Bar bending schedule format (BBS) to IS 2502, with cutting lengths and steel weight

A bar bending schedule lists every reinforcement bar in a member: its mark, diameter, shape, cutting length, number and weight. This one works out the totals and the weight for you. Fill it in on the page, or download Excel.

  • Schedule columns from IS 2502, Table I
  • Weight by d²/162 kg per metre
  • Stirrup and crank bar workings
  • A4 landscape, Excel with formulas

Written for India. Elsewhere:BS 8666 bar bending schedule format UAE

Last updated

Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.

Site copy
Bar bending schedule

All dimensions in mm unless stated. Cutting lengths to the next whole 25 mm.

Schedule

Bar markMember and locationShapeBending dimensionsDia mmNo. of membersBars in eachTotal barsCutting length mmTotal length mWeight kg (d²/162 per m)
Total

Working: cutting length of stirrup B1-04

Beam width, mm
Beam depth, mm
Clear cover, mm
Stirrup bar diameter, mm
Hook extension each end, mm (as drawn; IS 2502 asks for at least 8d)
A, out-to-out width (b minus 2 covers)
B, out-to-out depth (D minus 2 covers)
Bend deductions: three 90° at 2d, two 135° at 3d
Cutting length = 2(A + B) + 2 extensions minus deductions, mm

Working: cutting length of cranked slab bar S5-01

Bar length end to end, mm
Slab thickness, mm
Clear cover top and bottom, mm
Bar diameter, mm
H, height of crank (slab minus 2 covers minus 1 dia)
Extra length for two 45° cranks, 2 x 0.42H
Bend deductions: four 45° bends at 1d
Cutting length, mm

Steel to order

Total weight in this schedule, kg
Wastage allowed, %
Steel to order, kg
Steel to order, tonnes

Notes

Laps as per IS 456 clause 26.2.5, staggered. Tie bundles with a label giving the bar mark, this BBS number and the position. Check the schedule against the latest drawing revision before cutting.

Prepared by (site engineer)
Checked by (QS or structural)
Approved by (PMC or consultant)

What a bar bending schedule is

A bar bending schedule (BBS) is the list of every reinforcement bar in a member, taken from the structural drawing: the bar mark, the diameter, the shape and its bending dimensions, the cutting length, how many are needed and what they weigh. The bar bender cuts and bends from it, the site engineer checks fixing against it, and the quantity surveyor uses its weights for steel ordering, reconciliation and billing.

In India the schedule follows IS 2502:1963, the code of practice for bending and fixing of bars for concrete reinforcement (reaffirmed since). Its Table I sets the standard form: location, bar mark, size and type, number of members, number in each, total number, length and shape with dimensions. The format above keeps those columns and adds the total length and weight.

What each column of the BBS format means

ColumnWhat to write
Bar markA short, unique identifier that goes on the bundle label, such as B1-04 for the fourth bar type in beam B1.
Member and locationThe member and where in it: bottom main, top, extra, stirrups with spacing, slab main or distribution.
ShapeThe shape from IS 2502 Tables III to IX (straight, L, U, cranked, closed link) or a sketch with dimensions.
Bending dimensionsThe dimensions the bender sets, measured as IS 2502 shows for that shape. Mark outside (OD) or inside (ID) dimensions where there could be doubt.
DiaNominal diameter in mm: 8, 10, 12, 16, 20, 25, 32.
No. of members and bars in eachHow many identical members and how many of this bar in each. The sheet multiplies them.
Cutting lengthThe straight length of bar to cut, rounded up to the next whole 25 mm as IS 2502 clause 5.1.1 asks.
Total length and weightTotal bars times cutting length, and that length times the unit weight d²/162 kg per metre.

Unit weight of steel bars: why d²/162

Steel weighs 7,850 kg per cubic metre. A bar of diameter d mm has a cross-section of π d² / 4 mm², so one metre of it weighs 7,850 × π d² / 4 / 1,000,000 kg, which is d² / 162.2. Sites round it to d² / 162. The nominal masses in IS 1786 come from the same density, so the shortcut agrees with them to within about 0.2%.

