Free templateService and maintenance

Service report format for breakdown, PPM and AMC visits

The report a technician leaves after a breakdown, PPM or installation visit: the asset, the contract cover, the times against the SLA, what was found and done, readings, parts used and the customer's sign-off. Fill it in here, or download Excel, Word or a blank PDF.

  • Breakdown and PPM sheets
  • SLA times, readings and checklist
  • Covered and chargeable parts split, with GST
  • Free, no sign-up

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Customer copy
Service report

Breakdown / PPM / installation visit

GSTIN
Service desk

Customer and site

Contract cover

Complaint as reported

Work done

Readings

ParameterUnitBeforeAfterNormal range

Checklist

Sr.CheckOK / not OKRemarks

Parts and consumables used

Sr.Part no. and descriptionNew serial / old partQty usedChargeable qtyRateChargeable amount
Chargeable parts

Charges

Chargeable parts (total above)
Chargeable labour and call-out
Taxable value
GST at 18%
Amount to be invoiced

Photos

Customer remarks

Technician (name and ID)
Customer representative (name and signature, or OTP approval with time)
Service supervisor

What a service report is

A service report (also called a field service report, job sheet or technician visit report) is the record a technician leaves with the customer after every visit: what was wrong, what was done, what parts went in, how long it took, and the customer's sign-off. It is the provider's proof that the visit happened and the customer's proof of what they are being billed for.

Under an AMC or CMC the signed reports are also the evidence that the preventive visits in the contract were done and that breakdown calls were met within the response time. If a dispute comes up at renewal, the reports are what both sides go back to.

What a service report format must contain

FieldWhy it matters
Report no. and job or call no.Links the report to the call log and the invoice; one call can need two visits.
Customer, site and contactLarge customers have many sites; the report must say which.
Asset make, model, serial and tagProves which unit was serviced. Without the serial, nobody can build the unit's history or check its cover.
Contract coverAMC, CMC, warranty or chargeable decides who pays for labour and parts.
Call logged, response due, arrival, completionThe SLA is measured on these times. Write them down, not "morning".
Complaint as reportedThe customer's words, before diagnosis. Helps when the fault found turns out to be different.
Fault found, failure code and root causeCodes let you count repeat failures by model; the root cause stops the same call next month.
Work donePlain sentences, in the order done.
Readings before and afterShows the equipment is back in range, and gives the next technician a baseline.
ChecklistThe standard checks for that equipment type, so nothing is skipped.
Parts used, with serialsSerials for warranty claims and traceability; old parts returned or left on site.
Covered and chargeable splitThe customer agrees to the chargeable part on site, not when the invoice arrives.
PhotosBefore and after, the nameplate, the failed part. Settle most disputes on their own.
Technician and customer sign-offA signature or an OTP approval, with name and time. An unsigned report is weak proof.
Follow-up and next visitOpen items, quotes sent and the next PPM date.

Breakdown, PPM and installation reports compared

Breakdown reportPPM reportInstallation and commissioning report
Starts fromA customer callThe contract's visit planA sales order or project
Times that matterCall, response due, arrival and fixPlanned month and date doneHandover date
Main contentFault, failure code, work done, partsChecklist and readings for every unitSite checks, settings, test readings, training given
Usually one report perCallVisit, covering many unitsInstallation
What it provesThe SLA was met and the fault fixedThe contract's PPM was doneThe equipment was handed over working; warranty starts

The download has two sheets: the full report for a breakdown or single-unit visit, and a PPM sheet for a visit that covers many units. For an installation, use the first sheet with visit type "Installation" and record the commissioning readings and the warranty start date.

How to fill in this service report format

  1. Before leaving for the site, fill in the report and job numbers, the customer, the asset and the contract cover from the call log.
  2. Note the arrival time when you reach the equipment, not the gate.
  3. Write the complaint in the customer's words, then take the before readings and photos.
  4. Record the fault found, pick a failure code from your company's list, and write the root cause if you know it.
  5. List every part with its serial, and mark how many are chargeable. Show the chargeable amount to the customer before you fit a chargeable part.
  6. Take the after readings, run the checklist, and note the equipment's status at handover.
  7. Get the customer's signature or OTP approval with name and time, and leave a copy before you go.

