Free templateProjects and construction
DPR format for construction sites: daily progress report in Excel and PDF
A daily progress report records what happened on site today: who worked, what machines ran, how much work was done against the plan, what material came in and what held the work up. Fill this one in on the page, or download it.
- One page a day, per site
- A4 landscape
- Excel with formulas
- Free, no sign-up
Written for India. Elsewhere:Daily construction report template US
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
One report per site per day, signed by the site engineer and the project manager
Manpower on site (nos)
Machinery and equipment
Hindrances and safety
Work done today against the plan
| Sr. | BOQ item and activity | Location | Unit | BOQ qty | Planned today | Done today | Up to yesterday | Up to date | % of BOQ | Short of plan |
|---|---|---|---|---|---|---|---|---|---|---|
Materials received and used today
| Sr. | Material | Supplier and challan | Unit | Opening stock | Received | Used | Closing stock | Remarks |
|---|---|---|---|---|---|---|---|---|
Plan for tomorrow
Write the work planned for the next day, the manpower and machines it needs, and anything the client or PMC must clear first (drawings, inspections, approvals). Attach dated photos of today's work.
One report per site per day, signed by the site engineer and the project manager
Manpower on site (nos)
Machinery and equipment
Hindrances and safety
Work done today against the plan
| Sr. | BOQ item and activity | Location | Unit | BOQ qty | Planned today | Done today | Up to yesterday | Up to date | % of BOQ | Short of plan |
|---|---|---|---|---|---|---|---|---|---|---|
| 412 | 40.79% | 2.60 | ||||||||
| 436 | 20.28% | -2 | ||||||||
| 10,140 | 26.68% | -40 | ||||||||
Materials received and used today
| Sr. | Material | Supplier and challan | Unit | Opening stock | Received | Used | Closing stock | Remarks |
|---|---|---|---|---|---|---|---|---|
| 41 | ||||||||
| 730 | ||||||||
Plan for tomorrow
Write the work planned for the next day, the manpower and machines it needs, and anything the client or PMC must clear first (drawings, inspections, approvals). Attach dated photos of today's work.
Example entries. Go back to blank to fill in your own.
What a DPR is on a construction site
A DPR, or daily progress report, is the site's record of one working day. The site engineer fills it in at the end of the shift: the workers on site by trade, the machines that ran, the work done against the day's plan, the material received and used, the weather, and anything that stopped the work.
It is not a legal form with a fixed layout. Its fields come from the contract and from practice. But it is the document everyone reaches for later: the project manager to see whether the site is on plan, the quantity surveyor to measure work for the running bill, and both sides when there is an argument about delay.
What a daily progress report should contain
The format above has a place for each of these, in the order a site engineer usually works through the day.
| Section | What to record |
|---|---|
| Header | Project, client, contract or work order number, report number, date, weather and working hours. |
| Manpower | Workers on site by trade, and by subcontractor if more than one is working. Count heads, not the gang leader's estimate. |
| Machinery | Each machine with the hours it worked, the hours it stood idle and why, and any breakdown. |
| Work done | Each activity against its BOQ item, with the location, the quantity planned for today, the quantity done and the total to date. |
| Materials | What came in (supplier and challan number), what was used and what is left. |
| Hindrances | Anything that stopped or slowed work, with the start and end time: rain, drawings not issued, a client decision, power, a site access problem. |
| Safety | The toolbox talk given, incidents, near misses, and any unsafe condition noticed and fixed. |
| Instructions and visitors | Instructions from the client, the architect or the PMC, and who visited. |
| Plan for tomorrow | The work planned for the next day and what it depends on. |
How to fill in this DPR format
- Fill in the header once for the project; change the report number, date and weather each day.
- Count manpower at a fixed time, usually after the morning roll call, and enter it by trade.
- For each machine, enter hours worked and the reason for any idle time. Idle time with a reason is what supports a claim later.
- For each activity, enter the BOQ item, the location, the quantity planned for today and the quantity done. Enter the total up to yesterday from the previous report. The Excel version works out the total to date, the percentage of the BOQ quantity and the shortfall against today's plan (a negative shortfall means you are ahead).
- Enter the material received with the supplier's challan number, and the quantity used. The closing stock is worked out for you.
- Write every hindrance with its start and end time, the toolbox talk topic and any near miss.
- Sign it, get the project manager's signature, and send a copy to the client or PMC the same evening if the contract asks for it.
Why hindrances in the DPR matter for extension of time
When a project runs late, the contractor asks for an extension of time and the client asks for liquidated damages. Who wins usually depends on what was written down on the day, not what people remember a year later.
- Record each hindrance with the date, the start and end time, the area affected and who caused it: the client, the weather, a supplier or your own crew.
- On CPWD works, and on many other government contracts, the department keeps a hindrance register and decides extension of time from it. Make sure every hindrance in your DPR is also in that register, with the same dates and hours.