Weights for checking the schedule and steel orders. Billing is usually on the weight worked out this way, not on the weighbridge figure; check your contract.
Diameter, mmkg per metre (d²/162)kg per 12 m bar
80.3954.74
100.6177.41
120.88910.67
161.58018.96
202.46929.63
253.85846.30
284.84058.07
326.32175.85

Hook and bend allowances in IS 2502

IS 2502 bends anchorage hooks and bends round an internal radius of k times the bar diameter, and gives the length each adds to the bar as a hook allowance (H) and a bend allowance (B) in Table II. Each is rounded to the nearest 5 mm, with a minimum of 75 mm.

IS 2502:1963, Fig. 1 and Table II. The standard hook also has a straight length of at least 4d beyond the bend.
k (internal radius = k × d)Bars it was written forHook allowance HBend allowance B
2Mild steel bars9d5d
3Medium tensile steel bars11d5.5d
4Cold-worked bars to IS 178613d6d
6Cold-worked bars above 25 mm (recommended)17d7d

For stirrups, binders and links, IS 2502 clause 3.3 asks for a straight length beyond the end of the curve of at least eight times the bar diameter: 64 mm for an 8 mm stirrup.

How to calculate cutting length

Cutting length is the length of straight bar that, once bent, gives the shape on the drawing. Bending stretches the outside of the bar, so the sum of the out-to-out dimensions is longer than the bar you need. Site engineers in India commonly deduct, for each bend: 1d for 45°, 2d for 90° and 3d for 135°. These deductions are a site convention, not figures from IS 2502; use your consultant's values where the specification gives them.

The cut lengths are rounded up to the next whole 25 mm, as IS 2502 clause 5.1.1 asks.
BarFormulaExample
StraightLength as drawnB1-02: 3,000 mm
L at both endsA + 2B minus two 90° deductions (2 × 2d)B1-01, 16 mm: 4,380 + 600 − 64 = 4,916, cut 4,925
Closed stirrup with 135° hooks2(A + B) + 2 extensions minus 3 × 2d minus 2 × 3dB1-04, 8 mm: 1,160 + 150 − 96 = 1,214, cut 1,225
Cranked slab barLength + 2 × 0.42H minus 4 × 1dS5-01, 10 mm: 3,460 + 84 − 40 = 3,504, cut 3,525

The 0.42 comes from the geometry of a 45° crank of height H: the sloping length is 1.414H against a horizontal run of H, so each crank adds 0.414H, rounded to 0.42H. The number of stirrups is the length to be covered divided by the spacing, plus one: 4,380 / 150 = 29.2, so 30 spaces and 31 stirrups.

Lap length and development length to IS 456

Bars longer than the stock length (usually 12 m) are lapped. IS 456:2000 clause 26.2.5.1 sets the lap length in flexural tension at the development length Ld or 30 times the diameter, whichever is greater; in direct tension, twice Ld or 30d; in compression, Ld in compression or 24d. Ld is worked out in clause 26.2.1 as φσs / (4τbd), with σs = 0.87 fy and the design bond stress τbd from clause 26.2.1.1, increased by 60% for deformed bars.

Development length Ld in tension for deformed bars to IS 1786, worked out from IS 456 clause 26.2.1 (τbd 1.2, 1.4 and 1.5 N/mm² for M20, M25 and M30, times 1.6). Round up on the drawing; the designer's figure governs.
Steel gradeM20M25M30
Fe 41547.0d40.3d37.6d
Fe 50056.6d48.5d45.3d
Fe 55062.3d53.4d49.8d

How to prepare a BBS from the drawing

  1. Take the latest structural drawing revision and write its number and revision in the header.
  2. Go member by member. For each bar type, give it a mark, and note the diameter, shape and bending dimensions from the drawing and the section details.
  3. Work out the bending dimensions from the member size and the clear cover, then the cutting length with the bend deductions and hooks, rounded up to the next 25 mm.
  4. Count bars in each member, including stirrups from the spacing, and the number of identical members.
  5. The sheet works out total bars, total length and weight. Check the total weight against the BOQ quantity for that item.
  6. Get it checked by the QS or the structural engineer and approved before the bar bender starts cutting.
  7. Plan cutting from 12 m bars to keep offcuts short, and issue steel to the bar bender against the schedule.

