format: running account bill in Excel with formulas

A running account bill claims payment for the work done since the last bill, measured against the BOQ, less the deductions the contract and the law ask for. Fill this one in on the page, or download it with every amount worked out.

  • Cumulative method
  • A4 landscape
  • Deductions worked out
  • Free, no sign-up

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Original for client
Running account bill

Measured against the contract BOQ. Amounts in rupees.

Contractor

Client

Abstract of measured work

BOQ itemDescriptionUnitRateContract qtyPrevious qtyThis bill qtyUp-to-date qtyPrevious amountThis bill amountUp-to-date amount
Total

Bill summary and deductions

Value of work in this bill (total of 'This bill amount')
GST rate (%)
GST
Gross amount of this bill
Retention (%)
Retention money
Security deposit (%), if deducted apart from retention
Security deposit
Mobilisation advance recovered
Income-tax TDS (%), Section 393 (formerly 194C)
Income-tax TDS
GST TDS (%), government clients only
GST TDS
Labour cess (%), where the client deducts it
Labour cess
Other recoveries (material issued, water, power)
Total deductions
Net amount payable

Certificate

Certified that the work billed has been done as per the contract and measured in the measurement book referred to above, and that no part of it has been billed before. The client's engineer certifies the quantities; payment is made on the certified amount.

Contractor, authorised signatory
Measured and checked by (client's engineer)
Certified for payment

What an RA bill is

An RA bill, or running account bill, is the interim bill a contractor raises while the work is still going on, usually every month. It claims payment for the work done since the last bill, measured against the BOQ items and paid at the BOQ rates. Each bill is numbered in sequence: RA-01, RA-02 and so on, until the final bill closes the account.

Running bills are on-account payments. The client pays what its engineer certifies, but the account is settled only at the final bill, when the full quantities are measured and every advance, retention and recovery is squared up. For the full process, read our guide to RA bills.

What an RA bill format must contain

Contents of a running account bill.
PartWhat goes in it
HeaderRA bill number, date, the period of work it covers, the contract number and value, and the measurement book reference.
PartiesContractor and client with their addresses, GSTINs and the contractor's PAN. If the RA bill is also your tax invoice, it must carry everything a GST invoice needs.
Abstract of workEach BOQ item with its rate and contract quantity, the quantity billed up to the previous bill, the quantity in this bill and the total up to date, with the amount for each.
SummaryThe value of work in this bill, GST on it, and the gross amount.
DeductionsRetention or security deposit, advance recoveries, income-tax TDS, GST TDS for government clients, labour cess where deducted, and other recoveries.
Net payableThe gross amount less the deductions.
Certificate and signaturesThe contractor's certificate, and the client engineer's measurement and certification.

How to calculate an RA bill: the cumulative method

Most contracts bill cumulatively: each bill shows the work done up to date, takes off what was paid in earlier bills, and pays the difference. That way an error in an earlier bill is corrected in the next one instead of carried forever.

  1. For each BOQ item, take the previous quantity from the last bill.
  2. Add this period's measured quantity, from the measurement book, to get the up-to-date quantity.
  3. Multiply each quantity by the BOQ rate. The format works out the previous, this-bill and up-to-date amounts.
  4. Carry the total of 'This bill amount' to the summary, and add GST.
  5. Work out each deduction at the rate your contract and the law set, and subtract the total to get the net payable.

Deductions in an RA bill, and the rule behind each

Common deductions from a running account bill. The contract decides the rates for retention, security deposit and advances.
DeductionUsual basisWhere it comes from
Retention moneyA percentage of each bill, often 5% to 10%, released after the defects liability periodThe contract. Read our guide to retention money.
Security depositA percentage of each bill until it reaches the amount the contract sets; some contracts accept a bank guarantee insteadThe contract. Government works follow the department's own conditions.
Mobilisation advance recoveryThe advance paid at the start, recovered in instalments from running bills, with interest where the contract charges itThe contract. CPWD's manual allows up to 10% of the tendered amount at 10% simple interest.
Income-tax TDS1% where the contractor is an individual or HUF, 2% for othersSection 393(1) of the Income-tax Act, 2025, table serial 6 (formerly Section 194C), for amounts paid or credited from 1 April 2026
GST TDS2% (1% CGST and 1% SGST, or 2% IGST) of the taxable valueSection 51 of the CGST Act, for government departments and notified bodies, where the contract value is over ₹2.5 lakh
Labour cess1% of the cost of constructionSection 100 of the Code on Social Security, 2020 (formerly the BOCW Welfare Cess Act), as notified; how it is collected follows the state's rules
Other recoveriesMaterial issued by the client, water, power, hire of client equipment, penaltiesThe contract

GST on RA bills

  • A works contract is a supply of services under GST. Since 22 September 2025 most works contracts are taxed at 18%, including government works that were earlier at 12%. Some residential and other entries carry different rates, so check the entry that covers your contract.
  • If your RA bill is also your tax invoice, it must have everything Rule 46 of the CGST Rules asks for: invoice number and date, both GSTINs, place of supply, SAC, taxable value and tax.
  • Many contractors raise the tax invoice on the amount the client certifies, not the amount claimed, so GST is not paid on work the client later cuts.

