Free templateProduction and quality
8D report template from D0 to D8, with containment and validation worked out
An 8D report is the eight-discipline record of solving a customer problem: team, problem, containment, root cause, corrective action, validation, prevention and closure. This template works out the containment results and the before-and-after defect rate for you.
- D0 to D8, Ford Global 8D order
- Occurrence and escape root causes
- Containment and PPM worked out
- IATF 16949 10.2.3 and 10.2.4
Written for US. Elsewhere:8D report format India
Last updated
Fill it in with your own details. Click any highlighted space and type, then print it or save it as a PDF, straight from this page. Nothing you type leaves your browser.
Status: open, contained, closed
D0: Prepare and emergency response
D1: Team
D2: Problem description, is
Is not
D3: Interim containment (100% sort of suspect stock)
| Location | Suspect qty | Sorted | Rejected | Reject % | Sorted by |
|---|---|---|---|---|---|
| Total |
Containment result
| Parts sorted | |
|---|---|
| Parts rejected | |
| Reject rate in suspect stock (%) |
D4: Root causes (occurrence and escape)
D5 and D6: Permanent corrective actions, verified and validated
| No. | Action | Cause | Owner | Done | Verification |
|---|---|---|---|---|---|
D6: Validation (defects at the customer, per million parts)
| Parts shipped before | |
|---|---|
| Defects before | |
| Defects per million before | |
| Parts shipped after | |
| Defects after | |
| Defects per million after |
D7: Prevent recurrence
D8: Closure and recognition
Customer complaint, status: closed
D0: Prepare and emergency response
Customer found sharp burrs on the slot edge of BR-4471 brackets at assembly; one operator cut through a glove, no injury. 8D accepted the same day. Emergency response: customer notified of the containment plan within 24 hours; all stock at our plant, in transit and at the customer put on hold.
D1: Team
A. Novak (quality, leader); M. Reyes (press shop supervisor); J. Kim (tool room); L. Hart (process engineer); S. Patel (customer quality, Bluegrass Seating). Champion: R. Delgado.
D2: Problem description, is
Is not
D3: Interim containment (100% sort of suspect stock)
| Location | Suspect qty | Sorted | Rejected | Reject % | Sorted by |
|---|---|---|---|---|---|
| 0.78 | |||||
| 0.33 | |||||
| 0.45 | |||||
| 0.42 | |||||
| Total | 11,400 | 11,400 | 54 |
Containment result
| Parts sorted | |
|---|---|
| Parts rejected | |
| Reject rate in suspect stock (%) | 0.47% |
D4: Root causes (occurrence and escape)
Occurrence: punch-to-die clearance on die D-4471-02 had grown to 14% of material thickness after a punch was resharpened on 08/23 without shimming; burrs form above about 10%. Escape: the in-process check measured slot width only; the burr check was visual, once per coil. Both causes verified by turning them on and off: shimmed die, no burrs in 500 hits; worn condition reproduced burrs on a trial run.
D5 and D6: Permanent corrective actions, verified and validated
| No. | Action | Cause | Owner | Done | Verification |
|---|---|---|---|---|---|
D6: Validation (defects at the customer, per million parts)
| Parts shipped, 3 months before | |
|---|---|
| Defects found by the customer, before | |
| Defects per million before | 437.50 |
| Parts shipped, 3 months after | |
| Defects found by the customer, after | |
| Defects per million after | 0 |
D7: Prevent recurrence
PFMEA for the slot piercing operation updated (occurrence and detection re-rated); control plan rev. E adds the burr gauge check. Die maintenance standard changed for all 38 progressive dies, not only D-4471-02. Lesson shared with the Lansing plant. Same risk checked on 3 similar brackets: clearance records added.
D8: Closure and recognition
Customer accepted the 8D on 12/04/2026 after 3 months and 104,000 parts with no defect. Team thanked at the December plant meeting; die card practice adopted as the plant standard.
Example entries. Go back to blank to fill in your own.
What an 8D report is
8D (eight disciplines) is a team method for solving a problem that has reached a customer, and the 8D report is its record. Ford built its Global 8D on the method, and automotive customers, then aerospace, electronics and medical device makers, now ask suppliers for an 8D whenever they raise a complaint. The report shows the customer that you contained the problem fast, found the real causes and changed your system so it doesn't come back.
| Discipline | What you do | What the customer looks for |
|---|---|---|
| D0 Prepare and emergency response | Decide an 8D is needed; protect the customer straight away | A quick, honest first response |
| D1 Team | A small cross-functional team with a champion who can approve changes | The people who know the process, not only quality |
| D2 Problem description | What, where, when and how many, as is and is not | Facts and numbers, no causes yet |
| D3 Interim containment | Sort, hold or replace suspect stock everywhere it could be | Every location covered, with results |
| D4 Root causes | Why it happened (occurrence) and why it wasn't caught (escape), verified | Causes proven by turning them on and off |
| D5 Permanent corrective actions | Choose actions for each root cause and verify they work | An action per cause, including the escape |
| D6 Implement and validate | Put the actions in place, remove containment, prove it with data | A before and after rate over a fair period |
| D7 Prevent recurrence | Change the systems: PFMEA, control plan, standards, similar parts | The fix spread beyond this part |
| D8 Closure and recognition | Close with the customer; thank the team | The customer's acceptance |
D2: describing the problem with is and is not
The is and is not comparison narrows the search before anyone guesses at a cause. For each question (what, where, when, how many) write what the problem is and what it could be but is not. Each difference points at something that changed. In the example, burrs appear on the slot but not the holes, on die D-4471-02 but not the spare die, and only in lots after 08/24: the slot punch on that die, changed on or about that date, is the place to look.