Common mistakes in bar bending schedules

  • Working from an old drawing revision, so bars are cut to a superseded detail.
  • Using out-to-out dimensions as the cutting length, without bend deductions. Every stirrup comes out too long and will not fit inside the cover.
  • Forgetting the extra stirrup at the end (spacing count plus one) or the laps on long bars.
  • Unit weight rounded to two places: 0.40 kg for 8 mm instead of 0.395 is 1.3% too heavy, which adds up to tonnes on the stirrups of a large building.
  • No bar mark on the bundles, so bars for different members are mixed up at the fixing location.

Emplotec Projects

Or issue steel against the schedule, and see wastage the day it happens.

In Emplotec Projects steel received at the site store is issued to the bar-bending crew against the bar bending schedule, so every tonne is tracked to a member. Steel issued is reconciled against the schedule and the BOQ, with a wastage limit.

  • Material is reconciled against the BOQ's coefficients and the bar bending schedule, with wastage limits.
  • Free-issue steel used past the limit is recovered on the subcontractor's RA bill.
  • Site stores record steel received with the mill's test certificate and issued to each crew.
  • Steel fixed is entered in the daily progress report against the BOQ item, on mobile, offline if the site has no signal.
Steel reconciliation · Block CMedvista Hospitals · up to 9 Nov · theory from the bar bending schedule
By diameterBy memberIssuesOpen BBSExport
Over limitSteel issued is 6.5% above the bar bending schedule against a 3% limit.
Per BBS412.0tRev 4, work done
Issued438.6tFrom site store
Wastage6.5%Limit 3%
Past the limit14.2tRecoverable
By diameter
BarBBSIssuedWastage
8 mm48.2 t50.1 t3.9%
12 mm96.5 t99.0 t2.6%
16 mm142.8 t155.3 t8.8%
25 mm124.5 t134.2 t7.8%
Schedule
  • BBS rev 4 on drawing rev 3
  • Checked by QS
  • Approved by PMC
  • Offcuts measured this weekDue Sat

Emplotec 16 mm and 25 mm account for 22.2 t of the 26.6 t over the schedule. Clause 11 of Venkata Rebar Works' work order allows recovery past 3%. Add the 14.2 t to their next RA bill as a recovery?

BBS rev 4Issue slipsWO-SUB-118 clause 11
Draft the recovery

Steel issued against the bar bending schedule for one block, by diameter, with wastage against the limit. Example companies, people and figures.

Questions people ask about the bar bending schedule format

What is a bar bending schedule?

The list of every reinforcement bar in a member: bar mark, diameter, shape, bending dimensions, cutting length, number and weight. It is prepared from the structural drawing and used for cutting, bending, fixing, ordering steel and billing.

Which IS code is used for bar bending schedules?

IS 2502:1963, the code of practice for bending and fixing of bars for concrete reinforcement. It gives the standard schedule form, shapes, hook and bend allowances and tolerances. Laps and development lengths come from IS 456:2000, and bar grades from IS 1786.

Why is steel weight calculated as d²/162?

Steel weighs 7,850 kg per cubic metre, so one metre of a bar of diameter d mm weighs 7,850 × π d² / 4 / 1,000,000 kg, which is d² / 162.2. A 12 mm bar weighs 144 / 162 = 0.889 kg per metre.

How do I calculate the cutting length of a stirrup?

Take the out-to-out dimensions (member size minus twice the clear cover), add twice the hook extension, and deduct for the bends: commonly 2d for each 90° bend and 3d for each 135° hook bend. A 230 by 450 beam with 25 mm cover, 8 mm stirrups and 75 mm extensions gives 1,214 mm, cut at 1,225.

What are the bend deductions for 45°, 90° and 135° bends?

Site engineers in India commonly deduct 1d for a 45° bend, 2d for 90° and 3d for 135°, where d is the bar diameter. These are site conventions rather than figures from IS 2502, so use your consultant's values where the specification gives them.

How much steel wastage is allowed?

It is set by the contract or the work order, often a few percent for cutting wastage. The schedule gives the theoretical weight; the difference between steel issued and the schedule is the wastage to compare with the limit.