Inspection report template for site, equipment and quality inspections

An inspection report records what was checked, what was found, how serious it is and who will fix it by when. This one has two forms: a findings report for sites, equipment and buildings, and a lot inspection for incoming and final quality checks.

  • Findings with a 5 x 5 risk score
  • Lot inspection to ANSI/ASQ Z1.4
  • OSHA inspection intervals listed
  • Excel with formulas, Word, PDF

Written for US. Elsewhere:Inspection report format India

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Inspection report

Site, equipment or building inspection

Findings (likelihood and severity 1 to 5; risk = likelihood x severity)

No.Item or locationWhat was foundLikelihoodSeverityRiskActionOwnerDue

Summary

Items checked
Findings raised
Items with no finding
Inspection score (%)
High risk findings

Overall result and immediate actions taken

Inspector
Area supervisor
Site manager

What an inspection report is

An inspection report is the written record of one inspection: what was looked at, against which checklist, specification or standard, what was found, how serious each finding is, and what will be done about it, by whom and by when. Without the report, an inspection is a walk around. With it, you have evidence for auditors, insurers and OSHA, and a list of actions you can close.

People search for inspection report templates for two different jobs, so this template has two forms. The site inspection form is for workplaces, warehouses, construction sites, equipment and buildings: findings, a risk score and actions. The quality inspection form is for manufactured parts: dimensions against tolerance, a sample sized to ANSI/ASQ Z1.4 and an accept or reject decision for the lot.

InspectionUse the formWhat decides the result
Workplace or warehouse safety walkSite inspectionFindings, their risk score and whether actions close on time
Construction site or jobsiteSite inspectionHazards found by the competent person and fixed before work continues
Equipment (forklift, crane, ladder, slings)Site inspection, one line per itemDefects that take the item out of service until repaired
Building, property or move-outSite inspection, one line per room or systemCondition recorded with photos, repairs and who pays
Receiving, in-process or final quality checkQuality inspectionDefects in the sample against the Ac and Re numbers, and readings against tolerance

What to include in an inspection report

FieldWhat to write
Report numberA unique number, so a finding can be traced to the report that raised it and the report that closed it.
Date, time and areaExactly where and when. Conditions change by shift, so the time matters.
TypeRoutine, pre-use, follow-up, after an incident, or a receiving, in-process or final inspection.
Inspector and who went alongThe person responsible for the result, and the supervisor or engineer who walked with them.
Checklist or standardThe checklist and its revision, the drawing revision, or the OSHA standard or code the inspection is against.
FindingsOne line per finding: the item, what was found in plain words, the risk score, the action, the owner and the due date.
SummaryItems checked, findings, the score and the number of high risk findings, so reports can be compared month to month.
Result and immediate actionsSatisfactory, satisfactory with actions, or unsatisfactory; and anything locked out or stopped on the spot.
SignaturesThe inspector, the supervisor of the area and the manager who accepts the actions.

How the risk score works

Each finding gets a likelihood (how likely it is to cause harm, 1 to 5) and a severity (how bad the harm would be, 1 to 5). Multiplied together they give a risk score from 1 to 25, which the template works out for you. The score sorts the action list, so the dock leveler that could drop a forklift is fixed before the dented upright that only needs watching.

These bands are a common company convention, not a legal rule. Use your own risk matrix if you have one, and keep it the same on every report.
ScoreBandWhat to do
10 to 25HighStop or lock out now if people are exposed; escalate to the site manager; fix within days
5 to 9MediumFix within the next few weeks; owner and date on the report
1 to 4LowFix when convenient, or record and monitor at the next inspection

In the example, 64 items were checked and 5 findings raised, so 59 items had no finding and the inspection score is 59 / 64 x 100 = 92.19%. One finding scored 10 or more (the dock leveler, 3 x 4 = 12). The pothole scores 3 x 3 = 9, medium, but the inspector escalates it too because forklifts drive over it every shift: the score sorts the list, it doesn't replace judgment.

