Free templateProduction and quality
Bill of materials format: a multi-level BOM in Excel with costing
A bill of materials lists every part and material that goes into one unit of a product, level by level, with the quantity of each. This one also works out the material cost. Fill it in on the page, or download it in Excel with the formulas in place.
- Indented levels: 0, 1, 2
- Make or buy, scrap allowance
- Material cost rolled up
- A4 landscape, Excel with formulas
Written for India. Elsewhere:Bill of materials template any country
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
Manufacturing BOM, per unit of the parent item
Components
| Level | Part no. | Description | Make or buy | Unit | Qty per parent | Parents per unit | Qty per unit | Scrap % | Rate | Cost per unit |
|---|---|---|---|---|---|---|---|---|---|---|
| Material cost per unit | ||||||||||
Material for an order
| Material cost per unit (from the BOM) | |
|---|---|
| Order quantity | |
| Material cost of the order | |
| Copper wire to issue, kg (1.15 kg x 1.03 x order) |
Notes
Manufacturing BOM, per unit of the parent item
Components
| Level | Part no. | Description | Make or buy | Unit | Qty per parent | Parents per unit | Qty per unit | Scrap % | Rate | Cost per unit |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 0.00 | |||||||||
| 1 | 620.00 | |||||||||
| 1.15 | 1,137.12 | |||||||||
| 1 | 780.00 | |||||||||
| 1 | 540.00 | |||||||||
| 1 | 95.00 | |||||||||
| 1 | 80.00 | |||||||||
| 1 | 165.00 | |||||||||
| 1 | 85.00 | |||||||||
| 1 | 690.00 | |||||||||
| 1 | 640.00 | |||||||||
| 1 | 120.00 | |||||||||
| 1 | 45.00 | |||||||||
| 0.08 | 33.44 | |||||||||
| 1 | 70.00 | |||||||||
| Material cost per unit | 5,100.56 | |||||||||
Material for an order
| Material cost per unit (from the BOM) | |
|---|---|
| Order quantity | |
| Material cost of the order | 12,75,140.00 |
| Copper wire to issue, kg (1.15 kg x 1.03 x order) | 296.13 |
Notes
Assemblies (Make) carry no rate: their cost is the sum of the levels below. Alternate for CAP-36: CAP-36B (any approved make). Winding of the stator is done by a job worker; copper issued is reconciled against wound stators returned.
Example entries. Go back to blank to fill in your own.
What a bill of materials is
A bill of materials (BOM) is the list of everything that goes into one unit of a product: assemblies, parts and raw material, with the quantity of each. Purchase uses it to buy, stores to issue, planning to run MRP, and accounts to cost the product. It answers one question: to make one of these, what do I need?
A multi-level BOM shows the product as a tree. Level 0 is the finished product, level 1 the assemblies and parts that go straight into it, level 2 what goes into each level 1 assembly, and so on. Written as an indented list, as in the format above, the tree fits in one Excel sheet.
What a BOM format contains
| Field | What it means |
|---|---|
| BOM number and revision | Which version of the BOM this is. A change in parts or quantities makes a new revision through an engineering change note (ECN) |
| Parent item and base quantity | The product the BOM is for, and the quantity the component figures are for (usually 1) |
| Effective from | The date or serial number from which this revision is used |
| Level | The component's place in the tree: 1 goes into the parent, 2 into a level 1 assembly |
| Part number, description, unit | The item code, a description purchase can buy from, and the unit (Nos, kg, m, L) |
| Make or buy | Whether you make it (with its own BOM and routing) or buy it |
| Quantity per parent | How many go into one of its parent, not into the finished product |
| Quantity per unit | Quantity per parent multiplied by the parents in one finished unit |
| Scrap allowance | Extra issued for losses in processing (cut ends, trimming, overspray) |
| Rate and cost | The purchase or standard rate, and quantity x rate x (1 + scrap) for the material cost |
Types of BOM
| Type | What it is | Who uses it |
|---|---|---|
| Single-level | Only the items that go straight into the product, no tree | Simple assemblies, traders who kit products |
| Multi-level (indented) | The full tree, assemblies inside assemblies | Engineering and machine builders |
| Engineering BOM (EBOM) | The product as designed, from the drawing | Design |
| Manufacturing BOM (MBOM) | The product as built: adds consumables, packing, paint and the order of assembly | Production, stores, costing |
| Recipe or formula | A process BOM: ingredients by weight or percentage per batch, with yield | Food, chemicals, pharma, rubber and plastics |
| Configurable (sales) BOM | Options a customer chooses, each pulling its own parts | Made-to-order products |
How to make a BOM in Excel
- Start from the approved drawing and the assembly sequence, not from a purchase list.