D3: containment, and how the template works it out
Containment protects the customer while you find the cause. List every place suspect stock can be: the customer's line and warehouse, in transit, your finished goods and work in process. Record the suspect quantity, how many were sorted, how many failed and who sorted. The template works out the reject rate per location and overall:
| Location | Sorted | Rejected | Reject % |
|---|---|---|---|
| Customer line | 1,800 | 14 | 0.78% |
| In transit | 2,400 | 8 | 0.33% |
| Finished goods | 6,000 | 27 | 0.45% |
| Work in process | 1,200 | 5 | 0.42% |
| Total | 11,400 | 54 | 0.47% |
D4: occurrence and escape root causes
An 8D needs two root causes. The occurrence cause is why the defect was made. The escape cause (Ford calls the point where it should have been caught the escape point) is why your controls let it reach the customer. Fixing only the occurrence leaves the next new defect free to escape the same way.
Verify each cause before acting on it: show the problem appears when the cause is present and disappears when it is removed. Use 5 whys, a fishbone diagram or a fault tree to find candidates, and data to confirm them. IATF 16949 clause 10.2.3 requires a documented problem-solving process covering root cause analysis, systemic corrective actions and verification of their effectiveness, and 10.2.4 asks for error-proofing where it fits.
D6: validating the fix with data
Compare the defect rate before and after over periods long enough to mean something. In the example the customer found 42 defects in 96,000 parts in the three months before the fix: 42 / 96,000 x 1,000,000 = 437.5 defects per million. In the three months after, 0 in 104,000 parts: 0 per million. The template works both out from the four inputs.
How to fill in the 8D report template
- Open the 8D with the customer's reference and answer D0 the same day: what you did to protect them.
- Name the team and the champion.
- Write D2 with facts only, using is and is not.
- Contain everywhere, record the sort results, and send the customer the D3 results; many customers want them within 24 to 48 hours.
- Find and verify both root causes in D4.
- List the corrective actions against each cause, with owners, dates and how each was verified.
- Enter the before and after quantities for D6 validation; the template works out the rates.
- Record the D7 system changes: PFMEA, control plan, standards and similar parts. Close with the customer in D8.
Common reasons customers reject an 8D
- Root cause given as "operator error" or "human error", with retraining as the action.
- Only the occurrence cause addressed; nothing on why the defect escaped.
- Containment that missed stock in transit or at the customer's other plants.
- D6 with no data, or validated over a few days.
- D7 left blank, so the same failure appears on a sister part.
- The report written by quality alone after the fact, not by the team.
Emplotec Quality
Or build the 8D from the records you already have.
In Emplotec the customer complaint is linked to the dispatch it came from, so the affected lots, stock locations and quantities are on the 8D from the start. The root cause, actions and the PFMEA and control plan changes stay on the part's record.
- Customer complaints are linked to the dispatch and to Quality, with the customer's rejection debits on the same record.
- NCR, CAPA with root cause and an effectiveness check, and 8D for customer complaints.
- PFMEA (AIAG-VDA), control plans and PPAP packs live with the part, so D7 updates them in place.
- Every heat and batch is traced from the gate to the customer, so containment starts from a list, not a search.
- J. Kim logged clearance on the die card after resharpen
- M. Reyes burr gauge checks, 21 of 21 recorded
- L. Hart control plan rev. E released
Emplotec Three other progressive dies were resharpened in the last 60 days without a clearance record. Add them to D7 and schedule checks?
8D-26-017Die maintenance log8D-26-017 at validation, with containment results by location and the control plan change linked. Example companies, people and figures.
Questions people ask about the 8D report format
What are the 8 disciplines of an 8D report?
D0 prepare and emergency response, D1 form the team, D2 describe the problem, D3 interim containment, D4 root causes (occurrence and escape), D5 choose and verify permanent corrective actions, D6 implement and validate them, D7 prevent recurrence, and D8 close and recognize the team. D0 was added in Ford's Global 8D.
What is the difference between an 8D and a CAPA?
A CAPA is the quality system's general process for corrective and preventive action. An 8D is one structured, team-based way of doing the corrective action, used mostly for customer complaints. Many companies open a CAPA and attach the 8D as its investigation.
How long should an 8D take?
Customers set their own deadlines. A common pattern is containment (D3) within 24 to 48 hours, root cause and planned actions (D4 and D5) within a couple of weeks, and closure after validation. Use your customer's requirements manual.
What is an escape point in 8D?
The point in the process where the defect should have been detected but wasn't. The 8D finds the root cause of the escape as well as of the occurrence, so the controls are fixed along with the process.
Is 8D required by IATF 16949?
IATF 16949 doesn't name 8D, but clause 10.2.3 requires a documented problem-solving process covering containment, root cause analysis, systemic corrective actions and verification of their effectiveness. Many automotive customers require the 8D format in their supplier manuals.
How do you validate an 8D corrective action?
Compare the defect rate before and after over an agreed period. In this template's example, customer defects fell from 437.5 per million (42 in 96,000) to 0 in 104,000 parts over three months, and the customer accepted the 8D.
Sources
- ASQ: Eight disciplines (8D) problem solvinghttps://asq.org/quality-resources/eight-disciplines-8d
- IATF: IATF 16949:2016 and sanctioned interpretationshttps://www.iatfglobaloversight.org/iatf-169492016/about/
- AIAG: CQI-20 Effective Problem Solvinghttps://www.aiag.org/quality/automotive-core-tools