Daily construction report template with manpower, weather and delays

A daily construction report (daily log) records what happened on site each day: weather, who worked and for how long, equipment, work done, deliveries, inspections, safety and delays. This one totals the labor and equipment hours and the delay time for you.

  • Labor hours by trade, totaled
  • Weather by time of day, delay hours
  • Inspections, deliveries and safety
  • Excel with formulas, Word, PDF

Written for US. Elsewhere:Daily progress report format India

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Daily construction report

Report no.

Manpower

CompanyTradeForemanWorkersHours eachTotal hoursArea worked
Total on site

Equipment

EquipmentOwned or rented, byHours usedHours idleNote
Total

Work performed

Concrete placed

Ordered (CY)
Placed (CY)
Returned or wasted (% of ordered)

Deliveries

TimeSupplierMaterialTicket no.Checked by

Inspections and tests

Inspection or testByResult

Delays and issues

Delay or issueCauseHours lostCrews affectedNotice or RFI
Total hours lost

Safety

Visitors, instructions and changes

Photos

Superintendent
Project manager

What a daily construction report is

A daily construction report, also called a daily log or superintendent's daily report, is the general contractor's record of one working day on one project. It records the conditions, the people and equipment on site, the work done, materials delivered, inspections, safety events, visitors, instructions received and anything that held the work up. It is written by the superintendent on the day and signed.

Its value shows up later. When there is a dispute about a delay, a change, a back charge or an injury months on, the daily reports are often the only record made at the time, and they carry more weight than anyone's memory. A report written every day, with facts and numbers, is the best protection a contractor has.

What to include in a daily construction report

SectionWhat to writeWhy it matters
HeaderProject, number, date, working day, superintendent, permit, shift hoursTies the report to the schedule and contract days
WeatherTemperature, conditions and wind at set times, precipitation, ground conditionsWeather delays are excused only if they are recorded, and cold or hot weather changes concrete, paint and roofing work
ManpowerEach company and trade, foreman, number of workers and hoursProves crew levels, supports back charges and certified payroll checks
EquipmentEach machine, who owns it, hours used and idleStandby and idle time is a cost in delay and change claims
Work performedWhat was done where, quantities, and schedule activities started or finishedProgress for pay applications and the schedule update
DeliveriesSupplier, material, ticket number, who checked itMatches invoices and finds shortages
Inspections and testsWhat was inspected or tested, by whom, the result and report numberEvidence for code compliance and quality
Delays and issuesWhat stopped work, the cause, hours lost, crews affected, notice or RFI sentThe basis for time extensions and claims
SafetyToolbox talk and attendance, incidents, near misses, inspectionsFeeds OSHA records and shows a working safety program
Visitors, instructions and changesWho came, what they said, any direction that may change the workUnwritten directions are where change disputes start
Photos and signatureWhere the photos are, and the superintendent's signatureDated photos are the strongest evidence

The numbers the template works out

Total hours for each company = workers x hours each, and the template totals the workers and hours on site. In the example: 4 x 8 + 9 x 10 + 5 x 8 + 3 x 8 + 2 x 8 = 32 + 90 + 40 + 24 + 16 = 202 labor hours from 23 workers. Equipment totals 16 hours used and 7 idle. Delays total 6 hours lost.

For concrete, the template works out what was returned or wasted as a share of the order: (190 - 186) / 190 x 100 = 2.11%. Tracked pour by pour, it shows whether takeoffs or ordering need tightening.

When daily reports are required

No general law requires a private contractor to keep a daily log, but most construction contracts and specifications do, and some public work rules make related records mandatory:

Rule or documentWhat it asks for
The contract's general conditions and Division 01 specificationsUsually a daily report or log, often submitted to the owner or architect daily or weekly
UFGS 01 45 00, Quality Control (federal work under Unified Facilities Guide Specifications)Contractor quality control daily reports, signed with a certification that the report is complete and correct, on the schedule the contract sets
Davis-Bacon and related acts, 29 CFR 5.5(a)(3)Weekly certified payrolls (DOL form WH-347 or an equivalent). The daily manpower log is how you check them
FAR 52.249-10(b), fixed-price constructionThe contractor is not in default for delays from unforeseeable causes beyond its control, including unusually severe weather, if it notifies the contracting officer in writing within 10 days of the start of the delay
29 CFR 1926.20(b)(2), OSHA constructionFrequent and regular inspections of the jobsite, materials and equipment by competent persons

Recording weather for concrete and other temperature-sensitive work

ACI 306 treats cold weather as a period when the air temperature has fallen, or is expected to fall, below 40 F during the protection period. Record temperatures at set times, the concrete temperature at placement and the protection used (blankets, heated enclosures), as in the example, because these are what an engineer will ask for if cylinder breaks come back low.