RA bill and final bill compared

RA billFinal bill
WhenEvery month or at agreed stages while work goes onOnce, after the work is complete
QuantitiesMeasured up to date, can be corrected laterFinal measured quantities of every item
PaymentOn account, of the certified amountSettles the account
RetentionDeductedShown as held; released after the defects period
AdvancesRecovered in instalmentsAny balance recovered in full

Common mistakes in RA bills

  • Previous quantities that don't match the last certified bill, so the cumulative figures drift.
  • Billing extra items before the variation is approved. They are cut, and the bill is delayed.
  • Retention worked out on the GST-inclusive amount when the contract says on the value of work, or the other way round.
  • Forgetting the mobilisation advance recovery until the last few bills, when there isn't enough left to recover it.
  • No measurement book reference, so the client's engineer has to measure the work again before certifying.

Emplotec Projects

Or bill from the measurements, not a spreadsheet.

In Emplotec the RA bill is drawn from the work measured against the BOQ. Previous, this-bill and up-to-date quantities fill themselves in, and retention and advance recoveries come from the contract's own terms.

  • With Billing, measured quantities become the RA bill, and the client's certified figure is recorded against what was claimed.
  • Work certified short stays visible as unbilled, so it is billed again once it is measured.
  • Retention held and advances left to recover are tracked for each contract, bill by bill.
  • Subcontractor RA bills come in against their work orders on the project, beside the work the DPRs recorded.
Client RA bills · Block CContract MHPL/CIV/2025/014 · Medvista Hospitals
RA-08All billsNew RA bill
With the PMCRA-08 was claimed on 2 Nov at ₹61.12 L of work. Measurement check booked for 5 Nov.
Measured₹61.12 LMB 14, from the DPRs
Claimed₹72.12 LWith GST, 2 Nov
CertifiedDue 5 NovPMC check
InvoicedPendingOn certification
Received₹64.86 LNet, if certified in full
Running account billRA-08
Awaiting certification
Client
Medvista Hospitals Pvt Ltd
Period
1 to 31 Oct 2026
Measurement
MB 14, pages 22 to 31
Contract
MHPL/CIV/2025/014
ItemThis billUp to dateAmount
B.2 RCC M30, slabs and beams186 m³3,860 m³₹16,64,700
B.3 Reinforcement Fe 550D51.6 t412.0 t₹40,50,600
C.1 AAC blockwork 200 mm64 m³436 m³₹3,96,800
Work this bill
₹61,12,100
GST at 18%
₹11,00,178
Less deductions
₹7,26,347
Net payable
₹64,85,931
Contract to date
Billed, up to date
₹6.96 Cr
Retention held
₹34.8 L
Advance left to recover
₹42.5 L
Measured, not billed
₹22.8 L

Emplotec RA-07 was certified ₹22.8 L short for 29 t of slab 4 steel not yet measured. It was measured on 28 Oct and isn't in RA-08. Add it before the PMC's check?

RA-07MB 14 p. 19DPR/P-2411/0276
Add to RA-08

RA bill 8 for one hospital block: claimed, certified and invoiced, with retention and the advance tracked. Example companies, people and figures.

Questions people ask about the RA bill format

What is the full form of RA bill?

RA bill stands for running account bill: an interim bill for the work done since the last bill, paid on account until the final bill settles the contract.

How is an RA bill calculated?

Most contracts use the cumulative method. Work out the up-to-date amount of every BOQ item, take off what earlier bills covered, add GST to the difference, and subtract retention, advance recoveries, TDS and other deductions to get the net payable.

What is the TDS rate on an RA bill?

Income-tax TDS on payments to contractors is 1% for individuals and HUFs and 2% for others, now under Section 393(1) of the Income-tax Act, 2025 (formerly Section 194C). Government clients also deduct GST TDS at 2% under Section 51 of the CGST Act.

Is retention money deducted from every RA bill?

Usually yes, at the percentage the contract sets, until the total retention reaches any cap the contract gives. It is released after the defects liability period, sometimes half at completion and half at the end of that period.

What is the GST rate on an RA bill for construction work?

Most works contracts are taxed at 18% since 22 September 2025, when the 12% rate for government works contracts was withdrawn. Residential projects and a few other entries carry different rates, so check the entry for your contract.

What is the difference between an RA bill and a measurement book?

The measurement book records the measured dimensions and quantities of work, signed by the engineer who measured them. The RA bill takes those quantities, prices them at the BOQ rates and claims payment.

Sources

  1. Income Tax Department: FAQs on interplay and transition to the Income-tax Act, 2025https://www.incometaxindia.gov.in/documents/d/guest/faqs-on-interplay-and-transition-pdf
  2. Income Tax Department: TDS rates (Section 194C, carried into Section 393)https://wm.incometaxindia.gov.in/w/tds-rates-1
  3. CGST Act, 2017: Section 51 (TDS) and Rule 46 (tax invoice), CBIC tax information portalhttps://taxinformation.cbic.gov.in/
  4. The Code on Social Security, 2020, Section 100 (building workers cess), India Codehttps://www.indiacode.nic.in/bitstream/123456789/16823/1/aA2020-36.pdf
  5. CPWD Works Manual 2022 (as hosted by NDMC)https://www.ndmc.gov.in/departments/Departments/Finance/nodal_cell/CPWD%20Works%20Manual%202022.pdf

Stop typing RA bills by hand.

Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.

WhatsApp