Free templateProjects and construction
BOQ format: bill of quantities template in Excel and PDF
A bill of quantities lists every item of work in a contract with its unit, quantity and rate, so every bidder prices the same work and every bill is measured against it. Fill this one in on the page, or download it.
- Measured to IS 1200
- A4 portrait
- Excel with formulas
- Free, no sign-up
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
Quantities measured as per IS 1200. Rates exclude GST.
| Item no. | Description of item | Unit | Quantity | Rate (₹) | Amount (₹) |
|---|---|---|---|---|---|
| Total carried to summary | |||||
Summary of bill
| A. Earthwork | |
|---|---|
| B. Concrete work | |
| C. Masonry | |
| Total, excluding GST | |
| GST rate (%) | |
| GST | |
| Total, including GST |
Notes
Quantities are measured net from the drawings as per the relevant part of IS 1200, unless the item says otherwise. Rates include material, labour, plant, wastage, overheads and profit, and exclude GST. Read the preambles and specifications with each item.
Quantities measured as per IS 1200. Rates exclude GST.
| Item no. | Description of item | Unit | Quantity | Rate (₹) | Amount (₹) |
|---|---|---|---|---|---|
| 3,53,400.00 | |||||
| 1,02,300.00 | |||||
| 6,19,200.00 | |||||
| 8,41,30,000.00 | |||||
| 7,92,85,000.00 | |||||
| 1,33,30,000.00 | |||||
| Total carried to summary | 17,78,19,900.00 | ||||
Summary of bill
| A. Earthwork | |
|---|---|
| B. Concrete work | |
| C. Masonry | |
| Total, excluding GST | 17,78,19,900.00 |
| GST rate (%) | |
| GST | 3,20,07,582.00 |
| Total, including GST | 20,98,27,482.00 |
Notes
Quantities are measured net from the drawings as per the relevant part of IS 1200, unless the item says otherwise. Rates include material, labour, plant, wastage, overheads and profit, and exclude GST. Read the preambles and specifications with each item.
Example entries. Go back to blank to fill in your own.
What a BOQ is
A BOQ, or bill of quantities, is a list of every item of work in a construction contract: what it is, how it is measured, how much of it there is, and what it costs per unit. The client's engineer or quantity surveyor prepares it from the drawings and specifications, and bidders fill in their rates.
Because every bidder prices the same quantities, bids can be compared line by line. After the award, the priced BOQ becomes the basis for payment: each running bill measures the work done against the BOQ items and pays it at the BOQ rates.
What a BOQ format contains
| Part | What it holds |
|---|---|
| Item number | A unique number, usually by section: A.1, A.2, B.1. The same number is used in every bill and measurement. |
| Description | What the work is, its materials, its specification and where it applies, in enough words that only one price makes sense. |
| Unit | The unit the item is measured and paid in: m³, m², m, kg or t, nos, or a lump sum. |
| Quantity | The quantity measured from the drawings. |
| Rate | The bidder's price per unit, including material, labour, plant, overheads and profit. |
| Amount | Quantity times rate. The Excel format calculates it. |
| Sections | Items grouped by trade or by part of the building: earthwork, concrete, masonry, finishes, plumbing, electrical. |
| Summary | Each section's total carried to one page, with GST shown separately. |
| Preambles and notes | How items are measured, what rates include, and the specifications they refer to. |
Larger BOQs also carry provisional sums (an allowance for work not yet designed), prime cost sums (for items bought from a named supplier) and a dayworks schedule (rates for labour and plant used on unmeasured work).
IS 1200: how quantities are measured in India
IS 1200 is the Bureau of Indian Standards' method of measurement of building and civil engineering works. It comes in parts, one per trade, such as Part 1 for earthwork, Part 3 for brickwork and Part 5 for formwork. Each part sets the units, what is deducted (openings, for example), what is included in the rate and how the item should be described.
- Earthwork, concrete and masonry are usually measured in cubic metres.
- Plaster, flooring, painting and formwork are usually measured in square metres.
- Reinforcement steel is usually measured by weight, in kilograms or tonnes.
- Pipes, cables and skirting are measured in running metres, and fittings and fixtures in numbers.
How to prepare a BOQ
- Split the work into sections, by trade or by part of the building.
- Take off quantities from the drawings into measurement sheets, with dimensions, numbers and deductions, so anyone can check them.
- Write each item's description to the specification and the measurement standard, and give it a number and a unit.
- Carry the measured quantities into the BOQ. Round only at the end.
- Leave rates blank for a tender BOQ. For an estimate, use the schedule of rates you work to, or a rate analysis.
