Free templateProjects and construction

Change order template for construction, free in Excel, Word and PDF

A change order records an agreed change to the work, the contract sum and the contract time, signed by the owner and the contractor. Fill this one in on the page, or download it.

  • Contract sum carried forward
  • Cost breakdown with markup
  • Time extension and new completion date
  • Excel with formulas

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Owner copy
Change order

Change to the work, the contract sum and the contract time

Phone

Owner

Contractor

Description of the change

Cost of this change

No.DescriptionQtyUnitUnit costAmount
Cost of the work

Contract sum

Original contract sum
Net change by previous change orders
Contract sum before this change order
Cost of the work (total above)
Overhead and profit, %
Overhead and profit
This change order: increase (decrease)
New contract sum, including this change order

Agreement

Signed by the owner and the contractor, this change order adjusts the contract sum and the contract time as shown above for the work described. Unless written here, it covers all direct and indirect costs, markup and delay for that work. All other terms of the contract stay the same.

Contractor (signature, name, date)
Architect or engineer (if any)
Owner (signature, name, date)

What a change order is

A change order is a written amendment to a construction contract that changes the work, the contract sum, the contract time, or all three, and is signed by the owner and the contractor (and the architect, where there is one). Once signed, it becomes part of the contract.

Changes come from many places: an owner who wants something added, a design error found on site, a concealed condition behind a wall, or a material that is no longer available. Whatever the cause, the change order is the record that the parties agreed what changes and what it costs.

What a change order must include

The same layout as the standard owner-architect-contractor change order form, such as AIA G701.
FieldWhat to write
Project, contract date and change order numberNumber change orders in sequence for each contract: CO-001, CO-002 and so on.
Owner, contractor and architectThe parties to the contract, and the architect or engineer who administers it.
Description of the changeExactly what is added, removed or changed, with references to drawings, sketches, RFIs or specifications.
Cost breakdownLabor, material, equipment and subcontract costs, with markup as the contract allows. Credits for deleted work are shown as negatives.
Original contract sumThe sum in the signed contract, or the guaranteed maximum price.
Net change by previous change ordersThe total of every change order signed before this one.
Contract sum before this changeOriginal sum plus previous changes.
This changeThe increase, decrease or no change in this change order.
New contract sumThe sum before this change plus this change.
Contract timeThe days added or removed, and the new date of substantial completion.
Signatures and datesOwner, contractor and architect. A change order isn't agreed until it is signed.

How the contract sum carries forward

Every change order restates the running total, so anyone can see the current contract sum from the latest one. In the example above:

LineAmount
Original contract sum$78,500.00
Net change by previous change orders$4,215.00
Contract sum before this change order$82,715.00
Cost of the work in this change$7,566.00
Overhead and profit at 10%$756.60
This change order$8,322.60
New contract sum$91,037.60

Keep a change order log beside the contract: each number, its date, amount, days and status (pending, approved, rejected). The log's approved total should always equal the net change on the latest change order.

How to price a change order

  • Lump sum: a fixed price for the change, built from a breakdown the owner can check.
  • Unit prices: quantities times the unit prices agreed in the contract, common for earthwork, concrete and piping.
  • Time and materials: actual labor, material and equipment, plus markup, usually with a not-to-exceed amount.
  • Credits: deleted work is priced as a credit to the owner, often with less markup than additions carry, or none.

Time extensions

Ask for the time in the same change order as the money. If the added work delays the critical path, state the days and the new substantial completion date. A change order signed with no change in time can make a later claim for that delay hard to win, and where the contract has liquidated damages, the completion date is what they run from.

Change order, change directive and minor change

Change orderConstruction change directiveOrder for a minor change
Used whenOwner and contractor agree the change, price and timeThe owner needs the work done before price or time is agreedA small change with no cost or time effect
Signed byOwner, contractor and architectOwner and architectArchitect
Price and timeAgreed and finalSettled later, then a change order followsUnchanged
AIA formG701G714G710

Federal contracts use different terms. Under FAR Part 43, a change order is a written order the contracting officer signs alone under the contract's changes clause, while a change both parties sign is a supplemental agreement (a bilateral modification), issued on Standard Form 30.

Common change order mistakes

  1. Doing the work on a verbal instruction and pricing it afterward.
  2. Leaving out the time, then claiming a delay later.
  3. Describing the change too loosely to check what was included.
  4. Getting the running contract sum wrong because a previous change order was missed.
  5. Leaving markup on credits for deleted work, or pricing the credit at a different rate from the addition.

Emplotec Projects

Or let the change order update the job's budget.

In Emplotec, a change order is raised on the project, priced by cost code, and counts only once it is approved, so the budget, the contract value and the forecast to finish move together.

  • Change orders are approved before they count, against a work breakdown, cost codes and budgets by cost type.
  • Commitments from orders and subcontracts, and actual cost from receipts, invoices and hours, sit on the same project.
  • The forecast to complete and the project P&L update as each change is approved.
  • Ask Emplotec how much approved change has added to a job, and it shows each change order with its date and amount.
Change orders, project 26-118QC lab fit-out · Ridgeline Components
LogBudgetForecastNew change orderExport log
EmplotecCO-004 adds 6 days: substantial completion moves to December 24.
Original contract$78,500
Approved changes$4,215
Pending$8,3231 change order
Forecast margin11.8%
Change order log
No.ChangeAmountDaysStatus
CO-001Relocate two office doorsOwner request$1,200.000Approved
CO-002Steel lintel, east wallSite condition$1,690.002Approved
CO-003Added data drops, 12Owner request$1,325.000Approved
CO-004Lab drain and caseworkRFI-031$8,322.606With owner
CO-004
  • Priced by cost code
  • Sub quotes attached2
  • Schedule impact checked+6 days
  • Owner signature

Emplotec Tom Becker hasn't signed CO-004, and the slab pour for the trench is booked for November 10. Draft a reminder with the cost breakdown attached?

CO-004SK-12
Draft reminder

The change order log for one job, with a pending change and its effect on the margin. Example companies, people and figures.

Questions people ask about the change order format

What is a change order in construction?

A written amendment to the construction contract that changes the work, the contract sum or the contract time, signed by the owner and the contractor, and by the architect where there is one. Once signed it becomes part of the contract.

Who prepares a change order?

Usually the contractor prices the change and the architect or the contractor prepares the change order for signature. On a job without an architect, the contractor prepares it and the owner signs.

What is a reasonable markup on a change order?

Whatever the contract allows. Many contracts set a percentage for overhead and profit on self-performed work and a lower one on subcontracted work. If the contract is silent, agree the markup in writing before pricing changes.

Can a contractor refuse a change order?

A contractor can refuse to sign a change order whose price or time it doesn't accept. Most contracts still let the owner direct the work through a construction change directive, with the price and time settled later.

What is the difference between a change order and a change directive?

A change order is agreed by both sides, with the price and time settled. A construction change directive lets the owner order the work before they are agreed, and a change order follows once they are.

Do change orders need to be in writing?

Nearly every construction contract requires it, and written change orders are the only reliable proof of what was agreed. Work done on verbal instructions is the most common source of payment disputes.

Sources

  1. AIA Contract Documents: G701-2017, Change Order (summary and instructions)https://help.aiacontracts.com/hc/en-us/articles/1500009384382-Summary-G701-2017-Change-Order
  2. AIA Contract Documents: the fundamentals of change orders in constructionhttps://learn.aiacontracts.com/articles/6378493-the-fundamentals-of-change-orders-in-construction/
  3. Federal Acquisition Regulation, Part 43: contract modificationshttps://www.acquisition.gov/far/part-43