How to fill in the daily construction report

  1. Fill the header each morning, with the working day count from the schedule.
  2. Record the weather at the same times every day, and the ground conditions.
  3. Get headcounts and hours from each foreman before they leave; the template works out total hours.
  4. Write work done by area with quantities and the schedule activity.
  5. Log deliveries with ticket numbers, and every inspection or test with its result.
  6. Record every delay with its cause, hours and the crews affected, and note any notice or RFI sent the same day.
  7. Write down visitors and any instruction that could change the work, especially verbal ones.
  8. Note where the photos are, sign, and send it to the project manager before the end of the day.

Common mistakes in daily reports

  • Filling it in at the end of the week from memory.
  • "Weather: cold" instead of temperatures and times.
  • Subcontractor headcounts copied from yesterday.
  • Delays recorded with no cause or hours, so they can't support a time extension.
  • Verbal directions from the owner or architect left out because no work was done yet.
  • Opinions and blame instead of facts. The report may be read by a judge or arbitrator.

Emplotec Projects

Or file the daily report from the site, on a phone.

In Emplotec Projects the superintendent files the day's report on the mobile app, offline if the site has no signal. Work, labor, equipment and material post to the project as they are entered, so nobody retypes the daily log into a spreadsheet at night.

  • Work done is entered against cost codes and schedule activities, so progress, earned value and the S-curve update from the same entries.
  • Material received and issued comes from the site store, and consumption is reconciled against the estimate.
  • Subcontractor work orders sit on the project, so each crew's work in the daily report is there when their pay application comes in.
  • Emplotec drafts the weekly owner's report from the week's daily reports, for the project manager to check and send.
Daily reportsCherry Creek Medical Office Building · November 2026
TodayThis weekDelaysPhotosNew reportExport week
EmplotecReport 142: 23 workers, 202 hours. 186 CY placed on L2 deck B; activity 3120 complete.
Labor hours today202
Workers on site23
Delay hours this week6
ScheduleOn track
Report 142, manpower
CompanyTradeWorkersHoursArea
Ironwood ConcreteConcrete990L2 deck, area B
Summit RebarReinforcing540L3 columns
Bolt ElectricElectrical324L1 underground
Front Range BuildersLaborers432L2 deck
Today
  • C. Whitfield logged 31 F at 7 AM, frozen ground
  • Apex Testing passed L2 deck B rebar
  • Bolt Electric stopped at an unmarked line, RFI-118

Emplotec RFI-118 has stopped Bolt Electric for 5 hours, and their underground work is on the critical path for the L1 slab. Send the RFI to the engineer marked urgent?

RFI-118Activity 2210
Mark urgent

Today's report on the medical office building, with the pour logged and one delay waiting on an RFI. Example companies, people and figures.

Questions people ask about the daily construction report format

What should be included in a daily construction report?

The project, date and superintendent; weather at set times; manpower by company and trade with hours; equipment hours used and idle; work performed with quantities; deliveries; inspections and tests; delays with cause and hours; safety; visitors and instructions; photos; and a signature.

Who fills out the daily construction report?

The general contractor's superintendent, from what they saw and from each foreman's headcount and hours. Subcontractors often keep their own daily reports, which the superintendent collects.

Are daily reports required by law?

Not as a general rule for private work, but most contracts and specifications require them. On federal work, UFGS 01 45 00 calls for signed contractor quality control daily reports, Davis-Bacon work needs weekly certified payrolls, and FAR 52.249-10 requires written notice of excusable delays within 10 days.

How do you record weather delays?

Record the actual weather every day at set times, which work was stopped, the crews and hours affected, and whether that work was on the critical path. Send written notice as the contract requires. Compare against normal weather for the month when you claim time.

What is the difference between a daily report and a daily log?

Most contractors use the terms for the same document. Some keep a daily log as the superintendent's diary and a daily report as the formal version sent to the owner. This template works as either.

How long should daily construction reports be kept?

At least as long as the contract, warranty and claim periods, and your state's statute of repose for construction defects, which can run for many years. Federal contracts set their own record retention terms. Keep them with the photos.

Sources

  1. WBDG: UFGS 01 45 00, Quality Controlhttps://www.wbdg.org/dod/ufgs/ufgs-01-45-00
  2. 29 CFR 5.5, contract provisions and related matters (Davis-Bacon)https://www.law.cornell.edu/cfr/text/29/5.5
  3. U.S. Department of Labor: WH-347, certified payroll formhttps://www.dol.gov/agencies/whd/forms/wh347
  4. FAR 52.249-10, default (fixed-price construction)https://www.acquisition.gov/far/52.249-10
  5. 29 CFR 1926.20, general safety and health provisions (construction)https://www.law.cornell.edu/cfr/text/29/1926.20
  6. ACI: Cold weather concreting (ACI 306)https://www.concrete.org/topicsinconcrete/topicdetail/cold%20weather%20concreting

Stop typing daily construction reports by hand.

Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.

WhatsApp