Free calculatorOperations and costing
OEE calculator: availability, performance and quality
Enter one shift's time, stops, ideal cycle time and counts to get availability, performance, quality and OEE, with the minutes lost to each.
- Availability × performance × quality
- Minutes lost to each
- World-class benchmarks
- Cycle time or run rate
Last updated
One shift on one machine
Breaks, meals, planned maintenance, no orders.
Breakdowns, setups, changeovers, waiting for material. Every stop while the machine was meant to run.
The fastest the machine can run this part, by design or the best sustained rate seen, not the standard you plan with.
Everything made, good and bad.
Right first time; rework counts as bad.
OEE
80.3%
Typical for discrete manufacturing (60% to 85%)
- Availability
- 91.3%
- Performance
- 90.7%
- Quality
- 97.0%
The biggest loss is availability: 38 min of the 435 min planned, from breakdowns, setups and changeovers.
- Good parts at ideal speed 349.2 min
- Quality loss 10.8 min
- Speed loss 37 min
- Downtime 38 min
How it is worked out
| Figure | |
|---|---|
| Planned production time480 less 45 planned stops | 435 min |
| Run timeless 38 min downtime | 397 min |
| Availabilityrun time ÷ planned production time | 91.3% |
| Ideal time for the count900 pcs × 24 sec | 360 min |
| Performanceideal time ÷ run time | 90.7% |
| Rejects900 made less 873 good | 27 pcs |
| Qualitygood count ÷ total count | 97.0% |
| OEEavailability × performance × quality | 80.3% |
Check: good count × ideal cycle time ÷ planned production time gives the same OEE. Planned stops are left out of OEE; count them in TEEP if you measure against all time.
The OEE formula
OEE (overall equipment effectiveness) = availability × performance × quality. It is the share of planned production time in which a machine makes good parts at its ideal speed. The same figure, read as time: good count × ideal cycle time ÷ planned production time.
| Factor | Formula | What it loses |
|---|---|---|
| Availability | Run time ÷ planned production time | Time the machine was meant to run but stood: breakdowns, setups, changeovers, waiting |
| Performance | (Ideal cycle time × total count) ÷ run time | Speed while running: small stops and slow cycles |
| Quality | Good count ÷ total count | Parts made but not good first time: rejects, rework, start-up scrap |
Planned production time is the shift less planned stops such as breaks, meals and planned maintenance. Run time is planned production time less unplanned stops.
A worked example
One 8-hour shift on a CNC lathe, with an ideal cycle time of 24 seconds:
| Step | Working | Result |
|---|---|---|
| Planned production time | 480 min shift − 45 min breaks | 435 min |
| Run time | 435 − 38 min downtime | 397 min |
| Availability | 397 ÷ 435 | 91.3% |
| Performance | (24 s × 900) ÷ (397 × 60 s) | 90.7% |
| Quality | 873 good ÷ 900 made | 97.0% |
| OEE | 0.913 × 0.907 × 0.970 | 80.3% |
| Check | 873 × 24 s = 349.2 min ÷ 435 min | 80.3% |
Of the 435 planned minutes, 38 went to downtime, 37 to slow running and small stops, and 10.8 to the 27 rejects. These are the calculator's opening figures.
What is a good OEE?
| OEE | What it usually means |
|---|---|
| 85% or more | World class for discrete manufacturing |
| 60% to 85% | Typical for discrete manufacturing, with room to improve |
| 40% to 60% | Low, and common where OEE is first measured honestly |
| Below 40% | Check the inputs first, then the biggest loss |
The 85% world-class figure comes from the TPM targets of 90% availability, 95% performance and 99.9% quality (0.90 × 0.95 × 0.999 = 85.4%). It is a benchmark, not a law: a line with long changeovers by design, or a process plant, will sit elsewhere. The trend on the same machine tells you more than a comparison with someone else's.
The six big losses
| Loss | OEE factor | Examples |
|---|---|---|
| 1. Breakdowns | Availability | Equipment failure, tooling failure, unplanned maintenance |
| 2. Setup and adjustments | Availability | Changeovers, first-off approval, warm-up, waiting for material or an operator |
| 3. Small stops | Performance | Jams, misfeeds, blocked sensors, short stops under a few minutes |
| 4. Reduced speed | Performance | Running below the ideal rate: worn tools, cautious settings, poor material |
| 5. Start-up rejects | Quality | Scrap and rework while the process settles after a start or changeover |
| 6. Production rejects | Quality | Scrap and rework during steady running |
Short stops are easy to miss on a log sheet: if performance is low and no-one can say why, it is usually dozens of stops of under five minutes each.
Common mistakes
- Using the planned or standard cycle time instead of the ideal one. A padded cycle time hides speed loss and can push performance past 100%.
- Treating setups and changeovers as planned stops. They are downtime: losses OEE is meant to show.
- Counting reworked parts as good. Quality counts only parts that were right first time.
- Averaging the OEE of several machines. Add up their good minutes and planned minutes instead, so a long-running machine weighs more.
- Chasing one number. OEE is useful because it splits into three, and each points at a different fix.
OEE and TEEP
OEE measures against planned production time. TEEP (total effective equipment performance) measures against all the time there is, 24 hours a day, so it also shows how much of the week is not scheduled at all. TEEP = OEE × planned production time ÷ calendar time. It answers a capacity question: whether to add a shift before buying a machine.
Emplotec Manufacturing
Or get OEE from the shop floor's own entries.
In Emplotec, OEE and downtime come from job cards and the downtime log your operators already fill in, machine by machine.
- Work orders, job cards and shop-floor kiosk entry give the counts, good and rejected, for every operation.
- OEE and downtime per machine, with scrap, rejection and rework against each job.
- A finite-capacity schedule that re-sequences when a machine breaks down or a rush order lands.
- Downtime feeds capacity and maintenance, with preventive plans and spares in Assets & Maintenance.
- CNC-07 Spindle alarm, 41 min
- VMC-02 Changeover to HS-40, 26 min
- CNC-07 Spindle alarm, 23 min
- CNC-03 Waiting for material, 18 min
OEE for one shift across the machining cell, from job cards and the downtime log. Example companies, people and figures.
Questions people ask about the OEE calculator
What is the formula for OEE?
OEE = availability × performance × quality. Equivalently, good count × ideal cycle time ÷ planned production time.
What is a good OEE score?
85% is widely quoted as world class for discrete manufacturing, from targets of 90% availability, 95% performance and 99.9% quality. Around 60% is typical, and 40% is common where OEE is first measured.
What are the six big losses in OEE?
Breakdowns and setups (availability), small stops and reduced speed (performance), and start-up rejects and production rejects (quality).
Is changeover time included in OEE?
Yes. Setups and changeovers are unplanned stops in OEE terms and reduce availability. Only breaks, meals, planned maintenance and time with no orders are taken out as planned stops.
Can OEE be more than 100%?
No. If performance comes out above 100%, the ideal cycle time entered is slower than the machine really runs. Use the fastest proven cycle time.
What is the difference between OEE and TEEP?
OEE measures against planned production time; TEEP measures against all calendar time. TEEP = OEE × planned production time ÷ calendar time, so it also shows the time not scheduled.
Sources
- ISO 22400-2:2014, key performance indicators for manufacturing operations management (includes OEE)https://www.iso.org/standard/54497.html
- Japan Institute of Plant Maintenance (JIPM), publisher of Seiichi Nakajima's TPM Nyumon (1984; in English as Introduction to TPM, 1988)https://www.jipm.or.jp/
Related
Run this inside one system.
Tell us how your business runs. We'll show you Emplotec doing this work on your own numbers, and reply within one working day.