- Total each section, carry the totals to the summary, and add GST at the rate that applies to the contract.
BOQ, estimate, schedule of rates and bill of materials compared
| BOQ | Estimate | Schedule of rates | Bill of materials | |
|---|---|---|---|---|
| What it lists | Items of work with quantities | Items of work with quantities and rates | Rates for standard items, no quantities | Materials needed, by quantity |
| Prepared by | The client's engineer or QS | The client or the contractor | A department, such as CPWD or a state PWD | The contractor or the manufacturer |
| Used for | Tendering and paying for work | Budgeting and sanction | Pricing estimates and variations | Buying material |
In an item-rate contract, the BOQ quantities are estimates and you are paid for what is measured. In a lump-sum contract, the BOQ is often only a guide for pricing changes, and the risk on quantities sits with the contractor.
Bill of quantities in the UK: NRM2
In the UK, bills of quantities for building works are measured to RICS NRM2 (New Rules of Measurement: detailed measurement for building works), which replaced SMM7 in 2013. JCT contracts name NRM2 as the default measurement rules. Civil engineering works are usually measured to CESMM4 instead. The format above works for either: change the basis of measurement in the heading and the units where needed.
Common mistakes in a BOQ
- Vague descriptions, such as "concrete work as required". Each bidder prices something different, and every bill becomes an argument.
- Leaving out items the drawings show. They come back later as extra items at new rates.
- Mixing units: blockwork in m³ in one section and m² in another.
- Quantities with no measurement sheets behind them, so nobody can check or correct them.
- Rates that include GST in one item and exclude it in another.
Emplotec Projects
Or run the project from the BOQ you signed.
In Emplotec Projects the contract BOQ becomes the project's budget, item by item. Every receipt, issue, DPR entry and bill afterwards is booked against it, so the gap between the BOQ and the site shows while there's still time to act.
- BOQ items map to the work breakdown and cost codes, with a budget by cost type for each.
- Extra items and changed quantities come in as change orders, and count only once they are approved.
- Site stores and DPRs post against BOQ items, so material is reconciled against the BOQ and progress is measured from it.
- With Billing, measured quantities against each BOQ item become the RA bill, with the client's certification recorded.
- CO-01 · lift pit deepenedA.1 +22 m³
- CO-02 · OT floor slabB.2 +40 m³
- CO-03 · basement waterproofingWith client
Emplotec B.3 steel is running at 6% wastage against 3% allowed. At this rate it ends 31 t over what the BOQ allows, about ₹24 L. Most of the gap is on slab 4 offcuts. Ask the rebar crew for a cutting plan before slab 6?
IS-2290DPR/P-2411/0287BBS rev 4The contract BOQ for one hospital block, against what has been executed and what has changed. Example companies, people and figures.
Questions people ask about the BOQ format
What is the full form of BOQ?
BOQ stands for bill of quantities: the list of items of work in a contract, each with its description, unit, quantity, rate and amount.
Who prepares the BOQ?
The client's engineer, architect or quantity surveyor prepares it from the drawings and specifications. Contractors price it at tender, and the priced BOQ becomes part of the contract.
Is GST included in BOQ rates?
It should be stated either way. Most BOQs ask for rates excluding GST and add GST on the summary at the rate that applies to the contract, which keeps a rate change from touching every item.
What is the difference between a BOQ and an estimate?
A BOQ lists quantities for bidders to price and is used to pay for work. An estimate adds rates to the quantities to work out what the project should cost, for budgeting and sanction before the tender.
What is IS 1200?
IS 1200 is the Indian Standard method of measurement of building and civil engineering works, published by BIS in trade-wise parts. It sets the units, deductions and what each rate covers, so quantities are measured the same way by everyone.
What happens when the executed quantity is more than the BOQ quantity?
In an item-rate contract the measured quantity is paid at the BOQ rate, up to the variation limit the contract sets. Beyond that limit, or for items not in the BOQ, a rate is agreed as a variation or extra item.
Sources
- Bureau of Indian Standards: IS 1200, method of measurement of building and civil engineering workshttps://www.services.bis.gov.in/php/BIS_2.0/bisconnect/knowyourstandards/Indian_standards/isdetails_mnd/3223
- RICS: NRM 2, detailed measurement for building workshttps://www.rics.org/content/dam/ricsglobal/documents/standards/nrm_2_detailed_measurement_for_building_works_1st_edition_rics.pdf
- JCT: New Rules of Measurement updatehttps://www.jctltd.co.uk/new-rules-measurement
- Central Public Works Department: schedules of rates and specificationshttps://cpwd.gov.in/
Related
Stop typing BOQs by hand.
Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.