Inspections OSHA requires, and how often

OSHA does not prescribe an inspection report form, but many standards require inspections at set intervals, and a written record is how you show they happened. A few that come up on most sites:

States with their own OSHA-approved plans can add requirements. Check your state plan, your insurer and the equipment maker's manual too.
ItemHow oftenStandard
Portable fire extinguishersVisual inspection monthly; maintenance check yearly29 CFR 1910.157(e)(2) and (e)(3)
Forklifts and other powered industrial trucksBefore being placed in service each day (after each shift if used around the clock)29 CFR 1910.178(q)(7)
Slings used in material handlingEach day before use, by a competent person29 CFR 1910.184(d)
Construction jobsites, materials and equipmentFrequent and regular inspections by competent persons29 CFR 1926.20(b)(2)
ScaffoldsBefore each work shift and after anything that could affect structural integrity, by a competent person29 CFR 1926.451(f)(3)

OSHA's Recommended Practices for Safety and Health Programs list regular workplace inspections as one of the ways to find hazards, alongside incident investigations and asking workers. Recording the findings, fixing them and checking at the next inspection that they stayed fixed is what turns the walk into a program.

Quality inspection: picking the sample with ANSI/ASQ Z1.4

For parts and materials, the US sampling standard for inspection by attributes is ANSI/ASQ Z1.4 (it matches ISO 2859-1 used elsewhere). Find the code letter from the lot size and the inspection level (general level II unless the contract says otherwise), read the sample size for that letter, then read the acceptance (Ac) and rejection (Re) numbers for each AQL.

Normal single sampling. Where the sample size is larger than the lot, inspect every piece.
Lot sizeCode letter (level II)Sample size
2 to 8A2
9 to 15B3
16 to 25C5
26 to 50D8
51 to 90E13
91 to 150F20
151 to 280G32
281 to 500H50
501 to 1,200J80
1,201 to 3,200K125
3,201 to 10,000L200
10,001 to 35,000M315
35,001 to 150,000N500
150,001 to 500,000P800
500,001 and overQ1,250

In the example, a lot of 1,200 valve bodies gives code J and a sample of 80. At AQL 1.0 for major defects the lot is accepted with 2 or fewer and rejected at 3; at AQL 2.5 for minor defects, accepted at 5 and rejected at 6. One major and three minor defects were found, so the lot is accepted. The 4 defects in 80 pieces are 5 defects per hundred units in the sample. Critical defects are set at zero by company rule, not from the AQL table.

For each dimension the template works out the margin: the distance from the worst reading to the nearest limit. The bore's highest reading is 18.04 mm against an upper limit of 18.05 mm, a margin of 0.01 mm. That is a pass, but a thin one, and worth showing the supplier before it becomes a reject.

How to fill in the inspection report

  1. Open the last report for the area first, and check whether its open actions were really closed.
  2. Walk the checklist in order, and write every finding on the spot with a photo reference. Don't trust memory for the afternoon write-up.
  3. Score likelihood and severity for each finding with the person who works there; they know how often the hazard is met.
  4. Stop or lock out anything that could hurt someone today, and write that down as an immediate action.
  5. Give every finding an owner who agreed to it and a realistic due date.
  6. Fill the summary: items checked, findings, the score and the high risk count. Compare it with last month.
  7. Sign, share it with the area supervisor the same day, and follow up on the due dates, not at the next inspection.

Common mistakes on inspection reports

  • A checklist of ticks with no findings written out, so nobody can tell what was wrong or check that it was fixed.
  • Findings with no owner or due date. The same item reappears on every report.
  • Inspecting the same route at the same time every month, so the night shift and the yard are never seen.
  • Using a fixed sample ("5 pieces") for quality checks instead of sizing it from the lot and the AQL.
  • Accepting a lot with a critical defect because the total count was under the major Ac number.
  • Changing the risk matrix between reports, so scores can't be compared.

Emplotec Quality

Or inspect on a phone and let the findings chase themselves.

In Emplotec Quality the checklist for the area or the part opens on the inspector's phone. Findings become actions with owners and dates, and a quality inspection holds the stock in QC until the result releases it.

