Free templateProjects and construction
Punch list template for construction closeout
A punch list is the list of work still to be finished or corrected before a construction project can be closed out. This template records each item by location and trade with an owner, a due date and a status, and works out the cost of what is open and the amount an owner holds back for it.
- Item, location, trade, owner, due date
- Cost to finish and holdback
- Fits AIA A201 closeout
- A4 landscape, Excel with formulas
Written for US. Elsewhere:Snag list template UK
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
Walk-through date
Items
| No. | Location | Trade | Item to complete or correct | Priority | Responsible | Due | Status | Cost to finish (open) |
|---|---|---|---|---|---|---|---|---|
| Open items | ||||||||
Progress and holdback
| Items on the list | |
|---|---|
| Items closed and verified | |
| Closed | |
| Cost to finish the open items | |
| Holdback factor in the contract (1 if none) | |
| Amount held back for the punch list |
Notes
Substantial completion walk-through, November 16, 2026
Items
| No. | Location | Trade | Item to complete or correct | Priority | Responsible | Due | Status | Cost to finish (open) |
|---|---|---|---|---|---|---|---|---|
| Open items | 3,380.00 | |||||||
Progress and holdback
| Items on the list | |
|---|---|
| Items closed and verified | |
| Closed | 50% |
| Cost to finish the open items | 3,380.00 |
| Holdback factor in the contract (1 if none) | |
| Amount held back for the punch list | 5,070.00 |
Notes
Items 5 and 10 were life safety and accessibility items and were closed before the architect's inspection. Test and balance report (item 8) is also a closeout document. Rev 2 issued Nov 20 after the subs' sign-offs.
Example entries. Go back to blank to fill in your own.
What a punch list is
A punch list (or punchlist) is the list of work that doesn't yet meet the contract at the end of a construction project: things unfinished, damaged or not done to the drawings and specifications. It is made on a walk-through near completion, each item is assigned to the trade that owns it, and the project is closed out when every item is done and verified. In the UK and Commonwealth countries the same list is called a snag list.
Punch list items are usually small: touch-up paint, an adjustment, a missing cover plate, a cleaning item. If an item stops the owner using the building for its purpose, such as a failed fire alarm test or no certificate of occupancy, the project isn't substantially complete, and that item is not a punch item but unfinished work.
The punch list in AIA contract closeout
- Under AIA A201-2017, section 9.8, when the contractor considers the work substantially complete, it prepares and submits to the architect a comprehensive list of items to be completed or corrected.
- The architect inspects. If the work isn't substantially complete, the architect adds items and the contractor completes them; the list grows rather than shrinks.
- When it is, the architect issues a Certificate of Substantial Completion (AIA G704-2017), signed by owner, architect and contractor, with the punch list attached. It fixes the date of substantial completion, which starts the warranties and lets the owner occupy or use the work.
- The contractor finishes the remaining items within the time the certificate sets.
- Final inspection, final payment and the release of retainage follow once every item is closed and the closeout documents are in.
How to fill in the punch list template
- Fill in the project, owner, architect, contract and the date of the walk-through. Give the list a number and revision; every reissue gets a new revision.
- Walk the project room by room in a fixed order, so nothing is missed and the list reads in the same order as the building.
- For each item write the location, the trade, and a description someone can act on: what is wrong, where exactly, and what done looks like.
- Set a priority. Life safety, accessibility and anything that blocks occupancy come first.
- Assign it to the responsible party and give a due date.
- When a sub reports an item done, verify it, then mark it closed. Only the person who raised it, or the architect, should close it.
- Enter a cost to finish for each open item. The sheet totals it and works out the holdback at the factor your contract sets.
Holding money back for punch list items
Owners commonly keep money back against open punch items so the contractor still has a reason to finish them after the owner moves in. How much is set by the contract and, on many projects, limited by state prompt payment or retainage laws, so check what yours allow. The template doesn't assume a figure: enter your contract's factor, or 1 to hold the cost to finish.
- Price each open item realistically: what it would cost the owner to have someone else finish it.
- Release the holdback item by item, or in one sum at final completion, as the contract says.
- Keep retainage (the percentage held from each progress payment) separate from the punch list holdback in your records, even where the contract releases them together.
Tips for a shorter punch list
- Run rolling punch walks, floor by floor or area by area, as each finishes, rather than one list for the whole building at the end.
- Ask each sub to self-punch their own work before the general contractor's walk.
- Photograph every item with its number and location, so there is no argument about what was meant.
- Issue the list the same day, and walk it again every week until it is closed.
- Collect the closeout documents (warranties, manuals, as-builts, test reports, attic stock) on the same list, since final payment waits for them too.
Punch lists for homeowners
On a new home or a remodel, the homeowner's walk-through with the builder before closing or final payment is the punch list. Walk every room with the list, test doors, windows, faucets, outlets and appliances, look at finishes in daylight, and write each item down with its location before you sign anything or make the last payment. Most builders' warranties also have a window for a second list after you move in; check yours for its dates.
Common punch list mistakes
- Vague items ("fix paint in corridor") that the trade can't find or close.
- No owner or due date, so items sit until the last week.
- Closing items on the sub's word without checking them.
- Calling the project substantially complete with life safety items still open.
- Several versions of the list in circulation, with no revision number.
Emplotec Projects
Or run the punch list from the site, on a phone.
In Emplotec Projects the site team records progress and closeout on mobile, offline, against the project's budget and its subcontractors' work orders.
- A daily progress report on mobile, offline, for every project.
- Mobile checklists with packs for construction, so walk-throughs follow the same list on every job.
- Subcontractor work orders and their bills, so an open item stays tied to the sub who owes it.
- Retention held and advances left to recover, on every contract.
- Warranties
- O&M manuals
- As-built drawings
- Test and balance report
Suite 300's punch list, five items open with the target date two weeks away. Example companies, people and figures.
Questions people ask about the punch list format
What is a punch list in construction?
The list of work still to be finished or corrected near the end of a project, made on a walk-through and assigned to the responsible trades. The project is closed out when every item is done and checked.
Who prepares the punch list?
Under AIA A201, the contractor prepares a comprehensive list of items to be completed or corrected when it considers the work substantially complete, and the architect inspects and adds to it. On other contracts, the owner, architect or construction manager may lead the walk-through.
What is the difference between substantial completion and final completion?
Substantial completion is when the owner can occupy or use the work for its purpose, with only punch list items left; it usually starts warranties. Final completion is when every punch item and closeout document is done, which releases final payment and retainage.
What should a punch list item include?
A number, the exact location, the trade, a description of what is wrong and what done looks like, a priority, who is responsible, a due date and a status. A photo makes it hard to dispute.
How much can an owner withhold for punch list items?
Whatever the contract says, within any limit in state prompt payment or retainage law for your project. Some contracts set a multiple of the cost to finish; the template takes your contract's factor and works out the amount.
What is the difference between a punch list and a snag list?
Nothing but the name. Punch list is used in the US and Canada; snag list in the UK, Ireland, Australia and much of the Commonwealth.
Sources
- AIA Contract Documents: A201-2017, General Conditions of the Contract for Constructionhttps://www.aiacontracts.com/
- AIA Contract Documents: Summary of G704-2017, Certificate of Substantial Completionhttps://help.aiacontracts.com/hc/en-us/articles/1500009430502