- Note drawings and decisions awaited every day they are pending, not only the day you first asked.
DPR, site diary, weekly report and measurement book compared
| DPR | Site diary | Weekly or monthly report | Measurement book | |
|---|---|---|---|---|
| Kept by | The contractor's site engineer | The site engineer, or the client's engineer | The project manager | The engineer who measures, usually the client's |
| Records | Manpower, machines, work, materials, hindrances | Events, instructions and visits, in prose | Progress against the schedule, cost, risks | Measured quantities of work, item by item |
| Used for | Daily control, delay records, cost booking | Evidence of what happened | Client and management review | Running account bills |
| Frequency | Every working day | Every working day | Weekly or monthly | Whenever work is measured |
Many sites combine the DPR and the site diary into one document, which this format does with its hindrances and instructions block. The measurement book stays separate: it is what running account bills are paid on.
Common mistakes in daily progress reports
- Copying yesterday's manpower figures forward. Labour cost and subcontractor bills are checked against these numbers.
- Writing work done without the BOQ item. Progress that can't be tied to an item can't be measured or billed.
- Filing the report two days late from memory. It loses its value as evidence.
- Leaving out idle machines and the reason. Idle hours are cost, and often someone else's fault.
- Recording material received but not material used, so stock on site and wastage are never known until the reconciliation at the end.
Emplotec Projects
Or file the DPR from the site, on a phone.
In Emplotec Projects the site engineer files the day's report on the mobile app, offline if the site has no signal. Work, labour, machines and material post to the project as they are entered, so nobody retypes the DPR into a spreadsheet at night.
- Work done is entered against BOQ items and cost codes, so progress, earned value and the S-curve update from the same entries.
- Material received and issued comes from the site store, and consumption is reconciled against the BOQ.
- Subcontractor work orders sit on the project, so each crew's work in the DPR is there when their RA bill comes in.
- Emplotec drafts the weekly client report from the week's DPRs, for the project manager to check and send.
- Manpower counted at roll call
- TC-2 hours logged, 9.5 h
- Rain recorded as a hindrance, 2 h
- Toolbox talk: work at height
- PMC countersignatureDue tomorrow
- K. Srinivas filed the DPR with 12 photos
- M. Rao issued 19.2 t of 20 and 25 mm bars to Venkata Rebar Works
- Emplotec flagged plaster at zero today: sand on PO-6611 not received
- K. Srinivas recorded the lift pit drawing R3 as awaited, day 4
Emplotec Steel fixing on slab 5 is 6.8 t behind plan over three days, and Friday's pour needs it done by Thursday noon. Add a second bar-bending crew on Wednesday?
DPR/P-2411/0285DPR/P-2411/0286DPR/P-2411/0287A day's DPR for one hospital block: work against the BOQ, the crews on site and the day's hindrance. Example companies, people and figures.
Questions people ask about the daily progress report format
What is the full form of DPR in construction?
On a site, DPR means daily progress report: the day's record of manpower, machinery, work done, materials and hindrances. Before a project is sanctioned, DPR can also mean detailed project report, the feasibility and cost document.
Who prepares the daily progress report on site?
The contractor's site engineer prepares it at the end of the shift, the project manager reviews it, and many contracts ask for a copy to go to the client's engineer or the PMC the same day.
Is a DPR format fixed by law?
No. The contents come from the contract and from practice. Government works also keep registers of their own, such as CPWD's hindrance register, so check what your contract's conditions ask for.
What is the difference between a DPR and an MPR?
A DPR covers one day on one site. A monthly progress report (MPR) sums up the month: progress against the schedule, cost, cash flow, risks and the plan for the next month, and it is usually built from the month's DPRs.
How do I calculate progress percentage in a DPR?
Divide the quantity done to date by the BOQ quantity for that item and multiply by 100. The Excel format does this for each row from the BOQ quantity, the total up to yesterday and today's quantity.
Is a daily construction report the same as a DPR?
Yes. Daily construction report, daily site report and daily log are the names used in the US and UK for the same document: the day's labour, equipment, work, materials, weather, delays and safety on one site.
Sources
- CPWD Works Manual 2022 (as hosted by NDMC)https://www.ndmc.gov.in/departments/Departments/Finance/nodal_cell/CPWD%20Works%20Manual%202022.pdf
- Central Public Works Departmenthttps://cpwd.gov.in/
- CAG Report No. 4 of 2017, chapter 11: hindrance registers in CPWD and extension of timehttps://cag.gov.in/uploads/download_audit_report/2017/Chapter_11_Contract_Variations_of_Report_No.4_of_2017_-_Contract_Management_in_Road_Works_Government_of_Uttar_Pradesh.pdf
Related
Stop typing daily progress reports by hand.
Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.