- Write level 0 in the header, then list each level 1 item. Under every 'Make' item, list its own components at the next level.
- Enter quantity per parent and the number of that parent in one finished unit; the sheet works out the quantity per unit.
- Add consumables the drawing leaves out: paint, sealant, packing, labels.
- Set a scrap allowance only where there is a real process loss, and keep it small and measured.
- Enter rates for bought items only. Assemblies carry no rate, so their parts are not counted twice.
- Give the BOM a number and revision, get it approved, and change it only through an ECN.
Using the BOM for job work, exports and costing in India
- Job work: when you send material to a job worker under Section 143 of the CGST Act (stators for winding, castings for machining), the BOM tells you how much should come back as finished parts. The gap is what ITC-04 and the job-worker reconciliation have to explain.
- Exports: exporters using an Advance Authorisation import inputs duty-free against standard input-output norms (SION) published by DGFT, or against their own norms. A clean BOM with scrap allowances is the evidence for an ad hoc norm.
- Costing: the BOM gives the material cost; the routing adds machine and labour time. Together they make the costing sheet, and the job card shows the actual against them.
- Stock valuation: work in progress and finished goods are valued from the BOM's standard costs, so an old BOM misstates inventory.
BOM, BOQ and routing compared
| What it lists | Used in | |
|---|---|---|
| Bill of materials (BOM) | Parts and materials for one unit of a product | Manufacturing |
| Bill of quantities (BOQ) | Items of work with measured quantities and rates for a construction contract | Construction and contracting |
| Routing (route card) | The operations, machines and standard times to make an item | Manufacturing, beside the BOM |
Common mistakes with BOMs
- Quantity per finished unit typed against a level 2 part, so it gets multiplied twice.
- Rates on assemblies and on their parts, which doubles the cost.
- No revision control: the shop builds from one version and purchase buys from another.
- Consumables and packing left out, so MRP never orders them.
- Scrap allowances padded to cover poor yield, hiding the loss.
- Two part numbers for the same item, so stock is split and reorder levels are wrong.
Emplotec Manufacturing
Or let the BOM drive purchase, planning and cost.
In Emplotec the multi-level BOM, with its versions and alternates, feeds MRP, the work orders and job costing, and every change goes through an engineering change note.
- Multi-level BOMs with versions and alternates, routings, and a drawing register with revision control.
- BOMs imported from CAD exports, and changed only through engineering change notes.
- MRP from customer orders, OEM schedules and reorder levels, checked against finite capacity.
- Job work given with job-worker reconciliation and ITC-04, and job costing planned against actual.
- Material, standard
- ₹5,101
- Material, last 3 work orders
- ₹5,178
- Open work orders
- 2
- Where used
- 3 products
Emplotec Actual material on the last three KFM-10 work orders is ₹77 a pump above standard, and ₹58 of it is winding wire: 1.24 kg used against 1.18 kg allowed (1.15 kg plus 3%). The job worker's returns match the issue, so the loss is in winding. Raise it with the winding job worker?
WO/26-27/0412WO/26-27/0437ITC-04 Q3The pump set's BOM at revision 03, with its cost roll-up and the change note that made it. Example companies, people and figures.
Questions people ask about the bill of materials format
What is a bill of materials in manufacturing?
The list of assemblies, parts and raw material, with quantities, needed to make one unit of a product. It drives purchase, stores issues, MRP and product costing.
What is a multi-level BOM?
A BOM shown as a tree: the finished product at level 0, its assemblies at level 1, their parts at level 2, and so on. An indented list in Excel, as in this format, shows the same tree.
What is the difference between a BOM and a BOQ?
A BOM lists the parts in one unit of a manufactured product. A BOQ (bill of quantities) lists items of construction work with measured quantities and rates for a contract.
Should labour be in the BOM?
No. The BOM holds materials. Operations, machines and labour time sit in the routing, and the costing sheet combines the two.
How do you add scrap to a BOM?
As a scrap percentage on the component, so the issue quantity is quantity x (1 + scrap / 100). Keep it to measured process losses.
What is an engineering change note?
The approved record of a change to a BOM or drawing: what changed, why, from which date or serial, and what happens to old stock. Each ECN makes a new BOM revision.
Sources
- CGST Act, 2017: Section 143 (job work); CGST Rules, 2017: Rule 45 and Form ITC-04, CBIC tax information portalhttps://taxinformation.cbic.gov.in/
- DGFT: Handbook of Procedures, Chapter 4, standard input-output norms (SION) and Advance Authorisationhttps://www.dgft.gov.in/
- ICMAI: Cost Accounting Standard 6 (material cost)https://icmai.in/