  • Mobile checklists for safety inspections and floor walks, kept with incidents, near misses and hazard assessments.
  • Inspection plans with AQL sampling for incoming, in-process, first-off and final checks, with stock held in QC until released.
  • A gauge past its calibration date is blocked from the inspection.
  • Corrective actions run as CAPA with a root cause and an effectiveness check, each with an owner and a due date.
InspectionsTacoma distribution center · November 2026
Open findingsDue this weekCompletedChecklistsStart inspectionExport report
EmplotecINS-26-0412 raised 5 findings. Dock 7 stays locked out until the vendor repair on Nov 21.
Inspection score92.19%
Findings open8
High risk open1
Closed on time86%
Findings from INS-26-0412
No.FindingRiskOwnerStatus
1Dock 7 leveler lip hinge crackedLocked and tagged out12FacilitiesVendor Nov 21
4Pothole in forklift pathTrailer spot 229FacilitiesOpen
2Extinguisher tag not initialedDock 46J. BrandtClosed
3Eyewash log missingBattery room8MaintenanceClosed
Recent
  • L. Okafor completed the monthly walk, 64 items, 5 findings
  • J. Brandt closed the extinguisher finding with a photo
  • Facilities booked the leveler vendor for Nov 21

Emplotec Spot 22's pothole is the third yard surface finding since August. Raise one work order to patch the whole forklift route instead of each hole?

INS-26-0412INS-26-0298
Raise work order

The distribution center's monthly inspection, with two findings escalated and two closed the same day. Example companies, people and figures.

Questions people ask about the inspection report format

What should an inspection report include?

The report number, date, time and area, the type of inspection, the inspector, the checklist or standard used, one line per finding (what was found, its risk, the action, the owner and the due date), a summary, the overall result with any immediate actions, and signatures.

How do you write an inspection report?

Walk the checklist and write each finding on the spot in plain, measurable words, with a photo reference. Score each finding for likelihood and severity, stop anything dangerous immediately, agree an owner and due date for every action, then summarize the result and sign it the same day.

How is the risk score worked out?

Likelihood (1 to 5) times severity (1 to 5), giving 1 to 25. This template treats 10 to 25 as high, 5 to 9 as medium and 1 to 4 as low. Those bands are a company convention, so use your own matrix if you have one and keep it the same every time.

Does OSHA require written inspection reports?

OSHA has no single inspection report form, but many standards require inspections at set intervals: fire extinguishers monthly (1910.157), forklifts before each day's use (1910.178), scaffolds before each shift (1926.451) and jobsites regularly by a competent person (1926.20). A dated, signed report is how you show they were done.

What sample size should I use for a quality inspection?

Use ANSI/ASQ Z1.4: find the code letter from the lot size at general inspection level II, read the sample size, then the Ac and Re numbers for your AQL. A lot of 501 to 1,200 pieces gives code J and a sample of 80; at AQL 1.0 you accept with 2 defects and reject at 3.

Can I use this as a home or building inspection report?

Yes, as a record of condition: one line per room or system, what was found, the photo reference, the repair, who is responsible and when. A licensed home inspection for a sale follows your state's standards of practice and report rules, so check those if you are a licensed inspector.

Sources

  1. 29 CFR 1910.157, portable fire extinguishershttps://www.law.cornell.edu/cfr/text/29/1910.157
  2. 29 CFR 1910.178, powered industrial truckshttps://www.law.cornell.edu/cfr/text/29/1910.178
  3. 29 CFR 1910.184, slingshttps://www.law.cornell.edu/cfr/text/29/1910.184
  4. 29 CFR 1926.20, general safety and health provisions (construction)https://www.law.cornell.edu/cfr/text/29/1926.20
  5. 29 CFR 1926.451, scaffolds: general requirementshttps://www.law.cornell.edu/cfr/text/29/1926.451
  6. OSHA: Recommended Practices, hazard identification and assessmenthttps://www.osha.gov/safety-management/hazard-Identification
  7. ASQ: ANSI/ASQ Z1.4, sampling procedures and tables for inspection by attributeshttps://asq.org/quality-press/display-item?item=T964
  8. ISO 9001:2015, quality management systems: requirementshttps://www.iso.org/standard/62085.html