The filled example: a chiller breakdown under CMC

The format above is filled for a 300 TR chiller that tripped at 07:30. The call was logged at 07:40; the contract gives 4 hours, so response was due by 11:40 and the technician arrived at 10:05. The contactor is covered by the CMC, but refrigerant is excluded, so the 6 kg of R-134a is chargeable: ₹5,700 plus 18% GST, ₹6,726 in all. The customer approved it on site.

Tips for service reports that hold up

  • Fill it in on site, not from memory in the evening.
  • Use failure codes, not free text alone. After a year you can see which model, part and site fail most.
  • Always take the asset's serial number, even on a PPM visit that covers twenty units.
  • Record readings with units and the normal range, so the next technician can compare.
  • Never leave a chargeable item for the invoice to explain. Agree it on the report.
  • Number the reports in one series per year, and keep them with the contract. At renewal, count PPM visits done against the contract and breakdowns met against the SLA.
  • If the customer refuses to sign, write "customer declined to sign" with the name and time, and send the report by email the same day.

Emplotec Field Service

Or let the signed report on the phone become the invoice.

In Emplotec the technician fills the service report on the phone, even offline in a plant room or a lift pit. The customer signs it or approves it by OTP before the technician leaves, and its time, parts and call-out charges are ready to bill through Billing.

  • The asset's history, cover and SLA on the phone before the visit; check-in by geofence, QR or the customer's OTP.
  • Checklists, readings, photos and parts used with serials, in regional languages.
  • Covered parts to the contract's cost and billable parts to the invoice, with the report and photos as the annexure.
  • PPM compliance and every signed report on the customer's portal.
Job BD-2611-042Lakeview Tech Park · Chiller 2
ReportPartsHistoryBill nowSend to customer
SignedApproved by OTP by AR at 15:24. Response SLA met: 2 h 25 min.
Visit
Asset
CH-2219-0457
Cover
CMC, refrigerant excluded
Logged
07:40
Arrived
10:05
Completed
15:20
Failure code
ELE-CTR-03
Chiller checklist
  • Leak testRemade
  • Oil level
  • Condenser strainerCleaned
  • Safety trips
  • Photos4
Parts used
PartSerialQtyCoverTo bill
Main contactor 185 ASC-882131Covered₹0
R-134a refrigerant, kgRC-55216Chargeable₹5,700
Flare nut and gasket1Covered₹0

Emplotec This is the third leak on Chiller 2 this year, each at a flare joint. Add a brazed-joint replacement to the quote for the next PPM?

BD-2611-042CH-2219-0457QT/26-27/311
Add to quote

Job BD-2611-042, signed by OTP on site, with its chargeable refrigerant ready to bill. Example companies, people and figures.

Questions people ask about the service report format

What is a service report?

The record a technician leaves after a service visit: the asset, the complaint, what was found and done, readings, parts used, times against the SLA, charges and the customer's sign-off.

What should a field service report include?

Report and job numbers, customer and site, asset make, model and serial, contract cover, call, arrival and completion times, fault and failure code, work done, readings, checklist, parts with serials, chargeable and covered split, photos, signatures and the next visit.

What is the difference between a breakdown report and a PPM report?

A breakdown report covers one call: the fault, the fix and the response time. A PPM report covers a planned preventive visit, usually many units, with a checklist and readings for each.

Is the customer's signature necessary on a service report?

No law requires it, but most AMC and CMC contracts ask for it, and an unsigned report is weak proof of the visit. A one-time password approval with the person's name and time works the same way and is easier on site.

Can the service report be used as the invoice?

It should be the invoice's annexure. Raise a proper GST invoice for the chargeable parts and labour, and attach the signed service report so the customer can see what the bill is for.

What is a failure code in a service report?

A short code for the type of fault (electrical, refrigerant, mechanical, control) and the part. Using the same list every time lets you count repeat failures by model, site and part.

Sources

  1. GST rates for goods and services, CBIC tax information portalhttps://taxinformation.cbic.gov.in/
  2. Indian Contract Act, 1872, India Codehttps://www.indiacode.nic.in/

Stop typing service reports by hand.

Tell us how your business runs. We'll show you Emplotec raising this from the work itself, on your own numbers, and reply within one working day.

WhatsApp